ILLINOIS POLLUTION CONTROL BOARD
    February
    6,
    1975
    HERBERT F. BANGERT,
    )
    Complainant,
    vs.
    )
    PCB 74—295
    CITY OF QUINCY,
    Respondent.
    Herbert F. Bangert, appeared pro se
    James N. Keefe, Attorney for Respondent
    OPINION AND ORDER OF
    THE
    BOARD
    (by Mr. Henss):
    Herbert Bangert,
    a resident of Quincy,
    Illinois, filed
    a
    Complaint against City of Quincy alleging that the City had
    constructed
    a sewer line in violation of municipal codes and
    without first securing a construction permit from the Environ-~
    mental Protection Agency.
    Specifically, Respondent is charged
    with installing a sewer line that:
    1)
    is too shallow,
    2)
    is
    only 6”
    in diameter,
    3) has no manhole for clean out, and
    4)
    is not feasible for future connections.
    Complainant seeks to
    have Respondent reconstruct the sewer in compliance
    with
    municipal codes and Agency requirements in order to eliminate
    defects now burdening Complainant.
    Pursuant to Rule 306 of the Board’s Procedural Rules the
    Agency was requested to provide additional information on the
    issues.
    After reviewing the Agency’s comment the Board ruled
    that the case be set for public hearing.
    Hearing was conducted
    on December
    4,
    1974 in Quincy,
    Illinois.
    The sewer line
    in question is a 245’ section of sanitary
    sewer located at
    N.
    22nd Street between Maple and Sycamore
    Streets in Quincy.
    Bangert owns two lots on the west side of
    N.
    22nd.
    Street.
    His home is located on one of the lots and the
    other lot is vacant.
    Complainant intends
    to develop the unoccupied
    lot.
    Also on the west side of N. 22nd Street are two homes which
    were built in 1972 by a Mr. Sandifer.
    In order to provide sanitary
    service to the new residences,
    Sandifer obtained a permit from the
    15 —369

    City to construct a
    6”
    sewer line which would run south on N.
    22nd Street about 245’ until it connected to the larger municipal
    sewer running east and west on Sycamore Street.
    Since it was
    necessary to avoid existing 36” and 42” storm sewers on N. 22nd
    Street Sand±ferwas permitted to install the sewer line at an
    initial depth of
    21
    to
    2 1/2’ or about
    6” above the storm sewers.
    As the 6” sewer approaches the Sycamore Street sewer it reaches
    a final depth of
    8’.
    Bangert alleges that he constructed an
    8” sanitary sewer in
    1957 in order to connect his residence to the City sewer system.
    He was required to conform to all applicable municipal codes
    during construction of the
    8”
    sewer line.
    Because of the enforce-
    ment of municipal codes in 1957, Bangert claims that he has been
    discriminated against by municipal actions in regards to the 6”
    sewer line installed by Sandifer,
    Respondent admits that it allowed installation of the 6”
    sewer line without an Agency permit.
    The reason given for this
    violation is that Respondent was not aware until May 15, 1973
    of the requirements of Rule 901(b) (2)
    of the Water Pollution Control
    Regulations.
    In December 1972 Bangert complained to Allen VanDeBoe,
    Superintendent of Sanitation, that he did not have access
    to the
    sewer for the lot he intended to improve.
    After studying the
    problem the Sanitation Committee informed Bangert that he could
    build
    a house on the lot and connect the sewer.
    If connection was
    made the City would assume maintenance responsibilities for the
    sewer.
    Respondent states that it did not hear from Bangert again
    until he appeared at a May 10, 1973 Committee meeting to voice
    his complaint about the sewer.
    The Committee again reviewed the
    problem and, on May 11,
    1973,
    sent Bangert a letter informing him
    of the Committee’s decision to allow connection to the sewer.
    Since
    the lateral sewer would be nearer the surface than normal,
    Bangert was required to encase the lateral sewer in concrete where
    it was located under pavement.
    This requirement was necessary to
    prevent future damage that might be caused by vehicular traffic.
    Cost for the lateral sewer,
    concrete encasement, and any
    damage to the roadbed or curbing was to be borne by Bangert.
    The
    letter also informed Complainant that the lateral sewer would have
    to be installed immediately since the City would be resurfacing
    N.
    22nd Street within two weeks.
    A City ordinance prohibits opening
    a street for a period of five years after resurfacing.
    15—370

