LINOIS POLLUTION CONTROL BOARD
June
6,
1974
CPC INTERNATIONAL, INC.
PETITIONER
)
v.
)
PCB 74-23
ENVIRONMENTAL PROTECTION AGENCY
)
RESPONDENT
)
)
MR. JAMES N. GLADDEN, JR., ATTORNEY,
in
behalf of CPC INTERNATIONAL,
INC.
MR~, JOHN PALINCSAR, ATTORNEY,
in behalf
of the ENVIRONMENTAL PRO—
TECTION AGENCY
OPINION
AND ORDER
OF
THE BOARD (by
Mr.
Dumelle)
Corn Products Corporation, Incorporated (CPC) filed a Variance
Petition on January 18, 1974~ On
March
11, 1974, Petitioner filed
an Amended Variance Petition and a Waiver of the 90—day decision
period. The Agency filed a Recommendation on April 30, l974~ No
hearing was held.
Petitioner operates a wet corn milling plant located in Pekin,
Tazewell County, Illinois. Petitioner seeks a variance from the
compliance program requirements of Rule 401 Ce), and the particul—
ate emission compliance dates established by Rule 203 (i) (4) and
SO2 compliance dates established by Rule 204
(a)
(1) (A) of the
Air Pollution Regulations. The Agency recommends the granting of
the variatce which would enable CPC to revise its compliance program
and project completion schedule for one of three coal-fired toilers
for the generation of process steam and in—plant electrical powers
The Agency filed an enforcement action against CPC
-in October of
1971 after receiving a petition signed by approximately 200 resi-
dents of the Pekin area alleging that CPC was a source of air pollu-
tion. The Board found CPC to have violated Section 9
(a) of the
Illinois Environmental Protection Act and Rule 3-3.112 of the Rules
and Regulations Governing Air Pollution (EPA v.CPC, International,
Inc., PCB 71-338, 5-541 (October 3, 1972)
).
The Board ord~
that CPC burn low ash-high heating coalin order to assurecon~li-
ance with the appl.icable air pollution particulate limitation of
0.6 lbs. per million Btu from Boiler~Cand ordered CPC to pay a
penalty of $15,000 (EPA v, CPC, International, Inc., supra at 5—546)~
Boiler C is the subj~ the present varIance petition, The Agency
—2—
granted CPC an operating permit for Boiler C on March 9, 1973, contin-
gent upon
CPC’s
compliance program and project completion schedule
which indicated the installation of an electrostatic precipitator
and
the use of low sulfur coal to comply with Rule 203 (i) (4) and 204
Cc) (1) (A) of the Air Pollution Regulations.
CPC entered into a contract with American Standard, Inc.,
Air
Qual-
ity Division of Dearborn, Michigan, to design and install an electro-
static precipitator, O?t November, 1973, American Standard, Inc.,
notified CPC that~~it would no longer desi,gn and install electrostatic
precipitators. However, American Standard, Inc., guaranteed it would
honor CPC’s existing order, including erection and maintenance. CPC
notified American Standard to cancel the contract because CPC felt it
was “essential to have technical. support people from the supplier of equip
ment as technically complex as electrostatic precipitators.” The Agency
agrees that CPC’s reluctance
to
complete the contract for the installa-
tion of electrostatic precipitators with American Standard, Inc., should
not be construed as a self-imposed hardship.
CPC entered into negotiations with Freeman Coal Company which were
to
lead to a long-term contract to supply CPC~sfacility with coal from one
of Freeman Coal Company~ssouthern Illinois mines which was being
equipped with coal preparation facilities. Freeman predicted that coal
with a sulfur content of 1.09 and a Btu rating of 12,100 Btu per pound
could be supplied in a sufficient quantity to meet CPC’s total coal re-
quirements. By August of 1973, Freeman began supplying CPC with coal
with the following characteristics: 1.25 sulfur; and 11,800 Btu per
pound. Therefore CPC determined that it would have to blend coal with
a lower sulfur content in order to still meet the SO2 standard while
using 75 mixture of the Freeman coal.
However, Freeman Coal Company then notified CPC that it would not
and
could not supply all of CPC~sneeds and would not negotiate a
long-term commitment.
In
February, 1974, CPC began burning only coal
from Orient #3 mine from Freeman Coal Company in Boiler C which
was
low
in ash content and had a sulfur content
of
less than 1.25 as opposed
to
previously burned coal with a
sulfur content of approximately
3.
While
this was not required by Pollution
Control
Board~sAir Regulations, CPC
alleged that coal supply negotiations indicate that this action is nec-
essary in order to establish a claim in the future
of
the limited supply
of low sulfur coal available in Illinois, This has had a result in in-
creasing the price per ton from $11.04 to $15.78 per ton.
Because of the coal supply situation and the
cancelling
of the
e1ectro~
static precipitator contract, CPC has determined that its present compli-
ance program no longer appears capable of achieving compliance. CPC
states that by April 15, 1974, it will have been presented an in-depth
engineering study evaluating five alternative means of control. Three
of the five alter~tives (sodium scrubber, water scrubber, and electro-
static precipitators) would result in compliance by August, 1976, Two
other alternatives (double alkaline scrubber and lime scrubber) would re-
sult in compliance by November, 1976. The Agency states that ~petitioner
has now
limited its choice of control systems to two alternatives.
