ILLINOIS POLLUTION CONTROL
BOARD
July 25, 1974
COMMONWEALTH
EDISON
COMPANY
)
PETITIONER
PCB 74—182
ENVIRONMENTAL PROTECTION AGENCY
RESPONDENT
MR. IkRRK
VIRSHBO,
ATTORNEY, of ISHAM, LINCOLN & BEALE in
behalf of
COMMONWEALTH EDISON COMPANY
MR. JAMES S~ SCHLIFKE, ASSISTANT ATTORNEY GENERAL, in behalf of the
ENVIRONMENTAL PROTECTION AGENCY
OPINION AND ORDER OF THE BOARD (by Mr~ Marder)
This action involves a request
for
variance filed
May 17, l974~
Relief
is
sought
from Rules 201 and 203 (i) of Chapter
3,
Water Poll-
ution Regulations of Illinois, until October 15, 1974, as they per-
tain
to
Edison~s discharges
from
the
Dresden Generating Plant., Pet-
itioner alleges that due to delays in construction and
delivery
of
essential materials the con~liance plan detailed in PCB 73—359 will
be
delayed two months.
Commonwealth Edison owns
and
operates,
in
Grundy County,
Illinois
a three-unit
nuclear powered generating station~ Unit One was made
cperabie
in
1960 arid has a capacity of 200 mw~ Units Two and Three
earns
on stream
in
1970 and 1971 with rated capacity of 809 mw each~
Pet:Ltioner~s
need
for variance centers around thermal pollution re~
suiting
from the discharge of
cooling
water into the Illinois River
Presently cooling water
for
Unit
*li
s pulled frOm the Kankakee River
and after once through
cooling of the
reactor
core
is
discharged to
the Illinois
River~
Cooling
water
for
the #2 and
#3
reactors
:Ls
pres-
ently
discharging to
an
open-cycle cooling lake
of 1300 acres.. Over-
flow
from this lake is discharged to the :llinois
River.
Petitioner has incorporated the record in PCB 73-359, and uses the
record generated
therein
as a basis for fu1fi~m~~He~ictates of
the
BOarCPS
Procedural Rule
401, The
Agency filed its recommendation
on June 24,
1974,
recommending a grant of variance
subject to certain
conditions
This action is
in
actuality a continuance of variances
granted in
the
following cases~ PCB 70—21, PCB 72—350,
and
PCB
73—359.
A brief description of the events 1eadT~q~
he in order and is as
follows
—2—
1. On March
3, 1971, the
Board
in PCB 70-21 issued a permit to
Commonwealth Edison to operate Unit 4~3.. In granting said permit a
number of conditions were imposed, e..g.:
“3 (b) The permittee shall within thirty days after
the issuance of this permit submit to the Board a
written program with a time schedule for controlling
the liquid radioactive discharges up to the amounts
set forth
in paragraph 3 (A) of this permit from
Dresden Unit III
without the use
of dilution water..”
“5 (b) Permittee in the operation of Dresden Unit 3
shall comply with the thermal discharge requirements
of SWB_8* as interpreted in the opinion of the Board..
In order to assume such compliance, Permittee shall
submit the followiiig information to the Board within
thirty (30) days from this date..”
2.. On April 13, 1971, Petitioner filed the abovementioned reports,
and also a request for time (PCB 70-21) to allow completion of their
proposed plans.. In the Board~sorder of NOvember 23, 1971, it was
noted that Petitioner had put into operation a cooling lake for Unit
#2 and
#3..
It had also installed 98 spray modules in the canals.. The
Board ordered Petitioner
to
begin installation of a “Maximum recycle
system~ for radioactive wastes to be completed by September 1, 1973..
The radioactive liquid waste limit of 80,000 microcurries per second
would then apply to the blowdown from this cooling lake..
The Board further granted a variance from SWB-8 until November 23,
1973.. The abovementioned lake and spray modules were found not to
comply with SWB-8 and thus the need for this variance.. A compliance
plan called for the installation of a diffuser pipe to meet the re-
quired 5°F.. maximum temperature rise..
3.. On August 23, 1972, Commonwealth Edison filed a petition for
variance extension (PCB 72-350).. By an interim Board order of October
10, 1972, a sixty-day extension was granted
in
order
to
gain time to
conduct public hearings and ~alsoprotect Petitioner from prosecution
during the interim period (Nov.. 23, 1972-Jan.. 22, 1973).. PCB 72-350
went to hearings to determine the facts.. Petitioner claimed that the
original wastewater system scheduled for completion by September 1,
1973, could not be completed before February 1, 1974.. The diffuser
pipe was not installed and no data on the barrier effect of such a
pipe on fish was elicited.. By Board order of March 29, 1973, variance
was granted from 201 and 203 (i) until November 23, 1973..
