ILLINOIS POLLUTION CONTROL
    BOARD
    January
    3~
    1975
    COMMONWEALTH
    EDISON
    CO~
    PETITIONER
    PCB 74—16
    ENVIRONMENTAL PROTE CT ION
    AGENCY
    RESPONDENT
    MESSRS. RICHARD H. POWELL and CHARLES H. WHALEN, ATTORNEYS, ISHAM,
    LINCOLN & BEALE, in behalf of
    COMMONWEALTH EDISON
    MESSRS. MARVIN MEDINTZ and DELBERT HAS CHEMEYER, ATTORNEYS, in be-
    half of the PEOPLE OF THE STATE OF ILLINOIS
    MR.
    MICHAEL
    GINSBERG, ATTORNEY,
    in
    behalf of the ENVIRONMENTAL PRO-
    TECTION AGENCY
    OPINION AND ORDER OF THE
    BOARD (by Mr. Marder)
    This action involves a request for variance filed January 11,
    ~974, by Commonwealth Edison Co. (Edison), Petitioner, Relief is
    requested from Rules 203 and 204 of Chapter 2 of the Board’s Rules
    and Regulations as they apply to five Edison generating facilities.
    A request is also filed for relief from Rules 103 and 104 as they
    apply to project completion schedules and compliance plans. Edison
    filed a motion on October 11, 1974, seeking to clarify its position.
    The motion contended that, although it was not inherently clear in
    the Petition, relief was also requested from Rule 3-3,112 for three
    Edison stations until May 30, 1975. Said Motion asks that the plead-
    ings in 74—16 be deemed to include a request for variance from Rule
    3—3.ll2~. The Board finds that sufficient evidence has been generated
    at hearings to rule on a 3—3.112 variance as well as a 203 variance,
    and additional hearings would add nothing to
    our decision. The vari-
    ance
    pleading will thus be deemed amended as requested by Edison.
    At least in part, this case dates back to August 8, 1972, at which
    time the Board denied variance to Edison for its Waukegan and Sabrooke
    generating plants.
    Such denial was without prejudice and Edison re-
    filed for variance on January 30, 1973. The Board at
    that
    time grant-
    ed variance for six months, conditioning the variance on plant load-
    ing (variance granted until April 4, 1974)
    .
    This was followed by the
    filing of 74-11 on January 4, 1974, seeking a six~monthextension.
    Such variance was granted on Septeirier 27, 1974. The present variance
    seeks,
    in part, to again extend variance for one additional year. Th
    above deals only with the Sabrooke and Waukegan generating stations,
    whereas
    PCB74-16
    in total deals with
    five generating stations.
    As”,
    further background the reader
    is
    referred to
    the
    following Board
    15
    —7

    opinions:
    Commonwealth
    Edison Co. v. Environmental Protection
    Age~~
    PCB 72—91, 5 PCB 101; PCB 72—491—492, 73—40, 9 PCB 367; PCB 74—li,
    13 PCB 235, 13 PCB 241, and PCB
    74—li, Septer~ber27, 1974,
    The instant Petition was filed on January 11, 1974. The separate
    facilities were consolidated for hearing in a rather unique manner.
    It was the Board~s feeling that much of
    the
    information to be generated
    would be applicable to all facilities.
    However, it was also mandatory
    to hold hearings in the areas to
    he affected by their variance requests.
    This was done to allow the public the opportunity to participate at
    hearing. Twenty days of hearings were held as follows:
    April 2,3,5,8,9, 1974
    at Chicago
    April 15, 16, 1974
    at Waukegan
    April 18, 1974
    at Rockford
    April 22, 1974
    at Joliet
    April 25, 1974
    at Kincaid
    April 29, 1974
    at Chicago
    May 7,8, 10, 20, 1974
    at Chicago
    June
    5,7,20,
    1974
    at Chicago
    July 9, 11, .1974
    at Chicago
    At these hearings the Board feels that a complete record was entered
    in this matter.
    This Opinion will handle system—wide information first, and then
    apply this evidence to individual plant evidence in making its decis-
    ions. Before proceeding it: is imperative to tabulate as much data as
    possible on the subject units. Table 1 includes such data as incorp-
    orated in this Opinion.
    Statement of Hardship: Edison contends that the hardship which
    would be incurred should variance be denied would fall not only on it-
    self but on its customers as well. This contention is based upon the
    premise that should variance be denied, Edison would be compelled to
    cease operations. This is not true, as pointed out by the Board and
    reiterated many times over (e.g., Androck Corp. v, Environmental Pro-
    tection Agency, PC3 74-3; 48 Insulation v, Environmental Protection
    Agency, PCB 7 3-478 E.I. duPontv~ Environmental P~tect~Aency,
    PCB 73-533), failure to grant variance is not a shutdown order but
    rather a shield from prosecution. Thus Edison’s true hardship, should
    variance be denied, is nothing more than being left open to an enforce-
    ment action. Edison, of course, has the option of shutting down cer-
    tain equipment to avoid prosecution, and this course of action would
    cause hardship on Edison’s customers who depend on a steady flow of
    electricity. To assess the potential hardship one must investigate
    the Edison system as a unit, looking at total capacity as well as re-
    quired maintenance outages.
    The Edison system (in 1974) has a total capacity of 17,066 mw. This
    breaks down as follows:
    1. 14,016 mw of fossil and nuclear power.
    2. 1,726
    mw of fast start peakers.
    3. 1,324
    mw of purchased power.
    15 —8

    17,066 mw (Appelgren Ex. 3)
    This capacity, due
    to
    ups and downs of
    the various equipment and
    dif-
    ferentials
    in sales and purchases of power through diverse exchanges,
    shifts almost constantly.
    The above
    figures are best used for a guide,
    and items (1) and (2) above reflect actual installed capacity.
    Edison projects growth in its peak demands
    as
    well as growth in its
    total system. Since these figures seem to change constantly, the Board
    will not try to assess the validity of these numbers at some future date,
    but will rather deal with the supply and demand in the period which this
    variance request would cover. The peak load during 1975 (the area of
    major concern to this proceeding) is projected at 14,900 mw. Projected
    capacity for 1975 is 16,423 mw. All of these estimates lead to Edison~s
    projections that, based on a 14 minimum reserve capacity, 1974 would
    show a reserve of 909 mw, while 1975 would show a deficit of 392 mw
    (Appeigren Ex. 4).
    There is much discussion as to the validity of these numbers and
    the Board concludes that if different bases are used, many different
    estimates can be reached.
    A typical example of this type of projection of numbers can be seen
    from examination of Appelgren Ex.
    1
    and 4, wherein growth in peak load
    is given and projected. Edison projects growth in peak load between
    1974 and 1977 as 6.05, 7.6, and 7.5 respectively. The following
    history can be determined from simple mathematics on the above exhibits:
    Year
    Actual Peak Load
    Growth in Peak Load
    MW
    Percent
    1968
    8950
    1969
    9265
    3.5
    1970
    10,027
    7.6
    1971
    10,943
    9.1
    1972
    11,750
    6.9
    1973
    12,462
    5.7
    1974
    14,050
    12,7
    1975
    14,900
    6.1
    1976
    16,030
    7.6
    1977
    17,230
    7.5
    The projected increase in peak load between 1973 and 1974
    is
    thus pro-
    jected at a very high 12.7. Mr. Appelgren (R. 75) states that the 1973-
    1974 winter loads were 400 to 800 mw below what Edison anticipated,
    therefore casting even greater
    doubt
    on Edison~s projections.
    While there are many other factors which must be considered when ass-
    essing figures of this nature (e.g., purchases, sales, maintenance out-
    ages), a detailed description of how these numbers were generated was
    not afforded the Board. We can only go by past growth rates and actual
    1974 load demand to project what future demands may require. The Board~s
    conclusion on this
    subject is that Edison~s estimates are significantly
    above
    what will actually occur, and Edison~s fear of a serious hardship
    on its customers should certain units be curtailed is simply unfounded.
    15—9

