ILLINOIS POLLUTION CONTROL BOARD
December 19,
 1974
A.?. GREEN REFRACTORIES
 CO.
PETITIONER
 )
)
 PCB
 74—163
ENVIRONMENTAL
 PROTECTION AGENCY
 )
RESPONDENT
 )
MR.
 JAMES
 PEACOCK,
 ATTORNEY,
 in
 behalf
 of
 A.?.
 GREEN
 REFRACTORIES
MESSRS.
 JOHN
 PALINSCAR
 and
 WILLIAM
 A.
 ERDMAN,
 ATTORNEYS,
 in
 behalf
of
 the
 ENVIRONMENTAL
 PROTECTION
 AGENCY
OPINION
 AND
 ORDER
 OF
 THE
 BOARD
 (by
 Mr.
 Marder)
This
 action
 involves
 a
 request
 for
 variance
 filed
 on
 April
 26,
1974.
 The
 Board
 on
 May
 2,
 1974,
 ordered
 more
 information
 so
 as
 to
allow a more reasoned decision.
 Petitioner on June 10, 1974, sup-
plied such additional information which fulfilled the Board’s re-
quirements.
 Relief was requested from Rules
 202
 (b),
 203
 (b)
,
 203
(f),
 and 204
 (f) (1) (A)
 of the Board’s Air Pollution Regulations, as
they apply to Petitioner’s facility.
Petitioner owns and operates in Morris, Illinois, a facility for
the mining of raw clay as well as associated unit operations such as
crushing,
 grinding,
drying,
 and mixing.
 Materials produced are used
basically in the steel and foundry industry.
 It is alleged that the
nearest alternate source for such material is located in Southern
Ohio and Missouri.
 The facility engages in strip mining on site to
supply approximately 81.2
 of its raw material.
 Mining is carried
out by the use of dozers, drag crane, and scraping equipment.
 It is
alleged that water sprays are utilized to minimize fugitive dust.
Mined material is then passed through a roll crusher to reduce its
size to less than 2”
 in
 diameter..
 Material so crushed is then trans-
ported via conveyor belts
 to the central grinding department.
 Mater-
ial is then passed through pan grinders to reduce the particle size.
This
 is then bucket
 conveyed
 to
 a
 screening
 and
 rotary
 drying
 opera-
tion.
 A selected portion of the screened material is sent to the drier
for admixing with undried material or to be used to generate a separate
 end product.
 Approximately 21.6
 (15,561 tons) of total grinding
throughput was dried.
 Transference from the screening operations
 to
either bulk loads
 or other production areas in the plant takes place.
These transfer points are allegedly controlled by means of a fabric
filter baghouse.
A percentage of the material from the grinding department
 is con—
‘4—693
—2—
veyed
 to
 the
 “Castable”
 department.
 Material
 is
 then
 passed
 through
two
 rotary
 dryers
 as
 needed.
 Material
 is
 then
 mixed
 and
 transported
for
 shipment.
 Other
 materials
 from
 the
 grinding
 operation
 are
 diverted
to
 the
 “Hendryx”
 Building,
 which
 is
 essentially
 a
 material
 handling
facility.
 The
 final
 portion
 of
 ground
 material
 is
 diverted
 to
 either
the
 sleeve
 press
 or
 fireplace
 brick
 facilities.
 Both
 of
 these
 opera-
 tions entail drying and firing operations
 (via a kiln).
 A detailed
flow sheet for the above operations has been submitted verbally in
“Appendix A”
 to the Petition and schematically in Drawing #ll6F-7 ap-
pended
 to
 the
 Petition.
Emissions
 are
 generated
 at
 various
 points
 along
 the
 process.
 Trans-
ference and packaging operations give rise to fugitive dust problems,
while dryers generate particulates.
 The kilns, due to the high oper-
ating temperature and composition of feed,
 emit SO2 as a product of com-
bustion.
The main emission sources at the facility are as follows:
Source
 Type Emiss-
 App. Rule
 Allow.
 Estimated
Emiss ions
 ions
Crush. Dept.
Dryer
800-890#/hr.
 Particulate
 203
 (a)
 l2.5#/hr.
Castable Dept.
Dryers
600-700#/hr.
 Particulate
 203
 (a)
 4.144t/hr.
Crush.
 Dept.
Dryer
SO2
 4960 ppm
 204(f) (1) (A)
 2000 ppm
An initial hearing was held, on August 13, 1974,
 at which time a ten-
tative stipulation was entered into between the parties.
 This situa-
tion was,
 at a later date (10/30/74), followed with two joint stipula-
tions which are at the heart of this matter,
 and will be discussed lat-
er in this Opinion.
At the August 13, 1974, hearing, Mr. Noell
 (plant manager) discussed
the location and staffing of the plant.
 The facility has approximately
88
 employees
 (R.
 16)
 and
 is
 located
 on a 900-acre site which is rela-
tively
 isolated
 from
 residential
 structures.
 Mr.
 R. Besalke
 (mgr. en-
vironmental control) appeared to briefly discuss Petitioner’s attempts
at compliance.
