ILLINOIS POLLUTION CONTROL BOARD
July 25,
1974
VILLAGE
OF ROUND
LAKE BEACH,
)
Petitioner,
)
vs.
)
PCB 74-189
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
)
OPINION AND ORDER OF THE BOARD (by Mr.
Seaman):
On
May
23,
1974,
the Vi11~geof Round Lake Beach filed
its Petition
For Variance,
Petitioner seeks relief from an Agency imposed limitation
on further sanitary sewer extension connections
in an area tributary to
the sewage treatment plant owned and operated by the Round Lake Sanitary
District (District).
This ban was imposed pursuant to Rule 921(a)
of
Chapter
3: Water Pollution Regulations of Illinois.
Petitioner seeks such
relief in order to accomplish
the following:
a)
the construction of
a sanitary sewer system to serve a tract
of land known
as the Edwards Subdivision;
b)
the connection of said sanitary sewer system to the District’s
sewage treatment plant; and
c)
the connection
of 43 existing residences
to the said sanitary
sewer
system.
The District’s sewage treatment plant discharges
to Squaw
Creek,
which provides
a dilution ratio
of less than one-to-one,
Agency investigation
has revealed that the District is presently producing an effluent with
BOD and suspended solids concentrations of less than 20 and 25 mg/l
as
currently required by Rule 404 of Chapter
3.
The Agency believes that
the plant will be unable
to meet the
4
and
5 mg/l
requirements of Rule 404(f)
an December 31,
1974,
as required by Rule 409.
The Agency notes that the
plant
is presently operating
in apparent compliance with the requirements
of Rule 405 of Chapter
3.
Even though there
is an absence of apparent effluent violations, the
plant
is subject to extreme hydraulic overloading,
The design average flow
of the plant
is calculated
to be 1.6 mgd.
The plant consistently receives
flows
in excess of design average.
Bypassing to the plant’s three-cell
lagoon system occurs on
a regular basis.
There
is
no direct bypass to Squaw
Creek,
The precise amount of flow cannot presently be determined by the
District or the Agency because
of inadequate metering facilities
for raw
sewage intake.
13
—
225
-2-
On April
4,
1974,
the Agency denied
a permit application for the
construction and operation of the subject sanitary sewer system due
to overloaded conditions.
There appears
to be no dispute that the
system is overloaded and that the Agency acted properly in denying the
permit.
Petitioner alleges instead,
that Agency observance of the
requirements of Rule
921
imposes
an arbitrary or unreasonable hardship.
The alleged hardships relate primarily
to the health hazard created
by septic systems serving the subject 43 residences.
On occasion, raw
sewage has been observed on
the lots and flowing
in the streets adjacent
to the homes
in Edwards Subdivision.
It
is alleged that this raw
sewage also flows into Round Lake.
The Lake County Health Department
has substantiated these allegations.
The Department has investigated
the situation and concluded that the subsurface septic systems
in the
Edwards Subdivision are
inadequate.
In addition, Department investigation
has revealed the following:
a)
The area of
Round Lake proximate to Edwards Subdivision
consistently shows higher bacterial
counts than other
sampling points
in the lake;
b)
The area adjacent to Edwards Subdivision
is
unsatisfactory
for recreational
bathing;
c)
The degraded conditions
of Round Lake are due to the septic
tanks
in Edwards Subdivision;
d)
The subject septic tanks are old and located on small
lots
with unsatisfactory soil conditions.
The Department investigation of the area indicated that 18 out of 34
homes surveyed showed evidence of septic system malfunction.
The Department
has
concluded that the present conditions
in Edwards Subdivision result in
pollution of
Round Lake and also constitute “a public health hazard.”
The Department supports the concept of providing sewer service to Edwards
Subdivision regardless of treatment plant overload.
(See letter from Lake
County Health
Department to Mr.
David J.
Friedman, daX~edMay 31, 1974.)
Therefore,
the Board’s decision involves possible increases of pollution
due to overload on one hand versus the elimination of a documented health
hazard due to inadequate septic systems which cannot be reasonably repaired
on theother.
While we are reluctant to allow additional
connections
to overloaded
treatment plants, we are satisifed that the serious danger to health must
be abated.
The variance will
be granted, but only to the extent necessary to
protect the public health.
Finally,
the Agency has been informed that the Petitioner has contracted
for the installation of water mains
to serve Edwards Subdivision.
Substantial
expenses can be eliminated if the requested variance
is granted to allow the
simultaneous construction of both water and sewage service.
13
—
226
-3-
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
IT
IS THE ORDER of the Pollution Control Board that the Village
of
Round Lake Beach be granted a variance to allow the construction and
connection
of
a sanitary sewer system to serve the existing homes
of the
Edwards Subdivision, subject to the following conditions:
1.
Connections to the proposed sanitary ~ewersystem will
be
limited
to those residences served by inadequate septic
systems in which
improved maintenance or reasonable
repairs cannot eliminate potential health hazards
as determined
by the Agency.
2.
The Petitioner will prohibit future developments which would
utilize s~pticsystems where soil
conditions and other factors
are inadequate
to support such use,
3.
Petitioner will obtain all necessary permits
from the Agency.
I,
Christan
L. Moffett, Clerk of the Illinois Poflution Cont ol Board,
certify that
t e above Opinion and Order was adopted on this
~
day of
,
1974 by
a vote of
‘?‘—
0
13—227