    P1~nt/enit
    Jo3.ct 5
    ~1,
    1950
    Joliet 6
    344
    1959
    J~iiet /
    617
    1965
    Jo1i~t 8
    617
    196(
    ~abr~ ~e 1
    20
    1949
    0
    R~ooke 2
    1
    34
    19~2
    Sabroo1~ 3 35
    .1953
    —-
    Sdhrooke 4 57
    1961
    Waikegan 5
    1
    129
    1931
    Wautegari 6
    119
    1952
    ~
    -—~——
    Waukegan
    ~
    1
    338
    1958
    Waukega:: 8 360
    Powe~ton 5 850
    Kincaici
    1
    616
    Coal
    Coal 11,481,952
    Coal 49,700
    Coal 113,052
    Oil
    N/A
    Oil
    N/A
    1,540,214
    Part.
    Emiss-1 Comp
    ions Plan
    0
    148k
    U,
    148
    148’
    400’
    336’
    450’
    450’
    MW
    TAW
    PCB74-16__Commonwealth Edison
    System Data
    ~Annua1
    5ta~tup Date Fuel Fuel Usage1 Part.
    Tons/Year Cont.
    ~
    ~‘———H——
    ~
    Coal ~341,398
    ESP 0.081
    Coal
    502
    Cont.
    Comp.
    Plan
    330 ,646
    ~T5a3id~T
    Comp.
    Exp.
    SoxIni,
    Stack
    Ht.
    L.S .C
    ESP
    0.15
    ~SO~1nj.
    L,S,CtlO/1/15 258’
    ESP
    LS C
    .06l—.7~
    LS C
    SOX
    Inj.
    ESP
    3/1/76 431’
    LS C
    .061— .7~
    LS C
    10/76
    SO
    In~.
    Mech.
    550’
    LSC
    LS C
    1.5
    Oil
    10/76
    Oil
    Oil
    Mech.
    On
    Oil
    550’
    148
    FEA
    prob.
    2.0
    Oil
    Oil
    Oil
    FEA
    prob
    On
    Coal
    Oil
    338,850
    Two
    ESP
    0.5 onSplit
    l.6S$ ductwk.
    coal SO.~Inj.
    Coal
    291,481
    Coal
    981,055
    LS C
    ESP
    ESP
    LS C
    12/1/7
    .29 on
    2.4 ~
    Inj.
    coal
    TT,’5’~
    off~’tNe~
    Hot
    LS coal~ ESP
    196,
    1~’72
    1967
    LS C
    LSC
    LS C
    LS C
    6/1/76
    17/1/76
    Coal
    .
    928,448
    ESP
    Coal 2,500,000 ESP
    ccl
    .1,316,616 FSP
    0,4 on SO~In. LSC
    LSC-SO3
    .027 In corn.
    .05
    In corn.
    In Corn.
    None
    None
    Gas
    G a~
    Late
    1980
    1982
    500’
    500’

    —4—
    Thus, the Board finds that placing operational
    constraints
    on units
    which impact on the environment will not create an
    undue
    hardship,
    and
    in our final Order we
    will
    do so,
    Further complicating the situation of availability is the area of
    maintenance, both planned and unexpected. Mr. Robert Engle (April 3,
    Pg. 422-434, April 8, Pg. 436-499) testified
    in detail as to how
    Edison
    plans
    for maintenance. Engle Exhibits
    1—4 were
    entered as documenta-
    tion
    as to Edison’s contentions on this subject.
    Edison contends that
    actual outages
    for its units are 41 (based on 1961-1973 data) greater
    than its planned outages (R, 422), Although
    on the surface this seems
    like horrendous planning, it must be understood that “unplanned” out-
    ages are actually anticipated when developing the system strategy.
    Engle Exhibit #2 then projects the expected outages for the 1974-
    1975 maintenance period and anticipates a net capacity deficit for the
    months of November, December, January, February, and March. This esti-
    mated deficit is including the capacity under question
    in
    the instant
    Petition. Edison then contends that during the difficult months, Edi-
    son would be forced to either institute voltage reductions or forestall
    the least critical maintenance (R. 429).
    In analyzing Exhibit
    2,
    one finds
    that the projected differences be-
    tween estimated overhaul and projected total outages is very much great-
    er than the 41 average depicted in Engle Exhibit 1. In fact, calcula-
    tions during this period reveal the following:
    Month
    Est. Overhaul
    Total Overhauled Percent
    MW
    Dec. ‘74
    1800
    5600
    211
    Jan.
    ‘75
    2500
    5600
    124
    Feb. ‘75
    2700
    5600
    107
    On their face
    these figures
    are completely out of context with Edi-
    son’s historical averages. On the basis of information given
    to
    the
    Board, we can only conclude that these numbers cannot support Edison’s
    contention that the capacity which is the subject of this Petition is
    required to maintain the system’s integrity,
    but rather we conclude
    that this
    capacity would serve to increase the reserve capacity in the
    total system.
    The overriding conclusion that the Board must draw from Edison’s
    hardship plea is
    that while true in part, it
    is highly overexaggerated.
    When considering Edison’s compliance plan, the Board will thus
    not
    hesi-
    tate to order speedy compliance even if it requires prolonged shutdown
    of individual units,
    ~ts
    at Corn
    han
    cc and Hconomic Imp
    act
    James Fancher described in detail what the history of Edison’s en-
    vironmental control activities is, Edison alleges a total environmen-
    tally—related expenditure of $733,000,000 since 1929. This includes an
    estimate of expenditures up to 1977. Upon cross—examination it was
    noted that much of the monies spent, while “technically” pollution abate-
    15_

