ILLINOIS POLLUTION CONTROL BOARD
January
23,
1975
MISSOURI PORTLAND CEMENT COMPANY,
Petitioner,
vs.
)
PCB 74—407
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr.
Henss)
On
January
9,
1975
the
Board
granted
Petitioner
an
Interim
Extension
of
Variance
to
and
including
January
31, 1975 so that
Petitioner could continue operations pending receipt of the
Agency Recommendation and Board consideration of
the merits of
a requested three month variance extension.
Variance from Rules 203(b)
and 203(d) (3) of
the Air Pollution
Control Regulations was originally granted Missouri Portland on
June
6,
1974 in PCB 73-480.
This variance was granted for the
purpose of allowing Petitioner sufficient time to complete in-
stallation and testing of an electrostatic precipitator on kiln
~l
at Petitioner’s Joppa, Illinois cement manufacturing plant.
Missouri Portland now seeks a three month extension of
variance in order to complete the electrostatic precipitator
project.
Bruce Kester, Petitioner’s Vice President-Environmental
Systems, submitted an affidavit showing that installation of the
electrostatic precipitator has been delayed beyond the direction
and control of Missouri Portland by the following events:
a)
The
precipitator parts were not delivered until
late July,
1974.
To accelerate completion, Missouri
Portland Cement Company caused assembly to begin
at ground level in August of
1974, because certain
essential structural st~elwas not delivered on
schedule.
b) The structural steel was not received until
August,
1974.
Erection of the structure began
immediately and is still in progress.
c) The necessary duct work components could not
be delivered before late December,
1974 and
installation, therefore,
could not be started
before January of 1975.
15 —325
—2—
d) The fan and drive component for the precipitator
cannot be delivered before
February.
This
installation
will,
therefore,
be delayed until March of 1975 with
completion scheduled for April,
1975.
e)
The dust screws for the precipitator could not be
delivered until January,
1975, and installation cannot
be completed before April
1,
1975.
f)
The electrical equipment and supplies could not be
delivered until late October or November,
1974 and in-
stallation cannot be completed before March,
1975.
Petitioner has kept the Agency advised of progress and delays
throughout the term of the original variance.
Kester states that
Petitioner has taken all steps possible to accelerate installation
compatible with the late delivery schedules.
If no further delays
are experienced, Petitioner will shut down kiln #1 on March
1,
1975
and complete installation of the electrostatic precipitator before
restarting kiln
1f1.
During proceedings on the original variance,
a number of
Petitioner’s neighbors complained strongly about emissions from
the plant.
Agency interviews
relative tothe instant case indicate
that conditions have not changed as far as
these citizens are con-
cerned.
However,
the Agency believes that the impact upon these
citizens because of Petitioner’s emissions will be reduced once
the electrostatic precipitator is in operation.
Although the Agency recognizes that delay in completion of
the project is beyond the control of Petitioner,
they believe that
the time requested by Petitioner is excessive.
It is
the Agency’s
opinion that Missouri Portland should not be given any time beyond
the March
1,
1975 shutdown date particularly in light of the
citizen’s comp1aints~
If Petitioner is actually planning to shut the kiln down on
March
1,
1975 in order to complete the tie-in with the electrostatic
precipitator systems, there would be no reason to grant the variance
for an additional month.
Petitioner has not indicated that in
plans to operate this kiln on an intermittent basis while the tie-in
is taking place and we seriously doubt whether operations
could
continue during March even on an interim basis.
The Agency recommends denial of variance or in the alternative
that variance be granted only until March 1,
1975 subject to certain
conditions.
—3.-
The record clearly shows
that Petitioner is going to shut
the kiln down on March
1,
1975
and
the Board
is not inclined
to allow the variance to extend beyond that date.
Compliance
with the Regulation after March
1,.
1975 will not cause an
arbitrary and unreasonable hardship.
Variance will be granted
to and including March
1,
1975 on which date Missouri Portland
will he required to cease uncontrolled operations of its kiln #1.
This Opinion constitutes the findings
of fact and conclusions
of
law
of
the
Illinois
Pollution
Control
Board
with regard to the
appLication for a three month extension of variance~
ORDER
It is the Order of the Pollution Control Board that Missouri
Portland Cement Company be granted variance from Rules 203(b)
and
203(d) (3)
of
the Air Pollution Control Regulations
to
and in-
cluding March
1,
1975.
This variance is subject to the following
conditions:
1) Conditions
1 through
5 of our Order in PCB 73-480 shall
remain in effect through the term of this extended
variance.
2)
Within 15 days of this Order, Petitioner shall submit
its time table for completion
of the electrostatic
precipitator and stack test to the Environmental Pro-
tection Agency.
3)
Petitioner shall not operate kiln #1 in an uncontrolled
manner after the expiration date of this variance
except as may be authorized by the Environmental Pro-
tection Agency pursuant to Rule
105 of the Air Pollution
Control Regulations.
4) Petitioner shall use a continuous monitor attached to the
electrostatic precipitator as imposed by Part 1 of the
Board Order in PCB 73-480 throughout the term of this
extended variance.
The new electrostatic precipitator
shall use said monitor in the same fashion
as. described
in Exhibit B of the Board Order in PCB 73-480.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
~3R~
day
~
1975 by
a vote of ~toQ.
15—327