    —3—
    On May 15, 1973 a meeting was held between Bangert, an
    EPA employee, and representatives of the City.
    Respondent
    states that it was at this meeting that it first learned of
    the permit requirements.
    The next day Respondent submitted
    its construction and operating permit application to the
    Agency.
    Rule 931(a)
    of the Water Pollution Control Regulations
    authorizes the Agency to adopt “criteria for the design, operation
    and maintenance of treatment works and waste water sources”.
    Pursuant to this authority the Agency has adopted Recommended
    Standards for Sewage Works, Great Lakes--Upper Mississippi River,
    Board of State Sanitary Engineers,
    Revised Edition 1971
    (also
    known as the Ten States Standards).
    In reviewing Respondent’s operating permit application the
    Agency considered three sections of the Ten States Standards
    in conjunction with Rule 921(b) of the Water Pollution Control
    Regulations.
    The three sections considered were:
    Section 25
    No sewer shall be less than
    8”
    in
    diameter
    Section 25.1
    In general, sewers shall be sufficiently
    deep so as
    to receive sewage from
    basements and to prevent freezing
    Section 26.1
    -
    Manholes shall be installed at the end
    of each line;
    at all changes in grade,
    size or alignment;
    at all intersections.
    Rule 921(b) provides that “the Agency shall not grant any permit...
    unless the applicant submits adequate proof that the...sewer...
    either conforms
    to the design criteria promulgated by the Agency
    under Rule 931,
    or
    is based on such other criteria which the
    applicant proves will produce consistently satisfactory results”.
    After reviewing data in the permit application, the Agency
    concluded that the
    6”
    sewer would “produce consistently satis-
    factory results” and thus conformity with Section
    25 requirements
    were not deemed necessary for the “as built” sewer.
    Section 25.1 does not establish an absolute requirement that
    all sewers be constructed to receive sewage from basement sewers.
    The Agency interpreted Section 25.1 to mean that circumstances could
    exist that make such construction unfeasible.
    Existence of the two
    storm sewers was,
    in the Agency’s opinion, such a “circumstance”
    therefore the provisions
    of Section 25.1 were waived.
    15—371

    —4--
    As to Section 26.1,
    the Agency concluded that the existence
    of
    a “clean out” was sufficient in this case to allow deviation
    from that requirement.
    The record shows that the Agency subsequently issued an
    operating permit for thiS
    6” sewer but denied the construction
    permit.
    Special conditions attached to the operating permit
    required that service not be extended to more than three residences
    and
    tl~et
    the City assume maintenance of the sewer.
    The reason
    g.
    ai~.
    ~or
    denying the construction permit was that the sewer had
    already been
    constructed and that no modifications were planned.
    VanDeBoe testified that two options were avilable to Bangert.
    If
    a house without basement is constructed, normal engineering
    standards would require that fill dirt be brought in to insure
    that the top of the foundation
    is at least
    1 1/2’
    above curb level.
    Then a lateral sewer could be installed from the house to the 6”
    sewer because the
    6” sewer is
    30” below the surface and the re-
    quired slope of 1/2” per foot could be met.
    If Complainant desired to construct a house with basement
    he would be required to install a force pump since the outlet
    from basement drains or sanitary facilities
    in the house would
    be below the level of the 6”
    sewer.
    Bangert testified that he
    estimated the cost of such pump to be at least $5,000.
    Bangert states that he did not install the lateral sewer
    because
    a plumber had informed him that the sewer could not
    adequately handle the waste load.
    According. to the Agency
    comment this issue was investigated thoroughly
    at the time
    Respondent’s permit was being reviewed.
    This investigation revealed that the sewer, with a slope
    of 1.31,
    would be able to carry 411,000 gallons of sewage per
    day.
    Using three houses with four persons per house and a factor
    of 100 gallons of sewage per person per day the Agency calculated
    an average flow of 1200 gallons per day.
    Peak
    flow through the
    sewer would be 9,600 gallons per day (peaking factor of
    8).
    Using these figures the Agency concluded that the 6” sewer would
    produce consistently satisfactory results.
    Conformity with the
    8” diameter requirement was not deemed necessary for this
    “as
    built” sewer.
    Complainant argues that one of the houses now served is a
    day nursery housing six or more children in addition to the four
    residents,
    The other house has four residents.
    Using these
    population figures instead of the Agency’s 4-to-a—house figure,
    15—372

