ILLINOIS POLLUTION CONTROL BOARD
    April 18, 1974
    OLIN CORPORATION
    PETITIONER
    V.
    )
    PCB 74—27
    ENVIRONMENTAL PROTECTION AGENCY
    RESPONDENT
    THOMAS B. MARTIN, ATTORNEY,
    in behalf of OLIN CORPORATION
    RONALD A. LINICK, ATTORNEY,
    in behalf of the ENVIRONMENTAL PROTECTION
    AGENCY
    OPINION AND ORDER OF THE BOARD
    (by Mr. Marder)
    This case comes to the Board on Petition of Olin Corporation,
    filed January 21, 1974,
    requesting variance from Rule 205
    (f)
    of
    Chapter
    2 of the Board’s
    Rules and Regulations.
    On March 21, 1974,
    the Board denied an Agency motion to dismiss
    the Petition.
    On April
    10,
    1974,
    the Agency filed a recommendation, recommend-
    ing the Board grant Petitioner
    a variance for six months, subject
    to certain conditions.
    No hearing was held.
    This variance is requested for Petitioner’s Roll-Bond aluminum
    heat exchange panel operation in East Alton, Illinois.
    The Agency
    has granted
    a permit
    for this operation to the Petitioner.
    The
    permit has as its compliance plan the shifting of all paint formulas
    to “exempt” solvents by December
    31,
    1973.
    Olin worked out a new paint formula ~ith its supplier, the P.D.
    George Co.,
    St. Louis, Missouri.
    A formula was found which proved
    to be acceptable
    on October
    2,
    1973.
    P.D. George then notified
    Olin that it could not obtain one of the solvents for the formula
    (Ethylene Glycci n-I3utyl Ether)
    ,
    because of
    a great shortage of
    supply.
    Olin
    then
    atternoted
    to
    obtain
    the
    solvent
    but
    failed.
    o:Lin
    alleges that the
    solvent
    is
    on
    strict
    allocation
    and
    no
    new customers
    are being allowed
    (Pet.
    p.
    2)
    12
    —93

    —2—
    On October
    30,
    1973,
    Olin submitted a new plan to the Agency,
    ex-~
    tending the time needed for compliance.
    On November 1,
    1973,
    a new paint formula was proven acceptable by
    an on-line test.
    On November
    2,
    1973, P.D. George notified Olin
    that it could obtain the solvents necessary to produce the paint.
    On November 28 Olin submitted a new compliance schedule showing com-
    pliance with Rule
    205
    (f)
    by December 31,
    1973.
    On December 12, 1973, Olin was notified by P.D. George that they
    again couldn~tsupply the paint, this time because isobutyl acetate
    could not he obtained for the resin.
    Again Olin tried to obtain
    this material, but failed because it
    is also on strict allocation.
    However,
    several suppliers indicated that this situation might change
    later in 1974
    (Pet.
    P.
    3)
    Petitioner~soperation
    uses
    about
    7000
    gallons
    of
    paint,
    and
    2000
    gallons
    of
    thinner,
    per
    annum
    (Pet.
    P.
    3,
    Agency
    Rec.
    P.
    1).
    This
    use
    is
    broken
    down
    further to
    3,5
    gallons
    per
    hour
    between
    8
    a.m.
    and
    4
    p.m.
    and
    1.75
    gallons
    per
    hour
    between
    4
    p.m.
    and
    12
    midnight,
    five
    days per week.
    The
    emission
    rate is
    17.7
    lbs.
    ‘per hr.
    during
    the
    day
    and
    8,85
    lbs.
    per
    hr.
    on
    the
    night
    Shift
    (Pet.
    P.
    3, Agency Rec.
    P.
    2)
    .
    This
    is
    above
    the
    allowed 8 lbs.
    per hr.
    in
    Rule 205
    (f).
    The composition of the solvent as presently sprayed is
    as follows:
    Xyloi
    42,4
    ~:wt)
    44.4
    (vol.)
    Toluol
    31,7
    (wt)
    32.4
    (vol.)
    Ethylene Glycol
    Mono Ethyl Ether
    Acetate
    21.1
    (wt)
    18.4
    (vol.)
    Methyl Isobutyl
    Ketone
    4,8
    (wt)
    4.8
    (vol.)
    (Pet,
    p.
    3, Agency Rec.
    P.
    2)
    Petitioner
    alleges and the Agency concurs there is no substantial
    environmental
    impact by
    the
    continued
    emissions.
    There
    is
    no
    Los
    Angeles-type
    ~hotochemica1
    smog in
    the
    area,
    and
    neither
    Petitioner
    nor
    the
    Agency
    has
    received
    any
    complaints
    or
    objections
    to
    the
    con-
    tinuation
    of
    the
    emissions,
    Also,
    the Agency investigation noted no
    odor problem f~omthis operation
    (Pet.
    P.
    5, Agency Rec.
    P.
    3).
    Petitioner alleges
    it would he forced to curtail its Roll-Bond op-
    eration
    if
    it
    is denied a variance.
    In its Petition, Olin
    states
    that
    loss
    to
    itself,
    customers,
    and
    employees
    would
    be
    too
    difficult
    for
    crecise computation, hut
    it
    would
    be
    great.
    Though
    a
    variance
    denial
    is
    not
    a
    shutdown
    order,
    it
    would
    seem
    that
    Olin
    would
    suffer
    a
    card—
    ship
    if
    the
    variance
    was
    deriacu,
    The
    Agency
    also
    states
    that
    PetitiOs
    er
    has
    made
    a
    reasonable
    effort
    to
    comply
    with
    Rule
    205
    (f)
    ,
    but
    has
    not
    neen
    able
    to
    because
    of
    SItuations
    eeyond
    its
    control
    (Agency
    Rec.
    P.
    2).
    The
    Agency
    states
    ttiat
    although
    Olin
    has
    been
    before
    the
    Board
    ~2~94