    rent pro~iects, would have beep spent uor ~thor
    reasons as ~e~1
    ~
    ixanpie, ~he construction of smoke stacks and mach ash handling equip’~
    aent ~s needed for tue safe and c~deriy ooerat~cn of a puartu
    For
    sta~’ce, one can not simply dusp ash on the p. ant ite iorever wiuhir
    a short .Jme the plant Itself woula ~e huried
    The anove ho ~evex
    3
    io~to irdicate that Edj son lac not spent corsideraule mcccv on oull
    don abatement equinment. As early ~s
    i
    29 Edison insta~.led and opeoa~
    ted
    an electrostafic
    precipitator on one of its units
    ~i~on
    next details
    its intended cospliance plan or tna a ~i iteS
    in quest~n. Said compliance plan was sunmitted on March 1,
    ~913
    CR 243 ~iibit F-3
    .
    The compliance olan (see Tanle 1) detailed idi
    Jon s rrtenoed method for each of the uniLs ir question,
    Bas cally
    ~ve stirtegies have been considered:
    1,
    Conversion to Oil: This is the compliance mode chosen for Sa—
    ~rooke 1—4. Units 3 and 4
    have
    already been converted to fuel
    oil.
    Un-
    its I and 2 are, as of this date, stil embroiled in a controversy be-
    tween the F.E,A, and Edison, but to date conversion to oil iS still
    the goal.
    Had Edison chosen conversion to oil for all other units, the alleged
    cost would have been about
    seven
    billion dollars over the life of the
    various plants.
    II. Conversion to
    Low-Sulphur Coal with New Electrostatic Precipi-
    tator:
    This is the compliance mode chosen for Waukegan 7. This
    alt-
    ernate includes the installation of a hot ESP.
    Should this option have been chosen for all units under considera-
    tion, a
    cost of $l.937 billion was alleged.
    III. Conversion to Low-Sulphur Coal with Flue Gas Injection: This
    compliance mode was chosen for Waukegan 5,6, and 8 and Joliet 5, 6, 7,
    and 8. This option, if considered for all units, is alleged to cost
    $1,546 billion.
    IV. Gasification of Coal: This compliance mode was chosen for Pow—
    erton 5 and 6* and Kincaid I and 2. Had this option
    been
    picked for
    all units, the alleged cost was $4,504 billion.
    Edison has chosen the mixed strategy detailed above because of nuxr-
    erous considerations which will be discussed further
    in this
    Opinion.
    The m~xedstrategy approach was estimated by Edison to cost $3,451
    billion over the life of the plants, expressed as revenue required by
    ~
    this~~~Ttsin~-
    pact on future decisions, both from an environmental impact as well as
    an economic point of v~ew,are very helpful
    as
    an aid in formulating
    our decision. Hovever, it must be remembered that this unit is not
    ifl
    question ~n this proceeding. An~ucipated startup will be in late 1975.
    fs such, it .~illin
    no way re affected
    by Lhe decisions of the instant
    Petition.
    15—12

    ~disor this is equivalen.~to $594 000,000 carital costs Brief Pg.
    4).
    Fanche~explained ~R, 254) that v’n~ie econo:~icswere considered,
    hey were
    iOc an
    overr~din9item in leve~opingthu mixed strategy. This
    was dore ~or toe twin reauons ~-ha~ a detailea economic analysis done in
    the past indicated that “order of aagnitud~ rankings
    ~
    tie same and
    seconely. because certain options wore sir~~lynot available on certain
    units For example, snortage of 0ist~llat fuel oii precluded the total
    system conversion to this fuel at any cos
    ~,
    and severe problems exist
    ir
    burning low-sulphur coal on ~ertain cycloce ooil~rs
    During consideration of eco~io~iicimuact Ediso r
    utilized
    a number of
    assuired costs
    which stoun. he ruLed *
    Cost of re.ouilding f5p**
    New ESP*
    Cost of L.S.C. over Ill, coal ‘1 cents/mmBTU
    Conversion to oil (Direct)
    $30/kw
    F.G.D. (Dixect)
    $63/kw
    Coal gasificatlo (Direct)
    $80/kw
    Under cross—examination, the subject of economics was hotly disputed
    (H.
    30 3—412)
    .
    Items of substantiai concern were cost of replacement
    (A.
    338) and a 15 figure for indirect
    escalation
    (H. 339)
    .
    Particular
    concern was expressed over different figures given for identical costs
    at different
    times of these proceedings (e.g.,
    cost
    of coal gasification
    capital).
    Financial data are extremely difficult to analyze in that
    various
    methods of estimation are possible. Mr. Busch (economic evaluation for
    Agency) presented a “financial rebuttal” of Edison’s $3,451 billion com-
    pliance estimate. Hr. Busch stated that the method of cost analysis was
    not a generally accepted method and that total cost by his methodology
    would be $347
    million. Also
    calculated by Busch is the
    total increase
    in power production of $.001/kwh, or 3.2 of the 1983 kwn, production
    cost. Under cross—examination of Mr. Busch, a number
    of potential areas
    of
    concern were uncovered (e.g., kwh growth rate projection and cost
    of
    capital estimates, A, 46-47)
    .
    Again, methodology and
    assumptions play
    a very significant part in
    the
    final number generated as a total cost
    projection.
    Mr. Todd Bolen (Supervisor of Economic Research, Edison)
    was called
    as a witness to reaffirm the background for Edison’s $3.451 billion
    estimate for compliance. Mr. Bolen countered the Busch testimony by
    stating that the method of financial analysis used was the “Revenue Re-
    quirement” method, which is commonly accepted by the utility field. He
    listee a number of
    textnooks
    which address themselves to this method
    CR, 129)
    .
    It must be noted that Mr. Bolen is saying that
    the “Total
    revenue request to support the PCB 74-16 variance” is $3,451 billion
    *This list is
    b’~
    I
    ~h~h~read~r
    sr~ferred to~h~
    record (4/3/74, Pg. 260 Ex. F-6,7) for a detailed
    description. Also
    sue cross-examination.
    **Diffjculty multipliers range from 1,1-2.7.
    15 —
    13

    —7
    (A.
    131). The
    thrust of Mr. Bolen’s testimony is that after adjusting
    the
    bases of Far(cher’s
    numbers, the original Fancher numbers and the Bus
    number were similar. The key statement is found on Pg. 158:
    “From his testimony (Busch) I have very few leads as to
    how he developed that $113 million annual revenue require-
    ment, but in my testimony I attempted by several different
    methods to show or to reconcile our two numbers, and I think
    rather successfully reconciled that we were definitely talk-
    ing in the same order of magnitude, which leads me to believe
    he was using a revenue requirement technique similar to
    ours.”
    (7/9/74, Pg. 158)
    The many, many pages of financial data and cross—examination on
    these data serve to reaffirm our feeling, that depending on the bases
    used and assumptions made, different numbers can be generated. Although
    most numbers mean essentially the same thing, their impact seems vastly
    different, depending on the vehicle used as a basis (e.g., total costs,
    annualized costs, etc.), However, whichever way one chooses to look at
    these figures, they represent a significant outlay of capital. The
    Board, in reaching its final decision, is well apprised of the economic
    impact of our decision and we will use this as a factor in reaching such
    a decision.
    The Options Available:
    As mentioned above, Edison has submitted a compliance plan for the
    units in question. Allegedly, this program encompasses the most prac-
    tical
    selection of
    options and the most rapid time frame possible. How
    realistic the time frame is will be discussed under
    the individual
    plan.t
    sections oi this Opinion.
    Thissection will deal with the reasonable-
    ness and potential problem areas of each option.
    I. Flue
    Gas
    Desulphurization (F,G,D.) : As a quick glance at Edi-
    son’s
    compliance plan
    (sedTabI~T)~buldshow, Edison
    has opted not
    to
    use flue gas
    desulphurization in its plans. Edison
    has taken the pos-
    ition
    that F,G.D, is not presently a
    viable technology which is worthy
    of utilization at its plants, and has thus eliminated it from present
    consideration. The Board must, as part
    of its consideration, determine
    if Edison is making a good-faith
    effort
    to attain compliance in the
    shortest practical time. However, we are not interested in
    dictating
    what type of compliance mode is used. Our main concern with the
    testimony
    in this area is to determine whether Edison has rejected
    a viable method
    which could bring about earlier compliance than could its submitted plan.
    Mr. Donald
    C. Gifford (Project Engineer, Scrubber Installation*) de-
    scribed Edison’s past attempt at utilizing F.G.D. Edison first initia-
    ted an FGD project in the spring of 1970. Bechtel Engineering suggested
    a wet scrubber operation and the contract
    for construction
    was let to Bab-
    cock and Wilcox in September 1970. One-half of
    the
    operation was put
    in service on February 23,
    1972.
    The
    system, commonly known as the Will
    County scrubber, is guaranteed
    to remove 98 of fly ash and 75 of SO2.
    ~sentlyemployedbyEdison;nowaProjectDirectorwitUni-
    versal Oil Products.
    15—14

