ILLINOIS POLLUTION CONTROL BOARD
    February
    14,
    1975
    ENVIRONMENTAL PROTECTION AGENCY, and
    THE PEOPLE OF THE STATE OF ILLINOIS,
    Complainants,
    vs.
    )
    PCB 74—204
    TRANSFORMER MANUFACTURERS,
    INC.,
    Respondent.
    Jeffrey Herden and Marvin Benn, Assistant Attorneys General for
    Complainants
    Kenneth Prince, Attorney for Respondent
    OPINION AND ORDER OF THE BOARD
    (by
    Mr.
    Henss):
    In this enforcement action Respondents are charged with
    operating an emission source without an Agency permit in violation
    of Rule 103(b) (2) (D)
    of the Air Pollution Control Regulations from
    June
    1, 1973 to June 19,
    1974,
    the date an Amended Complaint was
    filed.
    Count II of the Complaint charges Respondent with causing
    or allowing the discharge of foul odors, noxious vapors and com-
    pounds into the atmosphere in such concentrations
    as
    to cause air
    pollution in violation of Section 9(a) of the Environmental Pro-
    tection Act.
    A stipulation of
    facts reveals that Respondent has operated
    a transformer manufacturing facility in Village of Norridge,
    Illinois
    since 1962.
    In the manufacturing process Respondent uses
    22 dip
    pot soldering stations,
    two tanks containing styrene monomer, two
    tanks containing varnish,
    two tanks containing wax and four curing
    ovens.
    Respondent admits that the equipment was a source of odorous
    emissions and that such odors emanated from its plant at various
    times so as to unreasonably interfere with the enjoyment of life
    of citizens in the immediate vicinity of the plant.
    Odors from Respondent’s plant were substantially reduced by
    the installation of a $13,000 afterburner which controls the exhaust
    emissions from the four ovens.
    This afterburner was installed in
    September
    1973.
    Permits for the installation and operation were
    obtained,
    some prior and some subsequent to installation.
    15— 471

    —2—
    It is further stipulated that Respondent has shown cooperation
    and diligence in solving the remaining odor problem by the
    following actions:
    a)
    installed an interlock system in August
    1973 which prevents the ovens from operating until the afterburner
    has reached an efficient operating temperature,
    b) agreed to
    construct equipment to exhaust emissions from the varnish and
    styrene monomer tanks to the afterburner,
    c)
    agreed to install a
    temperature recording device capable of continually recording
    the afterburner temperature,
    d) has obtained an operating permit
    for the entire facility,
    e) agreed to keep doors and windows of
    the impregnation and baking room closed in order to reduce the
    amount of odorous emissions escaping through these outlets,
    f)
    agreed to obtain required permits for the installation
    of any
    additional pollution control equipment,
    and g)
    agreed to undertake,
    within
    90 days of any Board Order,
    any of the above measures which
    have not yet been implemented.
    Although two public hearings were conducted,
    no members of the
    public were in attendance.
    Respondent was granted 20 days to file
    its final brief and the Agency was allowed ten days to reply.
    The
    record shows that Respondent was the only party to file a post-
    hearing brief.
    According to Respondent’s brief, It
    was
    during an inspection
    by Agency employees that Respondent first learned that the plant
    was an “emission source” and was causing air pollution.
    After the
    inspection Respondent promptly hired
    a qualified, independent
    environmental control equipment firm to conduct a study and make
    recommendations “as to the alleged violations”.
    Six months later
    the firm proposed to install an afterburner to abate the odor
    problem.
    The following month Respondent ordered the afterburner from
    this firm.
    The contract called for the firm to deliver the after-
    burner and auxiliary equipment as soon as possible and to prepare
    and submit all drawings and applications necessary to obtain all
    “city, county and State permits for the operation of same”.
    Due
    to an equipment order backlog the firm did not deliver the equipment
    until May 1973.
    In the interim, Respondent installed gas lines
    and electrical equipment and obtained construction permits from the
    Village of Norridge in which Respondent’s plant is
    located.
    After receiving the equipment Respondent found it necessary to
    hire an experienced installer to connect the afterburner equipment.
    An order backlog delayed installation until September 1973.
    Prior to receiving the original complaint, Respondent believed
    the equipment firm had applied for all permits as specified in the
    contract.
    When this prosecution was commenced Respondent discovered
    that no Agency permits had been applied for and at that time

