ILLINOIS POLLUTION CONTROL BOARD
    August 1, 1974
    TEXACO, INC. (Lawrenceville Refinery),
    Petitioner,
    V.
    )
    PCB 74—135
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    James P. Peyton, attorney for Petitioner.
    John Palinscar, attorney for Respondent.
    OPINION AND ORDER OF THE BOARD (by Dr. Odell)
    On April 11, 1974, Texaco, Incorporated (Texaco) filed
    with the Illinois Pollution Control Board (Board) a Petition for
    Variance from Rule 206(c) of Air Pollution Regulations, Chapter 2
    (Chapter 2) until September 15, 1974.
    Texaco operates a petroleum refinery adjacent to the
    southern boundary of Lawrenceviile, Illinois, which has a population
    of 5,900. This refinery manufactures principally liquified
    petroleum gas, motor gasolines, aviation fuels, diesel and heating
    oils, heavy fuel oil, and asphalt, utilizing approximately 84,000
    barrels of crude oil per calendar day in the manufacturing process.
    The refined products are distributed for consumption in southern
    Illinois, as well as in Indiana, Kentucky, Ohio, Missouri, and
    other states. Approximately 600 persons are employed at this
    refinery.
    The specific emission source which is the subject of this
    Petit.ion.for Variance is the catalyst regeneration section of a
    Fluid Catalytic Cracking Unit. By a combination of thermal and
    catalytic cracking, this unit converts high boili~ig—range gas oils
    intoLP gas, gasolines, furnace oil, fuel oil, and coke~. The con-
    version is accomplished by mixing the gas oils with air and burn-
    ing them in a regenerator vessel. During this process carbon
    monoxide is released to the atmosphere in a concentration of
    62,000 parts of CO per million parts of air.
    Texaco is installing a Carbon Monoxide Boiler, at a cost
    of $3,270,000, to control the carbon monoxide emissions which are
    the subject of this Petition for Variance. Originally, Texaco
    had planned to have its Carbon Monoxide Boiler operative by
    December 31, 1973. However, equipment delivery delays and scarcity
    of critical craft manpower has revised Texaco’s time schedule as
    follows:
    251

    —2—
    January 20, 1972
    Awarded construction contract
    October 18, 1972
    Commenced construction
    June 15, 1974
    Complete construction
    September 15, 1974
    Commence operahion
    Texaco alleges that the period from June 15 to September 15, 1974,
    is needed to inspect and test the new equipment to avoid possible
    injury to personnel or the equipment.
    Petitioner stated that the construction delays, which were
    due to tardy equipment deliveries and scarcity of critical craft
    manpower, were beyond the control of Texaco and their construction
    contractor, Bechtel. Texaco alleges that compliance with “Rule
    206(c)
    prior to the forecasted operational date (September 15, 1974) of
    the Carbon Monoxide Boiler would necessitate shutdown of the Fluid
    Catalytic Cracking Unit” because of limited storage for charge stock
    for the latter Unit, “Cessation of operations would result in a
    most unreasonable and arbitrary hardship not only on Petitioner,
    but also on Texaco’s distributors and retailers, its employees, and
    the general public.” Petitioner claimed that granting this Variance
    would have no adverse effect on the public because there is very
    little difference in the ca~rbonmonoxide concentration upwind and
    downwind from the refinery, as shown by the following results from.
    a survey by an outside firm, Air Resources Incorporated, of ambient
    air at the perimeter of the plant:
    ~nMonoxide~oncentration~rn~
    ~einterval
    ~indof
    ~nw~of
    ~iner~
    ~iner
    1 hour max.
    8 hour max.
    15 mm. arithmetic mean
    A Recommendation was received from the Environmental
    Protection Agency (Agency) on June 10, 1974. On the basis of the
    catalytic unit charge of 45,000 barrels per day of gas oil, the
    Agency calculated carbon monoxide emissions as 25,800 pounds per
    hour in a concentration of 62,000 parts of carbon monoxide per
    million parts air. Thus, Petitioner currently operates in violation
    of Rule 206(c), However, Petitioner is installing a Carbon Monoxide
    Boiler to control its emissions by September 15, 1974. There are no
    other similar CO sources in the area, and no citizen interviews
    were conducted by the Agency because carbon monoxide is odorless and
    can be detected only by instrumentation. “The Agency is of the
    opinion that the proposed control program, if properly designed and
    operating, will achieve compliance with Rule 206(c),” The Agency
    (I) denies Petitioner’s alleged economic hardship in this case, but
    (2) recognizes that “the hardships caused by a plant shutdown would
    be a loss of earnings for Petitioner’s employees, and a disruption
    of gasoline and,.other important fuel supplies for the public.” The
    Agency recommended that Petitioner be granted a Variance from Rule
    206(c)~untilSeptember 15, 1974, subject to certain conditions,

    —3—
    A hearing was held in Lawrenceville, Illinois, on June
    13, 1974, Three Texaco employees testified concerning the
    operation of the refinery. Robert B. McBride, Chief Engineer,
    explained the delays in the construction of the Carbon Monoxide
    Boiler. The first notification of delay from the construction
    contractor (Bechtel) was in their progress report for the month
    ending September 30, 1973 (Exhibit 2; R,9), At this late date,
    no ~alternate solution was available except to complete installation
    of the CO Boiler as soon as possible.
    Mr. Joe W. Garrison, Supervisor of Air and Water Conservation,
    described the ambient air survey that was conducted at the refinery
    by Air Resources Incorporated. The samples were taken over a 30~
    day period on the top of a van, both upwind and downwind, around
    the perimeter of the refinery (R,l9, 21). The amounts of carbon
    monoxide measured (with a gas chromatograph) were~tonsiderably
    below levels which would be dangerous to human health (R,20), The
    carbon monoxide is dispersed from stacks approximately 200 feet
    Mr. A.L, Bishop, Plant Manager, explained the highly inte-
    grated operation of the refinery and, therefore, if the Fluid
    Catalytic Cracking Unit were,shut down cessation of all operations
    would necessarily soon follow.
    The “Agency is convinced of Petitioner’s good faith efforts”
    and recommends that the Variance be granted “subject to the con-
    ditions expressed in the Agency Recommendation as amended” (R.30).
    The Board concurs except that the suggested condition con-
    cerning a Performance Bond ~does not seem necessary at this time,
    Texaco committed itself in 1972 to installing a $3,270,000 Carbon
    Monoxide Boiler and construction of it was to be completed by
    June 15, 1974, according to the record in this case, The main
    objective now is proper operation of the equipment to adequately
    control carbon monoxide emissions, This Opinion constitutes the
    findings ~of fact and conclusions of law of the Board,
    IT IS THE ORDER of the Illinois PollutioB Control Board
    that Petitioner is hereby granted a Variance from Rule 206(c)
    of Air Pollution Regulations, Chapter 2, for its Fluid Catalytic
    Cracking Unit at Lawrencevilie, Illinois, from January 1, 1974,
    to September 15, 1974, subject to the following conditions:
    (a) Petitioner shall make timely application for all
    necessary operating permits.
    (b) Petitioner shall submit a progress report on
    August 10, 1974, to the Agency at the following
    address:

    —4
    Environmental Protection Agency
    Division of Air Pollution Control
    2200 Churchill Road
    Springfield, Illinois 62706
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the ove Opinion and Order
    was adopted on the j~±dayof
    ,
    1974, by a vote of
    __
    toO.
    (~).J~
    j
    ~stanL,Mt
    13—
    254

    Back to top