    The sy~emwas retrofitted to the Will County Unit #1 shich is rated
    at 1 ‘7 trw, It is a wet L.mestone scrubber, c~rrpIete ‘ith limestone
    miiilng, two—module (A and B) scrubber, and sludge Lr-eatir~ent facilities.
    The second stage (A) scrubber uscame operational on upril. 7, 1972.
    The
    record (4/5/74, A. 47—60) detail~ Pdison s ‘~rperience wish the system.
    For various reasons the system lid not funtion anywhere near guarantee I
    rati
    ig. Ivailability
    of the scrutbrr systom was particularly
    disappoir t
    ~ng.
    Ihe longest qonsecutive run on the A scrubber was 21
    days (H.
    48)
    Availability
    i.S
    reported for A scrubbcr, 29 5c, and B scrubber, 25.2.
    Edison decided on April 15, 1973, to disconti’rue work on the B scrubber
    and concentrate on the ~ s~.rubber. rihe problems during the startup
    phnse were many and varied.
    Of major conccrr were denister pluggage,
    rePeater pluggage and corrosior,
    e~br~tion
    Of
    fans, an6 stress cracking.
    Many problems cave been resolved, and the rain areas of concern at
    pres-
    ent
    are.
    1) Stress cracking of reheator tubes.
    2) Limestone blinding of scrubbant.
    3)
    Sulphate scale formation.
    4)
    Sludge disposal.
    Edison details the costs to date for this scrubber at $16.8 million
    and operating costs at 9.4 mills/kwh
    at (35 capacity factor),
    Under cross-examination, many of the facts and figures cited were
    ~ ilenged. The Board finds that, although there is a question as to
    validity of the exact figures, the overriding impression is that
    this system
    was
    particularly troublesome. The fact that Will County I
    may not
    have been an ideal location for a scrubber installation (H. 70)
    is of little value to the Board in that all plants considered
    would be
    retrofit operations with varying degrees of difficulty.
    Discussions of
    closed
    loop
    pH
    control (R. 99)
    or sludge handling problems
    (R. 137)
    likewise do not
    answer the question
    of why the system did
    not function
    properly.
    While it is true that these techniques are being developed
    every
    day, Edison was in 1972 put
    in
    the position of having to develop
    such a system. They simply were not readily available at the time.
    Edison
    further detailed its experimentation
    with an
    $8 million, 22
    nw pilot program at its State Line plant.
    This system, termed
    the sul-
    fox~.l
    system, produces elemental
    sulphur. Problems with
    the catalyst
    system
    have caused Edison to “mothball” the
    system, while
    consideration
    of
    future
    pilot plant runs
    is undertaken (H.
    69).
    Edison,
    however, contends that its decision to
    not consider F.G.D.
    is
    not solely based on its rather dismal record,
    but also on the cur-
    rent
    status of
    the
    systems on other plants.
    This area was perhaps the
    most
    hotly controversial subject in
    this matter, and
    one which has been
    presented to the
    Board
    in other forums (CILCO v.
    Environmental_Protect-
    ion Agency, PCB 73-65
    SO2
    Inquiry
    Hearings,
    R74-2). In
    the instant
    P~~Ton,weThi~
    the two divergent views on availability
    and technology
    presented by Mr. A.
    Slack
    for
    Edison
    and
    by Dr. H.
    Hesketh for the Agen-
    The Board feels
    it
    would
    be useless to again
    detail the testimony on
    15
    15

    t
    .
    subject. The pages of the record which the reader is directed
    to,
    .uld he wish a
    detailed description of each plant, are May
    8, 1974,
    1—151;
    June 5,
    1974, H. 1—105; and June 20, 1974,
    R.
    1—95. The follow—
    £ng plants were discussed, along with their merits and disadvantages: Will
    County, Lawrence, Mitsui, Duquesne, Paddy Run, Cholla, Reed Gardner,
    Southern California Edison, Mohave, Boston Edison, and LaCygne.
    The long,
    detailed discussion on the above plants leads the Board to
    a number of conclusions.
    Much progress has
    been made during the past few
    years on F.G.D, The hard lessons learned at Will County I and
    in the
    original injection processes have yielded new systems in which many
    of
    the original problems are being solved. The chemistry
    of the systems is
    becoming better understood, as is the necessity to closely control and
    monitor specific parameters such as pH. However, many problems still ex-
    ist. Corrosion scaling, vibration, reheaters, and sludge disposal are
    among the problems which, while being solved, have not yet reached final
    resolution. The Board can understand Edison’s hesitancy to
    install this
    technology when, in its opinion, the chances for success are
    below those
    compliance methods it has chosen.
    The Board takes judicial notice of the document entitled “National
    Public Hearings on power Plant Compliance
    with Sulphur Oxide
    Air
    Pollu-
    tion Regulations,” published in January, 1974. Referring
    to Page 63 of
    that report, time to install scrubbers
    is listed as between 27 to 60
    months, depending
    on the source of information.
    Vendor estimates ranged
    stallationfrom
    30 to
    and36
    monthsthe
    size(obviously,of the unit),dependentThe
    onmostdegreeobviousof
    candidatesdifficulty
    offor
    ii
    such systems are Powerton and Kincaid, Due to
    the fact that
    both
    of these
    units are large (850 mw and 1232 mw) and existing, a 36-month
    installation
    time woul.d be expected. Thus, if one considered a jump-off date as
    the
    time of decision in this action, compliance could be anticipated (should
    scrubbers be opted for) by January 1978, Thus,
    if scrubbers were select-
    ed, compliance could theoretically be accomplished earlier than Edison’s
    plans for gasification.
    The question of the Board’s position on the availability
    and
    reliabil-
    ity
    of
    scrubbers does not have to be determined
    in
    the instant proceed-
    ing, as once again the question is how will an extended compliance plan
    (beyond the theoretical 1978 date) affect the environment and thereby the
    citizens of the state.
    The function of the Board is not to support one
    method of compliance over another,
    but rather to support the most rapid,
    viable methodology consistent with environmental, economic,
    and technol-
    ogical considerations. Our decision
    on Edison’s compliance plan is thus
    made on its impact on
    the state.
    II. Coal Gasification: Edison’s
    proposed compliance plan for Powerton
    5 (850 mw) and Kincaid 1 and 2 (616 mw
    each) is the installation of a low
    BTU coal gasification unit, using high-sulphur Illinois coal as a
    feed-
    stock. Mr.
    J. Augosta (Research Engineer, Edison) explained Edison’s
    history in this area, as
    well as the intended plans for the future (5/7/74,
    H.
    1—133)
    Edison first began investigation of coal
    gasification in 1966 and se~
    15— 16

