T’XACO fl~C
    (LO ‘KP3RI RFFINFR
    PL~IlIIONER
    ~ a
    coac~
    t~c 3
    ci a
    pet
    t x ~ I~xa~ In
    Va ra e
    ii
    r ~u1e O~
    g
    i a a a aye ~t
    i~
    un~
    ct
    a.
    LO- OOt~
    1
    0
    ,
    Y
    ne
    a Sc
    i
    Pe~iLi
    is ~ ~e a Zuie
    c3~r ~
    ‘~
    3
    a~d
    I~
    Tue Ag n v ~ccommer d~ t.
    g r t
    fecommend t
    i~led
    3
    2
    ,
    7’
    T~e Loc Tort rc ir~r
    It
    has a
    cap
    rackarg
    Jiarge eoct~
    called coas dr~n~
    as aug oae ation waiT o~y
    ore aruir te~ne used ~t a a u~ 1
    o ~‘har o a routed
    a di r
    where rackirci tat
    ~ e~3) of tTc ~ra
    ano ~omc of
    tue c~argc a laid
    OvL
    a Lhe dir
    1h aapo~ pr case t
    the iractionatana
    ow~x for ccpa~at n
    Wher ~e batck is eompl~cd
    LTe drum a~ complete~y ± II of por r ~ohe
    A thas point
    there
    no f rther _np~t iito
    Trur
    vapors a
    £
    stal) goirg off t
    the frac ronating tower fo: p oceslng
    At this
    oiut b1owdo~n f
    the uni~ takes places
    ~.
    yap ~s are erouted t a blowdown k~o Y-~
    out drum
    Steair is ther ~njected
    into the druri to purge the vapors
    from the coke drura~ Then the aag r is water~cooled in the blowdowr~
    quench drums Part of the vapo~ are liquefied and are i~scharged
    to the sewers
    The renai~arg vapor’~ are discharged to the atma
    phere and are the vaporr ar quest o~
    Vapor emissions o~hydrocarooru~ are as foI1ows~ 253~4 lbs/hr.
    -
    13
    301

    31,500 ppm.. The
    limit
    set in Rule 205 (g) (2) is 10 ppm.. Such emiss-
    ions are of a periodic nature, existing only when the unit is being
    blown down..
    The control proposed for these vapor emissions is a knockout pot
    to
    collect and condense the vapors further.. Non-condensable vapors
    will then be routed to a smokeless flare.
    Petitioner~s compliance schedule
    to
    complete installation
    of
    the
    proposed equipment is as follows:
    Jan.. 28,
    1974
    Apply
    for
    IEPA
    construction
    permit
    Feb.. 22,
    1974
    Contract for concrete construction
    to
    be awarded (other construction
    work
    to be done by in—house per-
    sonnel)
    March 15, 1974
    Start construction
    Sept.. 1, 1974
    End construction
    Sept.. 1, 1974
    Start operations
    This project is, estimated to cost $80,000..
    The Board takes notice of the fact that though Rule 205 (g) (2)
    went intc effect on December 31, 1973, a permit ~.oconstruct
    this
    equipment
    was
    not applied for
    until
    January 28, 1974, a month later..
    Nowhere (Ices Petitioner allege any reason for this delay. Attached
    to the Petition is a chart indicating that this project has
    been in
    the
    works since May of 1972. The Board fails to understand why in-
    itiating the construction of this project did not begin until 22
    months after initial consideration was given by Texaco to this pro-
    ject. It appears that there is no new or novel technology being
    used to control this emission source.. This Board cannot speculate
    as to why this project could not have been accelerated to meet
    the
    December 31, 1973, deadline. While there may have been acceptable
    reasons for this delay, the Petition is devoid of such evidence.. It
    is clearly the burden of Petitioner to supply such data, and without
    it the Board must find that Petitioner has failed to establish due
    course for the grant of variance..
    Hardship:
    Petitioner alleged that it would suffer unreasonable and arbitrary
    hardship if this variance is not granted? for the reasons that follow..
    1, It cannot comply with Rule 205 (g) (2) before September 1,
    1974, because of fixed delivery dates from equipment vend-
    ors, beyond Petitioner~s control..
    2. A shutdown of the unit from May
    1,
    1974, until September
    1, 1974, would decrease production by 960,000 barrels of
    gasoline, 678,000 barrels of middle distillate, and 28,320
    tons of coke. Backup in tankage causes a loss of 184,000
    barrels of recovered gas oil. These products would be lost
    to the public and would cost the Petitioner $1,376,322. Pet-
    itioner would have to lay off 22 persons for four months and
    31 persons for one month..
    13— 302