4.. On August 22, 1973, PCB 73—359 was filed, asking for extension
to November 23, 1974, or such shorter time as needed to complete the
aforementioned compliance plan.. On November 13, 1973, Petitioner filed
for and was granted an interim variance until January 22, 1974.. On Jan-
uary 17, 1974, the Board extended variance until
August 15, 1974.. In
PCB 73-359 the Board also
ruled
that a slQt jet discharge pipe may be
used to conform with the Board~sinterpretation of mixing zones as they
*SWB8 was superseded in part by Rules 201 and
203 (1) of Chapter 3
on March 7, 1972 (PCB R7l—14)..
13
—
220
—3—
apply to Edison~s discharge, and that monthly reports would be required..
5.. On May 17, 1974, PCB 74-182 (the instant case) was filed, seek-
ing an additional 60-day extension of variance..
This chronology brings up to date the events since the startup of
Dresden #3.
Petitioner alleges that a short delay in completion of their maximum
recycle system for liquid radioactive wastes was anticipated in the
testimony elicited during PCB 73-359.. The following excerpt is used to
substantiate this fact..
“It
must be understood that the same high standards of qual-
ity assurance must still be met for the remaining period of
manufacture, and no one can guarantee that there won~t
be
some additional delay..” (Tr.. 73-359, Pg.. 48)
Edison
now
contends that due to quality assurance requirements rela-
ting to the
‘two
concentrators (the principal component of the
maximum
recycle system), delivery has been delayed as
much as
five
months..
Petitioner alleges that the maximum recycle system should be opera-
ting with one concentrator by August 15, 1974.. This will allow closed
loop operation of the Dresden plant.. The second concentrator is ex-
pected on site during August 1974.. Although the facility can operate
with one concentrator, the backup capacity of the second concentrator
will
not be
available
until
October 1974, Edison proposes to operate
closedloop unless the first concentrator fails. Thus in reality this
variance request is for permission to operate under malfunction condi-
tions.. It is therefore impossible to judge whether such operation will
consist of 60 days or no days. In deciding this case the Board will
work on the premise of the worst possible case
—
or 60-day open loop
operation.
In assessing the merits of Petitioner~scase the Board relies heav-
ily on documentation elicited during PCB 73-359.. The reader is directed
to our Opinion in this matter dated January 17, 1974, for a detailed de-
scription
of
hardship and environmental impact..
The subject of environmental impact was covered in detail in 73—359,
The Board finds no reason to alter its conclusion:
“From all the above the Board finds the weight of the
evidence is that no significant environmental harm has
occurred due to Dresden~sUnits 2
and
3. It is also
important to note that the proposed slot jet discharge
should yield even better mixing in the near future..”
(Opinion 73-359 Pg.
7)
The addition of a 60-day variance should, in the Board~sopinion,
not alter the validity of the above statement.
13
—
221
—4—
The subject of hardship must, of course, be updated to reflect the
latest facts.. Edison rests its
hardship case on the need by Edison
and the public for the output of the Dresden plant. Petitioner alleges
that the highest anticipated peak load demand during the summer of 1974
will be 14,050 mw. Petitioner further alleges that after deductions
for peaking loads, firm purchases, diversity interchanges, derating
due to low sulphur coal, and maintenance, the aggregate system capacity
of 16,755 mw will
be
reduced to 14,933 mw. Therefore Petitioner con-
cludes that the 1800 ins generation capacity will be required to main-
tain a safety margin in the system to protect against any forced outages..
Petitioner then details its loading requirements and expected outages
during the months of September and October, reaching similar conclusions
that the Dresden capacity is needed to secure an adequate safety margin..
The Board has difficulty in agreeing with Edison~srationale in sub-
tracting peaking capacity from its total system capacity.. It would
seem that peaking capacity is just that
—
a reserve generation load to
meet short-term excessive demands.. The rationale of exempting firm
purchases from the total available capacity also escapes this B6~P~.. If
such purchases are firm, they should be available..
Notwithstanding the above seeming inconsistencies, the Board sees
little vaLue in denying this variance. It is for a short time duration,
and as me:itioned above should have little impact on the environment,
The Board will thus grant the variance request..
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that Commonwealth
Edison Company is granted variance from Rules 201 and 203 (i) of Chap-
ter 3 as they apply to the discharge from the Dresden plant until Oct-
ober 15, 1974, subject to the following conditions:
I. Petitioner shall continue to file monthly operating
reports as described in Order #4 of PCB 73-359..
2.. Petitioner shall by August 15, 1974, have operable
a cooling water discharge system which will meet the
mixing zone criteria as outlined in PCB 73-359..
3. This variance shall apply only in the event that the
system in condition 2 becomes inoperable.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, certify that the above Opinion and Order was adopted by the
Board on
the 25th day
of July, l974,~ by a vote of 5 to 0,
13 —
222