    a task force in 1970. This task force was to determine
    answers to
    three questions: I) ability to produce gas from available coal, 2) en-
    vironmental acceptability of the gas produced, 3) a timetable to install
    a
    commercial system.
    As a
    result of this study, Edison reached the
    con-
    clusions that
    no technology
    is presently developed
    to reliably supply
    power generation
    gas, that the
    potential for such a system is very good,
    and that coal gasification offered the best option to meet Edison’s com-
    pliance criteria on a relatively short—term basis.
    Edison determined that before committing to a very large unit, a
    smaller prototype should be built.
    Powerton 4
    was selected as the site
    (119 mw)
    .
    On May 23, 1971, Edison entered into contract with Lurgi to
    provide engineering and other services to Edison,
    The cost of this (Pow-
    erton 4) project is listed at about 19 million dollars, with Edison com-
    mitted to $7.75 million and the Electric Power Research Institute con-
    tributing $11.5 million. Groundbreaking is anticipated in late 1975, with
    operation starting 30 to 36 months later.
    Edison then contends that one
    year of operation would be needed ~to shake down and test the system, at
    wh.ich time (about 1977) design will start for Powerton 5 and Kincaid 1 and
    2. A key point on technology is that Edison has had a 10,000-ton test run
    on a Westfield, Scotland, Lurgi gasifier.
    The results of this test were
    encouraging, according
    to Edison. However, they allege that more work is
    needed (H. 12).
    Before moving to
    the cross-examination, a
    brief description of how a
    ~~oal gasification plant operates is
    in order.
    The heart of such a system is the
    Lurgi coal gasifier. This is a
    high—pressure vessel into which coal (crushed and screened)
    is injected
    via an air
    lock. Air and steam are also injected
    with the
    subsequent
    generation
    of hydrogen, which combines with the coal, under high tempera-
    ture and pressure, to form methane gas and various other gases.
    The final
    gas stream has a heat content of about 175 BTU/ft3*,
    Ash is removed from
    the gasifiers via
    an
    ash lock.
    The resultant gas is then fed to a desulph-
    urization process where hydrogen sulphide (H2S)
    is stripped out. The con-
    centrated H2S
    stream then passes through a Claus kiln (an acceptable
    and
    reliable unit process) which produces elemental sulphur.
    The intended Powerton gasifier is to consist of three 12-foot-diameter
    Lurgi gasifiers (H. 44 and 88)
    .
    It is assumed that any construction of
    Powerton
    5
    would be increased by multiples of the same size gasifiers. Ed-
    ison predicts preoperation testing of this unit to commence during the
    last two months of 1976.
    The cross—examination essentially explored two points: 1) the state
    of
    the technology, and 2) the rationale for Edison’s extended compliance
    dates. It would seem that from experimentation at the Westfield, Scot-
    *Thls
    is in contrast to high BTU gasification, which is considered as
    a
    potential source of pipeline quality gas
    at
    1000 BTU/#3. Low BTU gasi-
    fication is economically feasible for power plants because there is no
    need to transport the resultant gas
    via
    pipeline. Low BTU gasification
    viates the need for the costly and rather intricate methanation step,
    ch would boost the BTU value by reaction with excess hydrogen.
    15— 17

    land, plant, a ccnsiderabl? part 03 tn~ r~~xwas rerved;
    indeed .r
    substanrial amount of Ii1~r.ois coa was ga.~Fued successfuliy.
    SO~
    clear up ~quipment
    ~as preser t and at ~ized on site,
    The Wes ~fr eld
    operationgas
    ‘~o the
    startedarea
    resfdentsup
    about
    since1960 tnonand
    has been supply~ng 240 BTJ/ft3
    Another plant of
    interesL is the Sasol plant in South Afrrca. 13115
    plant consists of about thirLee~ ~2iloot—oiaueter
    oxygyn-blowr gasitera
    used to produce feec for a petrochemiual ‘~peration.
    ‘h e tar cenerated
    is not
    ~ecirculated’
    there is no pollution a.oaterrert and a o~—qraae
    coa~
    is gasified
    (R.
    61)
    .
    However, upon an inspection of tro plant
    Edisce
    ~ that the ope’~ation was relatthely reliahle
    I~- wcrld seem that tne major point of technology which is untried
    tire udaptataon of a utility boiler
    to accept a low BTU gas
    feed. it
    ~sL be remembered that in using low
    BT’J
    gas
    as a feedstock, a much
    ~reat.er
    volume of gas must be fed and the boiler must be adapted to
    suit.
    Taking all of the testimony into account, the Board finds that Fdi-
    son
    is embarking on a project which has an excellent potential for suc~
    cess. Furthermore,
    it
    promises
    to open a viable alternate to 502
    re-
    moval, one which can be economical, clean, and still use our abundant
    supplies of high-sulphur coal. However, the Board finds that Edison’s
    timetable is unduly extended. Edison proceeded slowly and cautiously
    since its task force
    was formulated
    in 1970, and as such, valuable
    development time was lost. Attention is drawn to a memo (internal to
    Edison) proposing one gasifier on Powerton by 1973, and
    five
    gasifiers
    oy 1975 (H. 84). There is no good reason why this program was not
    pushed harder than it was. Therefore, the Board feels that every poss-
    ible barrier should be removed to expedite this program. We further
    feel that the 1980 date for Powerton 5 may be excessive. We do not
    feel that
    it is
    necessary to delay design of Powerton 5 until after one
    full year of experience on Powerton 4, nor do we feel Kincaid 1 and 2
    should be further delayed. We do feel that the bulk of construction
    costs should not be spent until Powerton ~ is proven, but also feel that
    construction should start as soon as Powerton
    4 is tested,
    e.g., early
    1777. This rationale will be applied to our Opinion concerning the in-
    dividual stations.
    III. Low-Sulphur
    Coal: Switching from high—sulphur coal to
    low-sul-
    phur coal
    is
    the option dh~osenfor Waukegan
    5, 6,
    7, and 8 and Joliet
    5, 6, 7, and
    8. However, Edison alleges certain problems exist in burn-
    ing low—sulphur coal. Before exploring these problems it is necessary
    to note
    that Edison discounted the use of low—sulphur coal on Powerton
    5
    and Kincard
    1
    and 2. This decision
    goes
    in part to the alleged ur-
    availability
    of low-sulphur coal.
    Mr. G. Marcus (fuel agent, Edison) detailed
    Edison’s attempts at
    securing additional 1ow~sulphur
    coal (4/9/74 H 615—624)
    .
    It was ex-
    plained that
    almost
    all low-sulphur coal must be
    imported from
    the West
    because Illinois produces
    no
    sucn coal
    for utrlity use,* An interest-
    ~
    small amounts of fairly .Low-sulpnur coal (1.5)
    are mined
    nn Illinois,
    it is used for making coke.
    15
    — 18