    —5—
    Complainant believes that he cannot be expected to receive
    adequate service.
    However, when the Agency factors are applied
    using Complainant’s population figures,
    it can be determined
    that the average daily flow from these
    two houses would be 1400
    gallons and the peak flow would be 11,200 gallons per day.
    These
    flow rates are substantially less than the capacity of the 6”
    sewer.
    Therefore,
    using Complainant’s own figures
    to calculate
    flow rates the Board is simply unable to find any basis to support
    Complainant’s charge of inadequate capacity.
    Complainant next argued that the correct length of the
    6”
    sewer is 232’
    instead of 245’.
    No measurements were ~ubmitted
    to prove this claim and,
    even
    if
    such evidence existed,
    it
    appears to have little or no bearing on the issue.
    Complainant
    claims that the true initial depth is 1.6-2.0 feet instead of
    2.0-2.5 feet.
    Again,
    no basis is shown for this testimony.
    Complainant also claims that the 36” and 42” storm sewers are
    inadequate, cause water to back up in certain yards, causes
    muddy and mosquito infested areas,
    are rat harbors and should
    be replaced.
    Although Complainant claimed to be able to produce
    photographs and corroborating testimony to support these two
    claims, the record contains only his statement.
    Complainant claims that the 6”
    sewer does not have
    a man-
    hole as required.
    The record shows that
    a “clean out” was pro-
    vided.
    VanDeBoe testified that the City has several pieces of
    equipment capable of maintaining the sewer through the “clean
    out” but no problems have been encountered with the sewer to
    date which required use of this equipment.
    During his testimony Complainant alluded to the existence
    of a second permit which contained conditions different from
    the permit of record (Respondent Exhibit 4~l). Although the
    Hearing Officer allowed Complainant 14 days in which to produce
    the second permit,
    the only permit
    in the record
    is that sub-
    mitted by Respondent.
    A number of other allegations or claims by Respondent are
    contained in this record.
    Having reviewed these allegations
    it is our opinion that they are not directly relevant to the issue
    or are not supported by evidence.
    The record shows that Respondent installed the sewer in
    question withou permit.
    However, upon being advised of its
    mistake the City promptly moved to correct the mistake.
    Upon
    receiving the permit application the Agency determined that
    criteria deviations
    in the sewer were relatively minor and not
    15
    —373

    —6—
    substantial enough to require reconstruction.
    If the City were required to reconstruct the sewer line
    a recently resurfaced street would have tôbe
    ripped, up and
    traffic
    would have to be rerouted.
    Cost to the City would be
    about $10,000.
    The Agency doubts that such reconstruction
    would enable a house with basement to be served.
    If the
    6” sewer were to be installed under the storm
    sewers it would apparently have to be at
    a depth of
    10’
    or 11’.
    A pump would then be required to lift sewage for a proper
    connection with the Sycamore Street sewer main.
    The Board has some sympathy for Complainant and can under-
    stand his feelings since he was forced to follow the City code
    to the letter and his neighbor was not.
    However, Complainant
    was given two opportunities to connect his lateral sewer to the
    6”
    sewer and on each occasion declined the opportunity.
    We
    believe the City’s offer was reasonable in light of the circum-
    stances and that there is little else that the City could have
    done.
    It is the finding of the Board that Respondent did allow
    installation of a sewer line without permit in violation of Rule
    901(b) (2)
    of the Water Pollution Control Regulations.
    This
    violation was not intentional, did not cause any environmental
    damage and was promptly corrected once Respondent was informed
    of the error.
    Based on the record before us, we believe that Respondent
    sought to rectify the mistake in a reasonable manner.
    We also
    believe that the Agency decision to issue an operating permit for
    the sewer was justifiable under the circumstances.
    We further
    find that the actions of Respondent have not caused discrimination
    to Complainant to
    a degree that will require the existing sewer
    to be reconstructed.
    We shall order Respondent to cease and
    desist from further violations
    of the type found in this proceeding.
    ORDER
    It is the order of the Pollution Control Board that City of
    Quincy shall cease and desist from further violations of Rule
    901(b) (2)
    of the Water Pollution Control Regulations.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certfy the above Opinion and Order was adopted
    this
    ~4\
    day of~Qj1~M~
    ,
    1975 by
    a vote of ____to ~
    15 —374

    Back to top