 One major point raised at this hearing is that by stip-
ulation the variance request for Rule 203
 (f) was withdrawn,
 as no evi-
dence of fugitive dust violations were found or anticipated.
 The Aug-
ust 13 hearing was then adjourned to allow time for submittal of a new
stipulation.
The
 second
 hearing
 was
 held
 on
 October
 30,
 1974,
 at
 which
 time
 new
stipulations
 were
 presented.
 The
 highlights
 of
 said
 stipulations
 are
as
 follows:
14
—
694
—3—
1.
 Continuing investigation of methods to control emiss-
 ions
has resulted in
 a new compliance plan.
2.
 The new compliance plan would,
 in the opinion of the
parties, abate the particulate and SO2 emissions.
3.
 The present drying operation in the grinding depart-
ment will be discontinued.
4.
 A 100 ft. by 140
 ft. structure shall be installed to
eliminate the artificial drying method at a cost of
$95,000.
The parties agree that the above plan: will eliminate all slurry and
water
 problems
 (which
 would
 be
 generated
 should
 a
 scrubber
 be
 used);
will
 eliminate
 all
 SO2 emissions; will conserve fuel for said dryer;
and
 be
 technically superior.
The parties suggest compliance will be accomplished by April
 1,
1975.
This
 plan
 also,
 calls
 for
 the
 installation
 of
 a
 fabric
 collector
 to
control
 emissions
 for
 the
 two
 rotary
 dryers
 in
 the
 castable
 building
according
 to
 the
 following schedule:
Purchase and order of equipment
 11/15/74
Erection contract
 12/31/74
Delivery
 4/15/75
Completion of installation
 5/15/75
Compliance testing
 5/30/75
Operational
 5/30/75
A second stipulation cites conditions which would be acceptable
should the Board grant variance.
To determine whether the Board should accept the above stipulation
as the basis
 for a variance, we must explore environmental impact and
hardship to Petitioner.
Environmental impact:
 As mentioned above, Petitioner’s facility is loc-
ated in a sparsely-populated area.
 The
closest resident is 3/4 mile from
the source,
 and the next closest resident is
 1 1/2 miles from the source
(R.
 22).
 A major alleged source of particulate emission was shut down
on April 11, 1974, when
 the
 Grundy facility ceased operation.
 Although
there is no evidence as to actual emissions that emanated from this
(Grundy) plant, Mr. Noell testified that by visual observation emissions
were large
 CR.
 20).
 Mr. Noells further testified that to
his
knowledge
he knew of no citizen complaints regarding the facility
 (R.
 20).
 It is
the Board’s feeling that the environmental impact of Petitioner’s emiss-
ions would be minimal.
Hardship:
 Petitioner alleges that failure to receive a variance would
result in a
shutdown of
Petitioner’s
facilities.
 The Board again reiter-
ates
its
 opinion
 that
 failure
 to
 grant
 variance
 is
 not
 a
 shutdown
 order,
but
 rather
 a
 shield
 from
 prosecution.
 The
 hardship
 then
 is
 exposure
 to
a threat of prosecution.
 Should Petitioner’s facility be shut down, Pet-
itioner alleges a potential loss of 88 jobs and loss of $572,000
 in
 corn—
14
—
 695
—4—
munity income.
 Although the hardship case is minimal, in light of the
minor environmental damage and a viable compliance plan, the Board will
grant variance.
The
 Board’s
 variance
 will
 be
 specifically
 limited
 to
 those
 operations
which
 are
 covered
 by
 compliance
 plans.
 We
 have
 no
 way
 of
 knowing
 wheth-
er a variance is required for Petitioner’s kilns, nor were we presented
with a compliance plan should such variance be needed.
This Opinion constitutes the findings of fact and conclusions of
law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that:
1.
 Variance is granted from Rules 204(f) (1) (A),
 202(b),
 and
203(a)
 as it applies to Petitioner’s crushing house and
grinding department until April
 1, 1975.
2.
 Variance is granted from Rule 202(b)
 and 203(a)
 as it ap-
plies to Petitioner’s castable building until May 30,
 1975.
The above variances are conditioned on the following:
1.
 Within
 50
 days from the date of this Order, Petitioner shall
post a performance bond with the Agency at 2200 Churchill
Road, Springfield,
 Illinois,
 62706,
 in the amount of $10,000.
Said bond shall guarantee installation of equipment
 as de-
tailed in the November 30,
 1974,
 Stipulation as agreed by
both parties.
2.
 Petitioner shall submit bi-monthly progress reports to the
Agency at the above address.
 Such reports shall contain as
a minimum a summary of progress made towards installation of
the six-bay storage shed and fabric filter collector,
 as well
as copies of all documents, purchase orders, or agreements
pertaining to this compliance plan.
3.
 In the event of unavoidable delay, Petitioner shall notify the
Agency as soon as possible.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board,
 certify that the above Opinion and Order was adopted by the
Board on the
 19th
 day of
 December
 ,
 1974, by a vote of
 4
to
 p
 .
 .
14
—
 696