    12
    ing statistic quoted
    by
    Marcus was that
    in 1969 the state of Montana
    mined 500,000 tons of coal and
    in 1973
    Edison utilized 5.5 million
    tons from Montana. This figure was entered to point out the fact that
    new mines will have to be opened
    to generate
    more coal as
    it
    is needed.
    Marcus Exhibit #2, summarized below, shows Edison’s deficits in commit-
    ted low-sulphur coal ranging from 0.5 million tons in 1974 to 11.6 mill-
    ion tons in 1980, which indicates that new sources will have to be com-
    mitted in
    the
    near future.
    Year Low Sulphur Coal Required Low Sulphur Coal Obtained Deficit
    1974
    9.35
    million
    tons
    8.9 million tons
    0.45 million
    tons
    1975
    11.7
    9.1
    2.6
    1976
    12.0
    9.3
    2.7
    1977
    13.4
    8.8
    4.6
    1978
    15.4
    8.7
    6.7
    1979
    13.5
    1.9
    11.6
    1980
    13,5
    1,9
    11,6
    TOTAL DEFICIT 40.3 million
    tons
    Mr. Marcus then detailed Edison’s efforts to procure additional supplies
    of low-sulphur coal (H. 618-620). Efforts to date have been very disap-
    pointing (H, 621) as summarized below:
    Date
    Number Bids Let
    Volume Coal
    Number Valid Volume Ob-
    _______________
    Required (Years) Bids Received tamed
    March 73
    11
    24 Million Tons
    2
    6.9 Million
    (1975—1978)
    Tons
    Sept. 73
    21
    16 Million Tons
    Bid under con
    (1977—1987)
    sideration
    (R 653)
    Oct. 73
    17
    72 Million Tons
    Bid rejected
    1979—1989)
    (R 655)
    Summing up this experience, Edison in 1973 was able to obtain only 14.3
    million tons out of the 52 million tons required for the years 1974 to
    1980 (R. 622). These deficits do not include the Powerton or Kincaid fac-
    ilities where coal gasification is planned. If Powerton and Kincaid were
    included to use low—sulphur
    coal,
    the yearly deficits would increase to
    15
    million tons
    in 1979
    and 1980 (Marcus Ex. 3). Because of the scarcity
    of low-sulphur coal and the fact that the Kincaid plant is a mine mouth
    operation, consideration of low-sulphur coal for these units (Powerton
    and Kincaid) was
    rejected. The logistics and reliability problem in
    transporting western coal was discussed by Edison in an attempt to
    rebut
    the
    Agency recommendation for coal blending at Powerton.
    To acquire the
    required low-sulphur
    coal (2.3 million tons per
    year)
    ,
    a new coal
    mine
    would have to be opened, which would take 3 to 4 years; five sets of loc-
    omotives and 500 railroad cars would be necessary. In addition existing
    coal cars in Illinois could not withstand the rigors of a 2500 mile round
    trip and thus could not be used (7/11/74, H. 24-25),
    In 1970 Edison was the first midwestern user of unit train deliveries
    15
    19

    of ~oc—s~’ nirur wes ..e’u ~oa
    .
    Dud .v ther~ ~ne
    Ji)
    ry austome~s :)r wester
    oal, in the midwest rr.d uisn~he:~ ~nd .fiison uxprerTed cunccrn ahu’L
    one abi Ii cy of tfi rafir ad~ ~o I unOle the ~r ~u r~a1~traffi
    ef5in ~eno~
    ~y ani rfi ~auiy
    part~e nrary surce ~fiao r reeds ~e. rile ~uil suu~iie~
    ll/~4, R. 27
    This oncerr ics expressed ii re.ards fi the 2.3
    il1,iion t. irs per year of lo~’~sulphur
    cc r~ jf rtel blenfi
    ic
    at ?owcrton
    as to occur.
    The Board is concur~ed auoui ld~sor ‘s anil:ty to obtaa~.
    s uric ect
    and reliable supply
    of low—sulpnur wes.~ern .oa. eased
    ir
    o~..croading of
    the
    ord
    in this
    case. We will therefore require at any fit ~re er~en
    sions
    of
    is variance firm ~ow.Lrgs
    that ~‘dison 1, has o~tarncd r~.rn
    coms ~m
    for low—solilur coal, ~ has ibta~red abe
    ao~
    .~
    tv no ~rnns
    ~rt
    su~r c~aa to ils plant site, 3’ nas ~orkcd out alternate o mpiirnce
    inns ul ~uld the above two conditions be unfulfilled.
    ~‘dison next moved to detail the probleurs ercoantered in nurning low-
    sulphur coal on existing units.
    The problems center about two areas: first
    the use
    of low—sulpaur
    coal with conventional
    E.S.P.’s causes a degradation in the equipment s
    capture efficiency. This consequence,
    first noticed a number of years
    ago, is now a well-established fact The following table
    details the
    loss of efficiency actually encouncered at Commonwealth Edison’s Wauk—
    egan #8:
    12
    3
    45
    BTU Coal
    10987
    11069
    10627
    11371
    9820
    Sulphur
    2.79
    2,16
    2.97
    0.82
    0.45
    Coal
    Outlet #/mm 0.067
    0.071
    0,060
    0.518
    0.335
    BTU
    Efficiency
    98.6
    98.4
    98.9
    87.2
    88.1
    The table clearly shows the mentioned degradation and resultant em-
    issions of large amounts
    of particulates to the atmosphere. There are
    two possible solutions
    to this problum. One is the construction of ‘~Hot”
    ESP’s
    -
    which are
    units installed before the
    air preheaters. At
    this
    nigher temperature the resistivity of
    the ash is
    such that ESP
    efficien-
    cy increases to acceptable levels. It should be noted that
    at these high
    temperatures the size of
    the
    ESP must
    be significantly larger
    so
    as to
    accept
    the
    increased volume
    of the
    gas.
    The retrofitting of such units
    is a long-range project and would not be available
    by May
    1975 (see dis-
    c~1ssion cc Waukegac ~)
    ;
    therefore,
    if low—sulphur coal was used, there
    could be a trade-off of pollutants.
    A second method of solving the ESP
    degradation problem .s ‘flue gas conditioning.”
    This project injects
    sulphur trioxide direct~.y into the flue gas; the SO3 then precipItates
    out
    on
    the partlculates,
    which increases the migration velocity of tne
    fly
    ash and thus increases ESP efficiency.
    15 —20

