ILLINOIS POLLUTION CONTROL BOARD
January 9, 1975
MISSOURI PORTLAND CEMENT COMPANY,
Petitioner,
vs.
)
PCB 74—407
ILLINOIS ENVIRONMENTAL PROTECTION
AGENCY,
Respondent.
ORDER OF THE BOARD ALLOWING INTERIM EXTENSION OF VARIANCE (by Mr. Henss):
On June 6, 1974 in PCB 73-480 we granted Petitioner a variance
from Rule
203(b)
and 203(d) (3) of the Air Pollution Control Regu~-
lations until January 1, 1975 for the purpose of installing and
testing an electrostatic precipitator on No, 1 kiln at its Joppa,
Illinois cement manufacturing plant. The variance provided that
the plant shall not operate after January 1, 1975 without an
electrostatic precipitator. Subsequently, Petitioner requested a
three month extension of the variance, representing that construction
delays beyond Petitioner’s control would prevent compliance with
the January 1, 1975 deadline. Under the time limitations established
by the Environmental Protection Act the Board must rule on the new
variance request by January 28, 1975. The Environmental Protection
Agency
has not yet filed its Recommendation and therefore the Board
finds that it is unable to advance its time schedule and make an
earlier determination in this case.
Missouri Portland Cement Company now requests an interim
extension of variance during the month of January 1975 until the
Board can make its final decision. Unless an interim variance is
allowed Petitioner may be required to close down the facility prior
to the time the Board can consider the merits of the original petition.
Petitioner’s request is supported by the necessary affadvait
and sufficient detail so that we can allow a short interim variance.
It appears that Missouri Portland Cement Company has made a good
faith effort to comply with its construction schedule and that the
delays in construction are beyond its control. The delays were
brought about by the following circumstances and conditions:
15
—
217
a)
delay of six weeks in general contractor’s
fabrication and erection schedule due to
delay in
receipt of
structural steel and
steel plates.
h)
delay of eight: weeks caused b delay in
shipping
of fan motor and associated switch
gear ordered on April,
:L974,
c) dela.y of eight weeks in delivery of pre—
cipi tutor.
Missouri Portland has kept the EPA advised of the delays and the
possible effectS on the time schedule for construction
and
operation
of
the precipitator.
The EPA has not responded to Petitioner’s
Application for
Interim Extension of Variance.
Under the circumstances, we accept
as true the pertinent facts stated by Petitioner,
and find that
an unreasonable hardship will he created for Missouri Portland
and its employees
if
the interim extension of variance is not
granted.
The interim extension of variance will be allowed
to
and
including January
31, 1975.
This Opinion constitutes
the findings of fact and conclusions
of law of the Illinois Pollution Control Board with regard to the
application for interim extension
of variance.
ORDER
It is
the Order of
the PoliUtjOfl Control Board that
Petitioner’s Joppa plant be granted variance from Rule
203(h)
and Rule 203(d) (3) of the Air Pollution Control Regulations to
and including January 31, 1975. Conditions 1 through 7 of our
Order entered in PCB 73-480 shall remain in effect.
I, Christen L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
~
day ~
,
1975 by a vote of ~ to 0
—
15--
218