ILLINOIS POLLUTION CONTROL BOARD
February
27,
1975
DUNDEE
CEMENT COMPANY,
Petitioner,
v.
)
PCB 74—450
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION
AND
ORDER OF THE BOARD
(by Dr. Odell)
On December 3,
1974,
the Dundee Cement Company filed its
Petition for Variance with the Pollution Control Board
(Board).
Petitioner sought
a variance from the fugitive particulate
matter requirements of Rule 203(f)
of the Air Pollution Regula-
tions
(Chapter Two) from March
7,
1975, until December 31, 1975.
The Board,
in Dundee Cement Company v.
Environmental Protection
Agency PCB 73-541, 11 PCB 597
(March 14, 1974), granted this
Petitioner a variance from Rule 203(f) until March
7,
1975,
for
fugitive dust emissions created when it transfers cement from
barges
to hoppers at its facility.
Petitioner operates a transfer terminal located on the
south bank of the Sanitary and Ship Canal and situated approximately
1,300 feet east of Illinois Route 83 in Lemont Township, Cook County,
Illinois.
The facility annually received about 150 barge loads of
bulk cement;
each flat-bottomed barge contains nearly 1,300 tons of
cement,
At Petitioner~sterminal,
the barges are unloaded and the
contents are transferred to storage silos.
The cement is removed
from the barges by clamshell cranes, deposited in hoppers, and con-
veyed through enclosed areas to the storage silos.
Depending upon
wind velocity and the physical condition of the cement,
a violation
of Rule 203(f)
of Chapter Two can occur during the unloading process
and transfer to the conveyors.
The area surrounding Petitioner’s
facility is devoted to heavy industry;
the nearest home is approx-
imately one-half mile from the terminal.
To achieve compliance with Rule 203(f)
of Chapter Two,
Petitioner is
in the process of installing
a modified pneumatic un-
loading system, which utilizes special suction nozzles.
This system
will be able to unload conventional barges and will replace the
crane operations.
This pneumatic loading system draws the cement
up into one of two pressure vessels; compressed air then forces the
cement into the storage silos.
Once the system becomes fully opera-
tional, cement dust will no longer be emitted into the atmosphere.
Completion of the project was originally scheduled for March 1975,
but delayed equipment delivery has postponed completion until May
1975.
Petitioner alleges that an additional time of at least two
months will be required beyond the May date to test and correct
initial operating difficulties.
Total cost of the system will be
15—
611
—2—
$1,054,000.
To date, Petitioner has expended $634,000 on the
project.
Beginning in January 1975 Petitioner expects to commence
using the basic pneumatic unloading system with specially de-
signed barges.
Such barges will be used until the specially
designed barges cannot be borrowed without impairing the
operation of other facilities.
Dundee hopes to avoid use of the
clamshell unloading system until May 1975, by which time the
modified pneumatic unloading system will be ready for testing.
The Environmental Protection Agency
(Agency)
filed its
Recomn~endationon February 3,
1975. Subject to certain conditions,
the Agency recommended that the variance be granted.
The Agency
noted that no public injury appeared from the grant of the
variance and that Petitioner has made substantial progress towards
emission control.
Furthermore, the Agency stated:
“The Agency recognizes that the time delays
experienced by Petitioner were legitimate, and feels
that the additional time requested for completion of
the project
is reasonable.
Furthermore,
the Agency
is of the opinion that once the pneumatic unloading
system
is operational, Petitioner will be in com-
pliance with Rule 203(f).”
On February 13,
1975,
the Petitioner filed a motion suggest-
ing that no hearing be held and agreeing to
a variance with the
conditions proposed by the Agency.
We believe that the Petitioner
is entitled to a
variance.
Petitioner has presented ample evidence that it would be an un-
reasonable hardship to deny a variance in this case.
While we
are satisfied with the Agency’s arguments, we do not agree with
the parties that a variance until December 31, 1975,
is warranted.
With installation of the new equipment scheduled for May 1975,
120 additional days should provide Dundee with sufficient time to
make its modified pneumatic unloading system operational.
This Opinion constitutes the findings of fact and conclusions
of law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that Dundee
Cement Company
is granted
a Variance from the fugitive particulate
matter standards of Rule 203(f)
of Chapter
Two
from March
7,
1975,
until October
1,
1975, subject to the following conditions:
(a)
Petitioner shall continue to submit quarterly progress
reports in writing to:
Environmental Protection Agency, Divisic~
of Air Pollution Control, Control Program Coordinator,
2200
Churchill Road,
Springfield, Illinois 62706.
lb
—612
—3—
(b)
Petitioner shall maintain its performance bond in
full force.
Cc)
Petitioner shall make every effort to utilize the
pneumatic unloading system with custom barges until the system
is capable of unloading conventional barges, and continue to
use the pneumatic unloading system thereafter.
(d)
Petitioner shall continue to supervise the crane
operator to assure that precautions to minimize fugitive emissions,
as specified in Petitioner’s Exhibit #7, are adhered to strictly.
(e)
Petitioner shall make every effort to have its control
program completed at the earliest date possible.
Mr. Henss dissents.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certi y that the above Opinion and Order was adopted
on the
~
day of
_______________,
1975, by a vote of
~
to
~~tanL.ett
15— 613