    34
    The second main area of con~’err i.n uti1izin~ low—sulphur coal is the
    potenc..al i r fires or exp1o.~icrrs
    .~r
    cern
    in
    types of ooileru
    Cyclone
    filers
    are particularly susceptJble t this type of problem. The
    prob-
    fn
    is es sentiaily caused by high ~ar~on c r
    ‘c
    icr u~,eurned coal) which
    c uld Lir~r be ignited outside of the boilcr,
    ‘ausing 5.amaae to the pre
    heaters and LSP’s.
    Information ger.e’~ated ly Bdis’n indicates that a
    solution to the proble’~ is fortnco~rng.
    ihe above problems are alleged ~r’ be the main reason why compliance
    with both Rule~ 203 and 234 carrot he ..~cconpltshed sImultaneously.
    The
    ditt~ cu...ties as they relate to each sp~cif c p3 ant will be discussed
    ater in this OpinIon.
    IV. Supplemental Control
    Systems (Sc.S) : Altiough not a permanent
    system, SCS has the advantage of allowing attainment
    of
    the short-term
    air quality standards
    on an
    interIm basis,
    Due to the reality that Ed~
    ison
    will not be
    in compliance
    with Rules 203 and 204 at many
    locations
    by 1975, it
    is incumbent for
    the ~3oard to investigate methods which would
    reduce the impact of such discharges on tire citizens of the state until
    such time as permanent capture
    equipment (or fuel switching) can be in-
    stalled.
    A brief overview of
    what an ideal SCS system is and how it would
    function is given in the following paragraphs.
    A supplementary control
    system can be defined as “Systems where the
    rate of emission from a
    source is curtailed when meteorological
    condi-
    tions conducive to high ground-level pollutant concentrations exist
    or
    are anticipated”
    (Federal Register, Vol. 38, No. 178, p. 25698, Septem-
    ber 14, 1973).
    It
    is, in fact, a program
    incorporating real time moni-
    toring of stack emissions, meteorological conditions, and
    air quality
    data with a numerical scheme for the determination
    of
    current and fut-
    ure ambient air quality in the vicinity of a specific source, such that
    when selected levels of ambient air quality are obtained or forecast,
    specific emission reduction activities can be taken.
    As a practical matter, such
    controls can include:
    I) fuel switching,
    2) load shifting, or
    3)
    curtailment
    of the industrial
    process to reduce
    emissions during periods when air conditions are
    not optimum
    for dis-
    persing and diluting SO2. These systems,
    though
    apnearing under dif
    f-
    erent names, have been used by such diverse entities as the Tennessee
    Valley Authority, at its Paradise plant, American Smelting and Refining
    Company,
    at
    its El Paso and Tacoma smelters, and Dow Chemical Company,
    at Midland Michigan.
    Though
    all
    interim control strategies are somewhat different, the
    basic elements
    of these systems
    are fairly common,
    The universal ele-
    ments
    of all systems
    are as follows:
    1. Equipment to measure the actual recil time meteorologi-
    cal conditions surrounding the plant.
    This is
    necessary
    for both predictive functions
    and to keep the operator
    aware
    of
    the conditions
    at the actual time they
    are hap-
    pening;
    15
    21

    15
    2. A model
    based
    on past meteorological and dispersion
    data that will predict atmospheric conditions as to
    both weather and as to conditions which would influ-
    ence dispersion of contaminants;
    3. Actual source emissions. This must be real time and
    constant to the operator so as to be aware of what
    the plant is discharging to the atmosphere;
    4. Predicted emissions. This is necessary for the oper-
    ator to know in advance what conditions he will be
    operating under in the future so as to determine
    whether the atmospheric conditions will be adequate
    to disperse what will be emitted;
    5. A dispersion
    model. This, of course, is necessary to
    predict the concentration of contaminants, once em-
    itted under certain atmospheric conditions, so as to
    determine whether control strategies must be instituted.
    6. Validation of model. This
    is
    necessary to determine
    whether the model is
    in
    fact reflecting actual condi-
    tions and would be done through real time monitoring
    of both contaminants in the ambient air and meteor-
    ological conditions;
    7, Indications and trends as to potential violations.
    This is necessary in order to give the operator a
    framework in which to make decisions as to when to
    institute a control strategy;, and
    8. A strategy to control emissions. This, of course,
    is the ultimate function of the control system. Such
    strategies can consist of load reduction, fuel switch-
    ing, load shifting, and part-time use of permanent
    controls when
    dispersion conditions would seem to in-
    dicate.
    It should be noted that there will be no standard supplementary control
    system.
    A supplementary control system must be developed for every plant
    to which it is applied. Such factors as terrain, meteorology, process,
    stack height, and congestion of the area are all factors which must be
    considered.
    Though all
    systems will not
    be alike, they will all have certain bas-
    ic hardware in common.
    These include monitors for the contaminants to
    be measured. The number of such monitors
    would depend
    on the plant and
    its location, and could range from just a few monitors to as many as
    18 to 20, Also, the system would have to have certain weather monitoring
    devices so as to measure the conditions surrounding the plant.
    These
    would all have to be on direct hookup back to a central operations point
    where an operator of such a system could at any time get information
    from the monitors and the meteorological equipment, A third element
    would necessarily be a computer, which could be used to correlate all
    real-time data with all predicted data in the models so as to determine
    15
    22

    what the conditions are and wnat tire coneitions are liable
    to
    be
    in
    the
    resr future.
    Such data transmission r,i~ht also be hooked into the en-
    aorcicg agency directly for eas~ of snfo~cemcnt
    The most important
    clement ~s not really a piece of ~ardwaie,
    ot is, in fact, a plan which
    woufi indicate that when certain levels
    are
    reached or are
    predicted
    Lo
    be reach~a bu~ing a time span in the fut~c.e, certalr set plans would co
    nto cfiect at the plant to brIng emissicn~ ~niLo line wrth those which
    would cot cause violaLior of any standard that applies to
    the plant.
    On September 14, 1973, the
    5.
    Environmeila~ fiotecfion Agency
    pub-
    listen rules and gu.deiines for a
    i~~i
    mstntary ‘~ontrol anstems (38 Fed—
    eralPegister
    25698 September 14, 1fi3
    .
    ihese
    ruler nave never beec
    is~aed as final, but they do glve insight into requirements
    for an SCS
    system that tire federai govern era tn~ugna wore minima~ at that
    time.
    It should be noted that even at this time the proposed guidelines
    would
    only
    allow
    supplementary control systems to
    be used in situations where
    their
    use was
    necessary to augment constant emission limitation tech-
    niques
    which were available to a specific source and
    only until
    com-
    pletely
    adequate, constant emission limitatron
    techniques became avail-
    able. This could be summed
    up to mean that it would be allowed in sit-
    uations where the sole alternatives
    are either cutting back production
    permanently or delaying
    the
    attainment date
    for the national standards.
    The basic requirement of the federal guidelines is reliability ir
    the system. Before allowing SCS to be used, the federal government
    al-
    so would require each user of
    an
    SCS to support and participate in
    ap-
    propriate research development
    and
    engineering and a demonstration pro-
    gram to
    insure
    that the SCS system can
    be replaced by
    constant emission
    limitation techniques as soon
    as
    possible. This would be expanded to
    indicate that SCS would not be allowed on new or newly-modified sources,
    but only on present existing sources.
    One of the major concerns relates to
    the
    enforceability of the regu-
    lation for meeting the national ambient air quality standard if an SCS
    system is instituted for a stationary source.
    It
    is feared that citi-
    zen enforcement of the Environmental Protection Act would
    be
    discouraged
    because of the difficulty of determining whether ambient air quality is
    being
    met,
    as compared to a simple determination of whether emission lim
    itations are being met. Indications are that an SCS system is validly
    enforceable under the regulatori scheme as exists today with certain mod
    ifications. There are basically awo methods of enforceability. The
    first, of course, is actual measurement of the ambient air quality to
    determine whether the national standards are being violated. The second
    method is by making the SCS control plan enforceable on its face, with
    the regulatory determination that failure to comply with all terms of
    the plan is a prima facie violation of the standards.
    Mr. Melvin (Illinois EPA) testified
    that an SCS
    would be applicable
    to Kancaid (R. 81)
    but
    that it would be very difficult
    in a major met-
    ropolitan area (Powerton)
    Mr. Melvin further testified
    that
    he could
    give no cost
    estimates
    for such a system,
    nor could he estimate the
    time required
    to install such a system. The Board feels
    that an SCS
    system
    is needed in areas where extended
    compliance
    plans
    are to be un-
    dertaken,
    but
    is
    fully aware that some tIme
    must be allowed
    for a form—
    15
    23