    —3—
    numerous times on variance cases, there has not been an enforcement
    action filed against it to date.
    Olin proposes a three-pronged approach to bring itself into com-
    pliance with Rule
    205
    (f).
    The first is to develop water—based
    paints.
    The second is
    to develop another solvent paint that would
    use other exempt solvents.
    The third is for Olin to continue to
    look for available isobutyl acetate.
    Olin will be pursuing all of
    these approaches concurrently.
    If
    a water—based paint or
    a new solvent—based paint
    is
    used,
    Olin
    will have to secure mandatory certification of the paint by
    the
    Nat-
    ional Sanitary Foundatiom,
    a proce~sthat takes
    about six months
    (Pet.
    P.
    4).
    The Board finds
    this to be a reasonable compliance plan.
    The Agency has recommended variance for only six months, but be-
    cause of the possible six-months delay Olin will have in getting new
    paint certified, the Board will grant a variance for one year.
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board.
    ORDER
    IT
    IS
    THE
    ORDER
    of
    the
    Pollution
    Control
    Board
    that
    Olin
    Corpora-
    tion
    be
    granted
    a
    variance
    from
    Rule
    205
    (f)
    until
    April
    1,
    1975~ or
    until
    it
    can obtain paints which comply with Rule
    205
    (f)
    ,
    whichever
    is shorter, for its Roll-Bond operation, subject to the following
    conditions:
    a)
    Olin shall follow the
    compliance
    plan
    outlined
    in
    its
    Pet-
    ition
    and
    this
    Opinion;
    b)
    Olin shall use paints with exempt solvents whenever they are
    available;
    c)
    Olin shall submit quarterly reports to the Agency beginning
    July
    1,
    1974, detailing all research done and its status as
    to compliance with Rule 205
    (f)
    IT IS SO ORDERED.
    I, Christan L.
    Moffett, Clerk of the Illinois Pollution Control
    Board, certify that the above Opinion and Order was adopted by the
    Board on the
    /X~”
    day of
    ___________,
    1974,
    by
    a vote of ~
    to
    C
    .
    (~i~
    -
    4.
    ~
    1)
    -~.
    ~
    i
    .~
    ~
    ~
    /, ~
    /
    ‘./~
    ~2
    -95

    Back to top