    —3—
    contacted the equipment firm.
    A permit application was filed
    immediately and the Agency granted a permit for the afterburner
    42 days after the original complaint had been filed in this
    suit.
    Believing it was now in total compliance, Respondent showed
    the permit to counsel for Complainants but was informed that
    Complainants recommended additional steps
    to insure that the
    plant would no longer be
    a source of odor and would be in
    compliance with all Statues, Rules and Regulations.
    Respondent
    then engaged the services of another consulting
    firm.
    This firm
    reported that its investigation showed the plant to be
    in compliance.
    It was recommended that Respondent apply for an operating permit.
    An operating permit application was filed on November 12, 1974 and
    approved on December
    2,
    1974.
    Respondent submits that the operating permit indicates
    Respondent’s total compliance and that further evidence of its
    diligence and good faith efforts
    is
    shown by the agreement to
    undertake additional precautionary and remedial measures as
    ~uggested
    by Complainants.
    During the hearing Respondent contended that the plant met
    all criteria necessary for issuance of a permit by September
    1,
    1973 and that “the ultimate ministerial act of issuing those
    permits was perfunctory”
    CR.
    4).
    The Board has previously said that the permit system is
    necessary “both to aid in obtaining emission information necessary
    for an evaluation
    of the control program and. as an effective
    enforcement mechanism”
    (Opinion of the Board in the matter of
    Emission Standards,
    R7l-23, April 13, 1972).
    Respondent’s mis-
    understanding of the importance of permits is evident.
    A permit
    under the Environmental Protection Act and Board Regulations is
    more than a mere “ministerial act”.
    Each permit application is
    scrutinized to insure that the operation will not cause the
    citizens of Illinois to be unreasonably exposed to pollutants
    which are injurious
    or which unreasonably interfere with their
    enjoyment of life or property.
    This careful scrutiny also serves
    to protect the economic interest of the permit applicant in that
    the Agency can advise the applicant of any shortcomings
    in proposed
    control equipment.
    This scrutiny and the benefits thereby derived are
    not to be considered “perfunctory”.
    We have reviewed the record in light of the requirements of
    Section 33(ç)
    of the Environmental Protection Act.
    We find that
    Respondent caused air pollution in violation of Section 9(a)
    of
    the Act.
    However, the Board finds that the delay in installing the
    afterburner was not the fault of Respondent.
    15
    473

    T~eparties agree that Respondent’s corrective action and
    the agreement to take additional
    steps make the imposition of
    monetary penalty unwarranted~ The fact that no members of the
    public appeared to testify against Respondent would indicate that
    the aggrieved have been satisfied.
    With that understanding and
    in view of Respondent’s good faith efforts no penalty will be
    imposed.
    A cease and desist order
    is required, however, and
    it shall be so ordered.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Pollution Control Board.
    ORDER
    It is the Order of the Pollution Control Board that:
    1.
    Transformer Manufacturers,
    Inc. cease and desist
    from further violations of Section
    9(a)
    of the
    Environmental Protection Act and Rule 103(b) (2)
    (D)
    of the Air Pollution Control Regulations.
    2.
    Respondent shall, within 90 days of the date of
    this Order, implement and perform all actions as
    outlined in the Stipulation of Facts.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order was ad,opted
    this
    ./i/~”
    day ~
    ,
    1975 by
    a vote of
    ~/
    to 0
    041
    h1-~s4~~
    ~
    15
    474

    Back to top