ILLINOIS POLLUTION CONTROL
    BOARD
    July 25, 1974
    COMMONWEALTH
    EDISON
    COMPANY
    )
    PETITIONER
    PCB 74—182
    ENVIRONMENTAL PROTECTION AGENCY
    RESPONDENT
    MR. IkRRK
    VIRSHBO,
    ATTORNEY, of ISHAM, LINCOLN & BEALE in
    behalf of
    COMMONWEALTH EDISON COMPANY
    MR. JAMES S~ SCHLIFKE, ASSISTANT ATTORNEY GENERAL, in behalf of the
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION AND ORDER OF THE BOARD (by Mr~ Marder)
    This action involves a request
    for
    variance filed
    May 17, l974~
    Relief
    is
    sought
    from Rules 201 and 203 (i) of Chapter
    3,
    Water Poll-
    ution Regulations of Illinois, until October 15, 1974, as they per-
    tain
    to
    Edison~s discharges
    from
    the
    Dresden Generating Plant., Pet-
    itioner alleges that due to delays in construction and
    delivery
    of
    essential materials the con~liance plan detailed in PCB 73—359 will
    be
    delayed two months.
    Commonwealth Edison owns
    and
    operates,
    in
    Grundy County,
    Illinois
    a three-unit
    nuclear powered generating station~ Unit One was made
    cperabie
    in
    1960 arid has a capacity of 200 mw~ Units Two and Three
    earns
    on stream
    in
    1970 and 1971 with rated capacity of 809 mw each~
    Pet:Ltioner~s
    need
    for variance centers around thermal pollution re~
    suiting
    from the discharge of
    cooling
    water into the Illinois River
    Presently cooling water
    for
    Unit
    *li
    s pulled frOm the Kankakee River
    and after once through
    cooling of the
    reactor
    core
    is
    discharged to
    the Illinois
    River~
    Cooling
    water
    for
    the #2 and
    #3
    reactors
    :Ls
    pres-
    ently
    discharging to
    an
    open-cycle cooling lake
    of 1300 acres.. Over-
    flow
    from this lake is discharged to the :llinois
    River.
    Petitioner has incorporated the record in PCB 73-359, and uses the
    record generated
    therein
    as a basis for fu1fi~m~~He~ictates of
    the
    BOarCPS
    Procedural Rule
    401, The
    Agency filed its recommendation
    on June 24,
    1974,
    recommending a grant of variance
    subject to certain
    conditions
    This action is
    in
    actuality a continuance of variances
    granted in
    the
    following cases~ PCB 70—21, PCB 72—350,
    and
    PCB
    73—359.
    A brief description of the events 1eadT~q~
    he in order and is as
    follows

    —2—
    1. On March
    3, 1971, the
    Board
    in PCB 70-21 issued a permit to
    Commonwealth Edison to operate Unit 4~3.. In granting said permit a
    number of conditions were imposed, e..g.:
    “3 (b) The permittee shall within thirty days after
    the issuance of this permit submit to the Board a
    written program with a time schedule for controlling
    the liquid radioactive discharges up to the amounts
    set forth
    in paragraph 3 (A) of this permit from
    Dresden Unit III
    without the use
    of dilution water..”
    “5 (b) Permittee in the operation of Dresden Unit 3
    shall comply with the thermal discharge requirements
    of SWB_8* as interpreted in the opinion of the Board..
    In order to assume such compliance, Permittee shall
    submit the followiiig information to the Board within
    thirty (30) days from this date..”
    2.. On April 13, 1971, Petitioner filed the abovementioned reports,
    and also a request for time (PCB 70-21) to allow completion of their
    proposed plans.. In the Board~sorder of NOvember 23, 1971, it was
    noted that Petitioner had put into operation a cooling lake for Unit
    #2 and
    #3..
    It had also installed 98 spray modules in the canals.. The
    Board ordered Petitioner
    to
    begin installation of a “Maximum recycle
    system~ for radioactive wastes to be completed by September 1, 1973..
    The radioactive liquid waste limit of 80,000 microcurries per second
    would then apply to the blowdown from this cooling lake..
    The Board further granted a variance from SWB-8 until November 23,
    1973.. The abovementioned lake and spray modules were found not to
    comply with SWB-8 and thus the need for this variance.. A compliance
    plan called for the installation of a diffuser pipe to meet the re-
    quired 5°F.. maximum temperature rise..
    3.. On August 23, 1972, Commonwealth Edison filed a petition for
    variance extension (PCB 72-350).. By an interim Board order of October
    10, 1972, a sixty-day extension was granted
    in
    order
    to
    gain time to
    conduct public hearings and ~alsoprotect Petitioner from prosecution
    during the interim period (Nov.. 23, 1972-Jan.. 22, 1973).. PCB 72-350
    went to hearings to determine the facts.. Petitioner claimed that the
    original wastewater system scheduled for completion by September 1,
    1973, could not be completed before February 1, 1974.. The diffuser
    pipe was not installed and no data on the barrier effect of such a
    pipe on fish was elicited.. By Board order of March 29, 1973, variance
    was granted from 201 and 203 (i) until November 23, 1973..
    4.. On August 22, 1973, PCB 73—359 was filed, asking for extension
    to November 23, 1974, or such shorter time as needed to complete the
    aforementioned compliance plan.. On November 13, 1973, Petitioner filed
    for and was granted an interim variance until January 22, 1974.. On Jan-
    uary 17, 1974, the Board extended variance until
    August 15, 1974.. In
    PCB 73-359 the Board also
    ruled
    that a slQt jet discharge pipe may be
    used to conform with the Board~sinterpretation of mixing zones as they
    *SWB8 was superseded in part by Rules 201 and
    203 (1) of Chapter 3
    on March 7, 1972 (PCB R7l—14)..
    13
    220

