ILLINOIS POLLUTION CONTROL BOARD
    February
    27,
    1975
    DUNDEE
    CEMENT COMPANY,
    Petitioner,
    v.
    )
    PCB 74—450
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Dr. Odell)
    On December 3,
    1974,
    the Dundee Cement Company filed its
    Petition for Variance with the Pollution Control Board
    (Board).
    Petitioner sought
    a variance from the fugitive particulate
    matter requirements of Rule 203(f)
    of the Air Pollution Regula-
    tions
    (Chapter Two) from March
    7,
    1975, until December 31, 1975.
    The Board,
    in Dundee Cement Company v.
    Environmental Protection
    Agency PCB 73-541, 11 PCB 597
    (March 14, 1974), granted this
    Petitioner a variance from Rule 203(f) until March
    7,
    1975,
    for
    fugitive dust emissions created when it transfers cement from
    barges
    to hoppers at its facility.
    Petitioner operates a transfer terminal located on the
    south bank of the Sanitary and Ship Canal and situated approximately
    1,300 feet east of Illinois Route 83 in Lemont Township, Cook County,
    Illinois.
    The facility annually received about 150 barge loads of
    bulk cement;
    each flat-bottomed barge contains nearly 1,300 tons of
    cement,
    At Petitioner~sterminal,
    the barges are unloaded and the
    contents are transferred to storage silos.
    The cement is removed
    from the barges by clamshell cranes, deposited in hoppers, and con-
    veyed through enclosed areas to the storage silos.
    Depending upon
    wind velocity and the physical condition of the cement,
    a violation
    of Rule 203(f)
    of Chapter Two can occur during the unloading process
    and transfer to the conveyors.
    The area surrounding Petitioner’s
    facility is devoted to heavy industry;
    the nearest home is approx-
    imately one-half mile from the terminal.
    To achieve compliance with Rule 203(f)
    of Chapter Two,
    Petitioner is
    in the process of installing
    a modified pneumatic un-
    loading system, which utilizes special suction nozzles.
    This system
    will be able to unload conventional barges and will replace the
    crane operations.
    This pneumatic loading system draws the cement
    up into one of two pressure vessels; compressed air then forces the
    cement into the storage silos.
    Once the system becomes fully opera-
    tional, cement dust will no longer be emitted into the atmosphere.
    Completion of the project was originally scheduled for March 1975,
    but delayed equipment delivery has postponed completion until May
    1975.
    Petitioner alleges that an additional time of at least two
    months will be required beyond the May date to test and correct
    initial operating difficulties.
    Total cost of the system will be
    15—
    611

    —2—
    $1,054,000.
    To date, Petitioner has expended $634,000 on the
    project.
    Beginning in January 1975 Petitioner expects to commence
    using the basic pneumatic unloading system with specially de-
    signed barges.
    Such barges will be used until the specially
    designed barges cannot be borrowed without impairing the
    operation of other facilities.
    Dundee hopes to avoid use of the
    clamshell unloading system until May 1975, by which time the
    modified pneumatic unloading system will be ready for testing.
    The Environmental Protection Agency
    (Agency)
    filed its
    Recomn~endationon February 3,
    1975. Subject to certain conditions,
    the Agency recommended that the variance be granted.
    The Agency
    noted that no public injury appeared from the grant of the
    variance and that Petitioner has made substantial progress towards
    emission control.
    Furthermore, the Agency stated:
    “The Agency recognizes that the time delays
    experienced by Petitioner were legitimate, and feels
    that the additional time requested for completion of
    the project
    is reasonable.
    Furthermore,
    the Agency
    is of the opinion that once the pneumatic unloading
    system
    is operational, Petitioner will be in com-
    pliance with Rule 203(f).”
    On February 13,
    1975,
    the Petitioner filed a motion suggest-
    ing that no hearing be held and agreeing to
    a variance with the
    conditions proposed by the Agency.
    We believe that the Petitioner
    is entitled to a
    variance.
    Petitioner has presented ample evidence that it would be an un-
    reasonable hardship to deny a variance in this case.
    While we
    are satisfied with the Agency’s arguments, we do not agree with
    the parties that a variance until December 31, 1975,
    is warranted.
    With installation of the new equipment scheduled for May 1975,
    120 additional days should provide Dundee with sufficient time to
    make its modified pneumatic unloading system operational.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that Dundee
    Cement Company
    is granted
    a Variance from the fugitive particulate
    matter standards of Rule 203(f)
    of Chapter
    Two
    from March
    7,
    1975,
    until October
    1,
    1975, subject to the following conditions:
    (a)
    Petitioner shall continue to submit quarterly progress
    reports in writing to:
    Environmental Protection Agency, Divisic~
    of Air Pollution Control, Control Program Coordinator,
    2200
    Churchill Road,
    Springfield, Illinois 62706.
    lb
    —612

    —3—
    (b)
    Petitioner shall maintain its performance bond in
    full force.
    Cc)
    Petitioner shall make every effort to utilize the
    pneumatic unloading system with custom barges until the system
    is capable of unloading conventional barges, and continue to
    use the pneumatic unloading system thereafter.
    (d)
    Petitioner shall continue to supervise the crane
    operator to assure that precautions to minimize fugitive emissions,
    as specified in Petitioner’s Exhibit #7, are adhered to strictly.
    (e)
    Petitioner shall make every effort to have its control
    program completed at the earliest date possible.
    Mr. Henss dissents.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certi y that the above Opinion and Order was adopted
    on the
    ~
    day of
    _______________,
    1975, by a vote of
    ~
    to
    ~~tanL.ett
    15— 613

    Back to top