    The hardship case
    thus rests
    on
    th~epossibility of
    an enforcement
    action being filed should Petitioner/fail
    to
    cease operations in vio-
    lation of Rule 205 (g) (2)..
    It must be
    noted that even
    if
    this Board
    were to grant variance, Petitioner
    is
    still liable to enforcement
    for the period of January 1, 1974,
    to
    April 2, 1974 (the date of fil-
    ing of the original variance petition).. This Board cannot help but
    wonder why, if Petitioner is concerned with possible enfOrcement act-
    ion, they waited until April 2, 1974, to file for variance, If the
    project for abatement was initiated in 1972, Petitioner should have
    filed its petition by October 1, 1973, to assure itself total protect-
    ion. Surely Petitioner was aware that
    it
    would not be in compliance
    by December 31, 1973.. Therefore, Petitioner by its own inaction has
    left itself open for enforcement proceedings for a significant per-
    iod of time. In
    light of this the Board’must
    find that Petitioner
    has not met its burden of proof regarding hardship, or even that such
    hardship was not self-imposed.
    Environmental
    Impact:
    Petitioner alleges that there will be no injury to the public from
    the grant of this variance,
    in
    that its emissions do not contribute
    to photochemical smog.. Air monitoring performed for Petitioner
    by
    Air Resources, Inc., taken between November 19, 1973, and December 17,
    1973, showed the following results:
    Ill, ppm
    Pollutant
    Ambient Air
    ~n~~Con~ibution
    Standard
    Oxidants
    0.059
    0,001
    0.08
    NO~
    0.017
    0.001
    0.05
    No data
    is
    presented
    to show how the refinery
    contribution was cal-
    culated,
    Petitioner alleges that
    its discharges will not contribute
    to photo-
    chemical smog.. This conclusion is
    based on tests which show that less
    than five percent of
    its emissions are olefinic compounds. This
    con-
    clusion, however, is not sufficient
    to meet
    the criteria as outlined
    in Chapter 2 of the Board Rules..
    The definition of photochemically
    reactive material includes three distinct categories of organic emiss-
    ions. Petitioner explores only one
    olefinics. There is no mention
    of aromatics of eight carboh
    atoms or
    more,
    or of ethylene, branched
    hydrocarbons, or
    toluene.. ~The
    combination of any
    of the
    above may
    not
    exceed 20, nor can
    the aromatics alone exceed 8 to be considered
    non-photochemically reactive.. Without such data the Board cannot accur-
    atel~assesss the contribution such vapors will add to the potential of
    photochemical smog.
    The Board takes note of the recent high ozone levels in the Chicago
    major metropolitan areas.. As such we must be even more aware that
    photochemical smog can no longer be assumed a potential problem, but
    one which becomes more real as time goes on..
    On April 4 an Agency inspector noted no odors outside the refinery
    boundaries. The refinery is in an industrial area with no residential
    buildings within 1/4 mile of the facility.. The Agency has received
    no citizen complaints..
    13
    303

    OS
    rt~
    ~ mb
    U
    g
    ho So id
    S
    o icasor
    0
    a
    nu~ coral da U
    a
    or:
    fo~ TO
    urar
    a a ~r
    tha
    a a ci as
    are e
    U
    U
    emertal
    ro~ U a
    t
    a or
    d
    P~tm
    i,i
    e
    ~~or
    ~
    Te ar cut
    r
    ~“i
    a ~y
    deq aU o
    ta a’~ ra~e x r giaa
    e t
    t
    3
    to
    d ~ort ose ar
    rru~ Cc
    C
    ci i~
    w le
    ch ate nay ear St at las
    t
    ~e
    do a ~l
    p esented
    t~
    e So r
    TU ‘a~ian e v all cc U
    tl
    U
    o:e
    di e ~o alio
    00t ~ ne to ‘~eir~tiate ~his proceed ro ~r 3
    a a adequate pro
    r ror
    arpose~ delay
    U a
    a
    rIm a
    ~ non cors ~‘t ~
    Ia
    Lb
    lard
    IT IS THE OR~U f tIe So 1 at
    octro
    3oa I
    pel-itior. for
    ~n e ~Ueb
    apra~
    5,
    1951
    .~
    ~
    ~s
    ‘~ —~
    withoU
    prejudice
    1, Chris~an L.. Moffett, Clerk of tIme ~ lano s P Ilution ContoU
    Board, o~rtafy that the above OpanUn a d drder ‘gas adoptea by ~he
    Board on the 8th 3c~y of August, 1 4, by a vot~ f 4 to 0
    13— 304

    Back to top