    —3—
    apply to Edison~s discharge, and that monthly reports would be required..
    5.. On May 17, 1974, PCB 74-182 (the instant case) was filed, seek-
    ing an additional 60-day extension of variance..
    This chronology brings up to date the events since the startup of
    Dresden #3.
    Petitioner alleges that a short delay in completion of their maximum
    recycle system for liquid radioactive wastes was anticipated in the
    testimony elicited during PCB 73-359.. The following excerpt is used to
    substantiate this fact..
    “It
    must be understood that the same high standards of qual-
    ity assurance must still be met for the remaining period of
    manufacture, and no one can guarantee that there won~t
    be
    some additional delay..” (Tr.. 73-359, Pg.. 48)
    Edison
    now
    contends that due to quality assurance requirements rela-
    ting to the
    ‘two
    concentrators (the principal component of the
    maximum
    recycle system), delivery has been delayed as
    much as
    five
    months..
    Petitioner alleges that the maximum recycle system should be opera-
    ting with one concentrator by August 15, 1974.. This will allow closed
    loop operation of the Dresden plant.. The second concentrator is ex-
    pected on site during August 1974.. Although the facility can operate
    with one concentrator, the backup capacity of the second concentrator
    will
    not be
    available
    until
    October 1974, Edison proposes to operate
    closedloop unless the first concentrator fails. Thus in reality this
    variance request is for permission to operate under malfunction condi-
    tions.. It is therefore impossible to judge whether such operation will
    consist of 60 days or no days. In deciding this case the Board will
    work on the premise of the worst possible case
    or 60-day open loop
    operation.
    In assessing the merits of Petitioner~scase the Board relies heav-
    ily on documentation elicited during PCB 73-359.. The reader is directed
    to our Opinion in this matter dated January 17, 1974, for a detailed de-
    scription
    of
    hardship and environmental impact..
    The subject of environmental impact was covered in detail in 73—359,
    The Board finds no reason to alter its conclusion:
    “From all the above the Board finds the weight of the
    evidence is that no significant environmental harm has
    occurred due to Dresden~sUnits 2
    and
    3. It is also
    important to note that the proposed slot jet discharge
    should yield even better mixing in the near future..”
    (Opinion 73-359 Pg.
    7)
    The addition of a 60-day variance should, in the Board~sopinion,
    not alter the validity of the above statement.
    13
    221

    —4—
    The subject of hardship must, of course, be updated to reflect the
    latest facts.. Edison rests its
    hardship case on the need by Edison
    and the public for the output of the Dresden plant. Petitioner alleges
    that the highest anticipated peak load demand during the summer of 1974
    will be 14,050 mw. Petitioner further alleges that after deductions
    for peaking loads, firm purchases, diversity interchanges, derating
    due to low sulphur coal, and maintenance, the aggregate system capacity
    of 16,755 mw will
    be
    reduced to 14,933 mw. Therefore Petitioner con-
    cludes that the 1800 ins generation capacity will be required to main-
    tain a safety margin in the system to protect against any forced outages..
    Petitioner then details its loading requirements and expected outages
    during the months of September and October, reaching similar conclusions
    that the Dresden capacity is needed to secure an adequate safety margin..
    The Board has difficulty in agreeing with Edison~srationale in sub-
    tracting peaking capacity from its total system capacity.. It would
    seem that peaking capacity is just that
    a reserve generation load to
    meet short-term excessive demands.. The rationale of exempting firm
    purchases from the total available capacity also escapes this B6~P~.. If
    such purchases are firm, they should be available..
    Notwithstanding the above seeming inconsistencies, the Board sees
    little vaLue in denying this variance. It is for a short time duration,
    and as me:itioned above should have little impact on the environment,
    The Board will thus grant the variance request..
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that Commonwealth
    Edison Company is granted variance from Rules 201 and 203 (i) of Chap-
    ter 3 as they apply to the discharge from the Dresden plant until Oct-
    ober 15, 1974, subject to the following conditions:
    I. Petitioner shall continue to file monthly operating
    reports as described in Order #4 of PCB 73-359..
    2.. Petitioner shall by August 15, 1974, have operable
    a cooling water discharge system which will meet the
    mixing zone criteria as outlined in PCB 73-359..
    3. This variance shall apply only in the event that the
    system in condition 2 becomes inoperable.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, certify that the above Opinion and Order was adopted by the
    Board on
    the 25th day
    of July, l974,~ by a vote of 5 to 0,
    13 —
    222

    Back to top