The
fi~aldecision on control systems will be made when all bids of these two
systems have been received,”
12—482
—3—
CPC alleges that the granting of the variance would not have an
unduly negative impact on the environment in the Pekin area.
CPC
estim~tes that it will contribute 0.54 micrograms per cubic meter
(ug/m~) to the primary ambient air quality standard of 75 ug/m3 an--
nual geographic means for particulates. CPC also estimates an addi-
tion of 0.35 ug/m3 addition to the annual average ambient SO2 air
quality standard of 80 ug/m3. In addition, CPC estimates an increase
in the peak 24 hour contribution of 1.08 ug/m3 for particulates
and
0.7 ug/m3 for SO9. This would be in excess of the peak 24 hour con-
centration if CP~s facility was in compliance with applicable regu-
lations as of May 30, 1975.
While agreeing that a variance should be granted, the Agency dis-
agrees with CPC’s estimates as to particulates
and
502 contributions.
As the Agency points out, CPC’s facility is located in a standard met-
ropolitan statistical area. Values contained in the operating permit
application for Boiler C list its emissions as 5.34 lbs. per million
Btu’s for SO2 and 3.76 lbs. per million Btu~sfor particulates. CPC
claims the existing multiclone collectors have an efficiency of 92.5
particulate removal. The Agency asserts the maximum acceptable effic-
iency of multiclone collectors systems is 75. The Agency calculates
CPC’s particulate emissions to be 2.08 lbs. per million Btu’s. The
Agency presented the following calculations for air contaminant emiss-
ions from CPC’s facility:
particulates 1682 lbs. per hour
SO9
—
2500 lbs. per hour
hyarocarbons
-
7.4 lbs. per hour
CO
-
24.2 lbs. per hour
NO~
-
589 lbs. per hour
ambientIn
contrastair
qualityto
thevaluesestimatedpresentedcontributionsby
CPC, theto Agencyparticulatesubmittedand
SO2
calculated contributions to ambient air quality for varius meteorol-
ogical conditions from the CPC facility. These were attached to the
Agency~s recommendation as Exhibit A. However, this Agency exhibit
lists the calculated contributions
for the entire CPC facility while
the values presented by CPC apply only to Boiler C~semissions.
The Board finds that because of CPC~sdemonstrated good faith in
complying with air pollution regulations in previous Board Order PCB
71-338, that the variance requested by CPC is reasonable, The envir-
onmental consequences of
this
delayed compliance from
12-15
months do
not warrant a denial of the request based upon
the estimated
contribu-
tions resulting from
this facility during the non-compliance period
and the calculated emissions for
all
of CPC~s
Pekin facilities. How—
ever,
the Board is limited
by Section 36 (b) of the Environmental Pro--
tection Act to only grant one-year variances from Air Pollution Regu—
lations~ Therefore the Board will grant a variance from Rule 104 (e)
in order to allow CPC to file a new project completion schedule. Be-
cause of the
one-year
limitation, th~eBoard will grant CPC a variance
from Rule 203 (i) (4) and 204 Cc) (1) (A) from May
30.
1975, the effect~
ive date of these Rules, until June 6, 1975. This short variance would
12—483
—4—
be extendable upon the appropriate showing of continued good faith
in achieving compliance with the particulate and SO2 standards as
outlined in Exhibit G of the Petition for Variance and in the appropri-
ate project completion program filed with the Environmental Protection
Agency.
The Board will also extend variance of Rule 3-3.112 of the Rules and
Regulations Governing Air Pollution until May 30, 1975. This will serve
to
allow Petitioner to operate above the ~limitof the existing rules re-
garding particulates until May 30, 1975, at which time 203 (i) (4) be-
comes effective.
This
Opinion constitutes the Board~s findings of facts and conclu-
sions of law.
ORDER
The Illinois
Pollution
Control Board hereby grants a variance from
Rule
104 Ce) of the
Air Pollution
Regulations to CPC International,
Inc., until July 30, 1974. The Board
hereby grants a variance
to
CPC
International, Inc., f~omRule 3—3.112
until
May 30, 1975, and from
Rules 203
(i)
(4)
and
204 Cc) (1)
(A) of the
Air Pollution Regulations
from May 30, 1975, until June 6, 1975.
These variances are conditioned
upon:
1.
Outlining a compliance program and project completion
schedule with the Environmenta~~~~Protection
Agency by
July 30, :1974, which shall conform
to the timetable
proposed
by CPC Exhibit S.
2.
CPC shall submit quarter19 progress reports to the
Agency at the following address: Environmental Pro-
tection Agency, Division of Air
Pollution Control,
Variance
Section, 2200 Churchill Road,
Springfield,
Ill:Lnois
62706,
3. CPC
shall
post a performance bond in
the
amount of
3100,000 in a form satisfactory
to the Agency, pur—
;~uant to the Illinois Revised
Statute,
Chapter 111
1/2 Section :1036 (1973)
Said performance bond shalL
be
posted
with the Agency at the following address:
Environmental Protection Agency
Division of Air
Pollution
Control, :Depar-tment of
Fiscal
Services,
2200 churchill Road, Springfield, Illinois 62706.
IT IS SO ORDERED.
1. christan B. .Moffett, Clerk of the Illinois Pollution Control
:loari fereby certify that the above Opinion and Order were
adopted
on the
stt
Say of S-~ne :L9 74
~c~y
a vote of 4 to 0
i/O