ILLINOIS
    POLLUTION
    CONTROL
    BOARD
    anu~~ryI~,
    I
    ENTRAL
    OUPAGE
    HOSPITAL ASSOCIATION
    ?CR
    74— :64
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    Respondent
    IN1~1MOPINION of the B3ard
    (by Mr.
    Dumefle):
    This Opinion
    is
    in support of
    an ORDER granting the sewer connection
    and issued
    on
    ~ovember
    22,
    1974.
    Petition for variance
    to permit
    a sewer connection
    to the Village of
    Wirifield sewage treatment plant
    in DuPaqe
    County was
    filed on October
    9,
    1974.
    No public hearing was held.
    The
    Environmental
    Protection Agency filed
    its
    recommendation
    on
    November 18,
    1974 and recommended
    a grant of the variance instanter.
    On
    November 19,
    1974, just three days before
    the Board made its decision, the
    Petitioner moved that the matter be decided
    on November 22 because of the
    expiration of bids on November 30.
    The variance petition asks for relief from Sections
    12 and 39 of
    the
    Environmental Protection Act and Rule 927 of Chapter 3 (which are the Water
    Pollution Regulations of the Board).
    The Central
    DuPage Hospital
    Association
    (“Hospital’) operates
    a 241-bed hospital
    on
    a 40-acre site in Winfield.
    Its
    primary service area contains
    in excess of 100,000 residents in central,
    western and northern DuPage County.
    Average occupancy in
    the hospital
    for the first half of 1974 was 90.3
    and
    at times
    all
    beds were occupied,
    it
    is
    alleged.
    In
    1972,
    the petition states,
    an addition of 150-beds was planned
    of which
    112—beds were to be installed and
    staffed.
    Fees and expenditures of some ~80O,O0O
    were incurred for this project.
    A
    refinancing of debt and fundinq
    for the addition of $20,000,000 was secured
    through
    the Illinois Health Facilities
    Authority.
    Construction of the addition
    is
    scheduled to
    begin November 1974.
    The fol-
    lowing schedule
    is planned.
    New Facilities
    in operation
    November 1976
    40-bed unit staffed
    -
    November 1976
    ~~ccpd40—ced
    ~.nit
    staffed
    )urinq 1977
    ~
    r
    nts
    15—205

    The Village of Winfield was unable to provide sewer service to the
    Hospi~land had hoped that the Board’s DuPage Regionalization pr~eedings
    (R 70—17) would bring
    a solution,
    The Board
    issued
    its Order in R 70-17
    on August 29, 1974 and
    its Opinion
    on September 27,
    1974.
    West Chicago,
    which was designated as
    one of the major treatment plants and was to have
    accepted Winfield’s wastes,
    has appealed the DuPage Regionalization regu1a~
    tion to the Appellate Court.
    Consequently it is not known how long
    it
    wilt
    take to resolve the legal questions raised.
    The Winfield sewage treatment plant
    is said to be “hydraulically and
    organically overloaded”.
    The hospital alleges
    a bid ex~irationdate of
    November 30,
    1974 but speaks of the necessity to enter into
    a firm construc-
    tion contract before October 31, 1974,
    a date since passed.
    The Agency’s
    recommendation
    is for
    a grant of the variance.
    The
    Agency asserts that the Winfield sewage plant, designed for 0.5 million
    gallons per day (MGD), averaged 1.61 MGD for the period from August
    1972
    through July 1973.
    Bypassing of sewage occurred during 11.3 days per month
    in the average
    in
    this same period.
    The average daily amount bypassed was
    1.86 MGD which
    is
    in excess of flow through the plant.
    As to the need for the hospital beds
    in northern DuPage County,
    the
    Agency states that the total
    hospital bed need
    is 818 beds and only 633
    beds are now in existence,
    leaving
    a need of 185 as delineated
    in the Health
    Facilities Plan issued by the Comprehensive State Health Planning P.gency.
    A letter was received by Board
    on November 20, 1974 from the President
    of the DuPage County Comprehensive Health Planning Agency.
    It pointed out
    that the 185-bed “need” cited above was based upon 1972 data and that a 291-
    bed facility was under construction in Downers Grove.
    The letter went on
    to state that its Board of Directors could not make
    a formal recommendation
    until January 8,
    1975.
    This of course, would be well past the November 30
    date for expiration of the bids.
    The Board feels that the record
    in this case
    is deficient.
    Neither the
    hospital
    nor the Agency delineate the damage,
    if any, caused by the constant
    bypassing of sewage to the West Branch of the OuPage River.
    The possible al-
    ternative of requiring holding tanks,
    as has been done in
    a dozen cases
    in
    the Rockford area,
    is not mentioned or discussed.
    Data for the Winfield plant
    end at August 1973 or 14 months prior to the date of the recommendation.
    We
    do not
    know the present extent of bypassing because of the lack of recent data.
    The alleged fact of the expiration of bids
    is not proven.
    We are not
    told when the bids were taken nor with whom or the amount.
    On
    the other hand,
    the 52,400 gallons per day of domestic waste will
    not
    flow, even partially,
    until
    November 1976 which
    is two years hence.
    With grant
    priority numbers
    for Winfield and West Chicago of 131 and 132 it seems reason-
    able that these projects will
    be funded soon and will proceed reasonably par-
    allel with construction of the hospital
    addition.
    15
    206

    4e c~.
    ~
    rule co
    the ne~d~or
    ~
    ~
    ~~ds
    t~r
    ~:he
    r~asonsgiuen
    i”~’e
    ~ut~heoverbu 1ding of ~
    ~‘
    beds
    is
    ~is’~
    risk which
    is
    ~nmarilvto ne carried by the Lert, ~lDuPa~e~tospi~a’
    ~~:oci~tton
    and one
    Ii y ~rew~‘ing to accept.
    The
    ariance is g~~ited
    on ~h~ ‘ncomplete record
    f
    the ‘mTnin~ntexpiration
    tr
    ds.
    ~e ~etair
    r
    stream ,~jdywithin 60 days
    as
    ielirea
    ~i
    n th~3rde~
    siso reoort on and th~Agency ~halI orrnLrt on the nece~~
    r
    no ~irg
    taNKs
    for this fac~i~t’
    narily because
    s~’rtionand require
    he ~iospital
    shall
    y and feasib lity
    T~iis(pinion consL~uLes~e Co~ros ~‘r~incs
    ~ ~
    ‘nd
    ~OflC~u5iOflS
    of
    Dr
    Odell dissents. Mr.
    Zeitlin aossaired
    I, Chr~stanL. Moffett, ~erk of the
    Itinois Pollution Controt
    Board,
    cetify that the above Opinion was adopted by
    the Board on the
    ~
    day
    ~
    1975,
    by
    a vcte of
    3
    to
    I
    ~stanL.Moffett,
    15—207

    Back to top