May
16, 1974
FERGUSON AND LANGE
FOUNDRIES,
INC.,
Petitioner,
)
PCB 74-82
vs.
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
John A.
Cook,
Attorney,
on behalf of Petitioner;
Kathryn
S.
Nesburg, Attorney, on behalf of the Environmental
Protection Agency.
OPINION AND ORDER OF THE: BOARD (by Mr. Seaman):
The Petitioner
is
Ferguson and
Lange Foundries,
Inc. (herein-
after Petitioner).
The Petition was filed with the Environmental
Protection Agency (hereinafter Agency)
on March 3, 1974.
This is a Petition for an Extension of the Variance granted
in PCB 73-474.
The Pollution Control Board (hereinafter Board)
granted the Variance from Rules 3-3.111
and 203(a)
until Feb-
ruary 28, 1974.
Petitioner operates
a foundry
in Chicago which produces
grey iron and ductile i~roncastings utilizing
a cupola furnace
which emits particulates and carbon monoxide.
Petitioner entered
into a turn-key contract with Combustion
Equipment Associates,
Inc.
(CEA)
on April
26, 1971
to engineer
and
install control
equipment to limit the particulate
emission
wtthtn the requirements
of the Environmental Protection Act.
Under the terms
of the contract, CEA assumed full responsibility
for all
facets of the job,
including design of equipment and
supervtsion of subcontractors.
On
March 22,
1973, the Board fined Petitioner
$200 for
failure to obtain a construction permit and operating the cupola
in vi’olation of Rule 3-3.111
of the Rules and Regulations
Governing
the Control of Air Pollution (PCB 72-284).
At the same time, the
Board granted Petitioner
a Variance until
March 31, 1973 in order
to continue operation of the cupola
in
an uncontrolled state
(PCB 73-46).
On November 8,
1973, Petitioner again filed
a Petition for
Variance.
The emission control system had been installed but
a design
error by CEA necessitated the replacement of a large motor
12
—
291
—2—
and modification of
a portion of the baghouse filter system.
The Board granted the Variance until
February 28, 1974
(PCB 73—474) after making the finding that the delay was not
caused by Petitioner and that the delay would result
in limited
particulate emissions.
Petitioner requests the variance extension until
April
30,
1974
in order to have time to complete certain finishing work and
adjustments to the system.
Petitioner’s facility is located
in a highly industrial
area.
Measurements of particulates taken at the nearest air
monitoring station (within two miles of the facility) show a
concentration of 132 micrograms
of oarticulates per cubic meter
as compared
to the National Air Quality Standard of 75 micrograms
per cubic meter.
Petitioner has expenüed approximately $140,000 in an attempt
to bring
its facility into compliance by installing
a control
system consisting of a
direct—flame
afterburner,
a baffle chamber,
a water spray quench system,
a cyclone,
and
a positive pressure
daghouse.
The manufacturer of the contrcl
system has guaranteed
the
efficiency
to be 99~9
-
more than
adequate
to
bring
the cupola
into
compliance.
The Agency states
in
its Recommendation to the Board,
“Petitioner
claims
that
CEA
is
primarily
responsible
for
the delay because of
its
failure
to meet
its
contractual
obligations
and
complete the
work
on
time,
Because
of
the nature of Petitioner’s
contract
with
~IE4,
that is, putting CI~Ain
complete
char~geof
design,
planning,
contractino,
and sub-contractina, Petitioner was unable to control
tn~proare~sof
tne
i~~ta~
~at
or
Thus
t
gould
amount
to
an
arotra~y
and
unreasonable hardshic
to
deny
the
Variance
when
the
delay
is
not
toe fauit of Petitioner~ hhiiet
ne
Board
agrees
that
at this period
of oomtdiance
to
deny
a
variance
would
he
arbitrary,
it
cannot
base
Li
e ~~nalna
on
the
Aqency ~ reeson
no
The
D@~
~tionercannot
delegate his
statutory
respons~ihility
to
another
narty.
He
has
~
oh~nator
and
any
)lislde
co~tr1c:u~i
egreernents
cannot rei’eve
him
as
to this Board.
The Agency has
not received any
adverse
citizen
comment with
~esoe~ ~oMe qranL
ci’~
~
ia’~
~roeanc ne
~es that the successfu
comoletion of the installation of control equipment will bring
Petitioner~s
facility into compi
once
us
dpinion constitutes one rindi nbc
01
tact
anb
conc~
us ons or
law of
the Board,
-3—
IT
IS THE ORDER of the Pollution Control
Board:
1.
That the Variance from Rules 3-3.111
and 203(a)
be
granted until
April
30,
1974,
subject to the following conditions:
a.
Within sixty (60)
days of the date of this Order,
the Petitioner shall
have performed a stack test on
the
cupola control
equipment.
Petitioner shall
give five
(5)
days notice of the test to:
Illinois Environmental Protection Agency
Division of Air Pollution Control
Region
II
Office
Illinois Naval
Armory
East Randolph at the Lake
Chicago, Illinois
60602
Telephone:
(312)
793-4966
and allow Agency observation
if required.
Petitioner
shall
submit complete results of the said test to the
Agency at the aforementioned address within thirty (30)
days.
b.
Petitioner shall
apply
all necessary operating
permits
for the facility from the Agency.
I,
Christan
L.
Moffett, Clerk of the Illinois Pollution Control
Board, c~tifythat the above Opinion and Order was adopted on
t
is
/1.
‘1
day of
47p
,
1974 by a vote of
—~
12
—
293