    17
    ulation of a plan.
    Our Order will require such planning and eventual
    installation
    of a
    viable permanent emission control system.
    Environmental
    Impact and Compliance at Individual Power Stations
    We will now turn to discussions of individual plants, detailing the
    intended methods of compliance and the environmental impact of each
    facility.
    ~
    The Waukegan Station
    is
    located
    in
    Lake County, Ill-
    inois, a part of the Chicago MMA. As such, Rule 203 dictates particu-
    late levels of 0.1 by May 31, 1975, and Rule 204 dictates levels of
    l,8#/mmBTU
    ~°2 by May 31, 1975.
    Environmental Impact: The subject of environmental impact is of
    critical interest in any decision the Board renders in this action.
    The Waukegan station is located within the city limits of Waukegan at
    Greenwood Drive near Lake Michigan.
    On April 16, 1974, Mr. Jack Klingbeil (representative of CAP) test-
    ified to the effect that they were concerned that Edison’s progress has
    not
    been good in complying with Board regulations.
    He
    urged the Board
    to put maximum pressure on Edison to insure speedy compliance.
    The effect of Edison’s discharges was discussed by both Fancher
    (4/15/74) and Melvin (7/11/74). Both witnesses discussed the results
    of model data that had been generated.
    Fancher’s data predicted the effect that the ~
    an ati2~* will
    have
    on
    ambient air quality by May 30, 1975~ Assumptions include the
    following:
    1, Edison’s proposed compliance plan is on
    schedule.
    2. Full load operation.
    3. Stability Class 2 conditions.
    The results of this computer model reveal the following:
    Unit
    SO2
    Rate
    Max.
    24 Hr. Max. 3
    Hr. Part.
    Rate Max. 24 Hr.
    Max.3Hr~
    56
    2,70#/MBTU
    2.70
    27.3ug/m50.6 3
    143.277.2
    ug/m3
    0.28O.50#/MBTU 5.25.0
    ug/m3
    14.814.3ug/m3
    7 2.70
    37.5
    106.2
    1.87
    26.0
    73.5
    8 2.70
    38.6
    109.3
    0.07
    1.0
    2.8
    Total
    134.0
    379.1
    37.2
    105.0
    Standards
    365
    1300
    260
    *ft must be noted that these
    figures, as well as Melvin’s figures,
    de-
    tail the effect of plant emissions
    on the ambient
    air, NOT the
    projected
    air quality in the area as a
    result of all emissions. Of further
    import-
    emittersance
    is that(overin
    200the
    tons/yr.)
    immediate
    .
    WaukeganOf
    these four,area
    thereEdisonareaccountsonly fourformajorabout SO2
    87.5 of the total load.
    Therefore, Edison should have the dominant
    in-
    fluence on
    ambient
    air quality as it pertains to SO2. This discussion
    15
    — 24

    18
    Upon cross—examination, a
    number of weaknesses in the model were
    pointed out.
    Most notably, the model does not take into account fumi-
    gation or inversior effects.
    Fum~gatior is particularly
    important in
    this case
    in that the plant is rocated directly adjacent to the lake
    In addition, certain topographical conditions are not considered. Some
    of the omissions
    in the model presented cause
    the Board to conclude that
    the data are given slanted
    low, However, the fact that 100 load was
    used to generate the model would tend to overestimate the results. Be-
    fore drawing any firm conclusions we will turn to Melvin’s testimony.
    Mr. G. Melvin (Ill. EPA
    Episode Unit) entered Melvin Ex. #2, whicn
    is an analysis of Edison’s contribution to the air quality in the sub-
    ject areas.
    Mr. Melvin’s data was intended to predict concentrations
    at the
    worst conditions, as well as other conditions.
    The following is
    the result of his study.
    I. Under trapping conditions, Waukegan will not cause (in it-
    self) a violation of tie 3-hr. SO2 standard (Pg 13, Ex.
    11.
    2).
    2. Lnder fumigation conditions, thukegan has the potential
    for vlolat~ng the o.5 ppm. 3-hr. secondary standard
    (see
    Ex. M—2 Table 12)
    3. Estimates of daily (24—hr.) concentrations
    under nor-
    mal meteorological conditions
    show both SO2 and part-
    iculates belov the standards (sea I’1-2, Table
    18, e.g.,
    S02--.04 vs. Standard of
    0.14, part.
    28
    vs. Standard
    260)
    The conclusion would be that under adverse conditions the Waukegan
    plant has the potential to exceed the short-term (24—hr.
    and
    3-hr.)
    standards
    for 302
    and particulates.
    This is best pointed out by Ex.
    M-2, Tables
    21 and 22, which give maximum short—term concentrations
    under adverse meteorological conditions,
    Under cross-examination, many
    of
    the assumptions (e.g., plume rise
    equations) were questioned, as were Fancher’s assumptions.
    In studying all data presented, the
    Board
    feels that a potential ex-
    ists for violation of short—term standards. To protect against excess
    violations and yet allow the use of equipment which is needed for pow-
    er generation, our Order will dictate operation loading for W-7, and
    early shutdown for W-6.
    Unit
    5 is a 129 mw unit fired by a pulverized coal, wet—bottom boil-
    er.
    The boiler
    utilizes 1.3 sulphur coal
    and is anticipated to still
    utilize coal with this sulphur content on May 31, 1975. Emissions while
    burning this coal are expected to be
    0.5#/mmBTU
    until December 1,
    1975,
    at which time an SO3 injection system will be installed. Edison states
    that the duct work on Unit 5 will be modified to incorporate two ESP’s
    and this will
    thereby
    reach
    the aforementioned 0.5#/mmBTU.
    This work
    ~~not consider st~kheighE~nd its effect on dispersion. This in-
    formation is from the
    Illinois EPA emission inventory.
    15—
    25

    19
    -
    snould be accomplished by December 9’4,
    Tino coard finds thaL
    this
    elan is .ceasonaele aria will endorse It.
    Variance will be granted from O~tober .5, ~974, to October 15, 1975,
    rub~ect to conditions of particulate discharge and sulphur content of
    toe coal to be burned.
    Tariance will also be granted to allow 502
    emissions over
    the
    l.8#/mnr~BTU Level front May 31, 1975, to October la,
    19/5, subject
    to
    conditions
    of maximum emissions tied to sulphur com-
    tent of the coal.
    The provisions for monitoring and reporting of PCB
    74-11 will also be required.
    Unit 6
    an 119 mw unit fired by a cyclone coal-fired bo...lei’ The
    hoilert~
    ~za~
    and will continue to utilize a fend of coal of about
    .~
    suaph r.
    Emissions are presently in tne range of 0.3#/mmBTU (run
    2.6
    c’u.~phur coal)
    .
    Edison contends that when burning low-sulpiur
    ~,
    deterioration of the system is encountered due
    to high carbon
    us ‘yover.
    This problem will be attacked by boiler modifications as
    suggested by Babcock and Wilcox.
    Parts for
    this modification were to
    be delivered by November 1974, and Edison proposes a shutdown for mod-
    ifications during the second quarter of 1975 (H. 12)
    .
    Edison then pro-
    posed to
    start design of a flue gas injection system with eventual com-
    pliance by June
    1976.
    Under cross—examination the element of time was examined. In re-
    sponse to a question as to whether the modifications could be moved up
    to begin as soon
    as the
    part arrived, Mr. Holyoak replied:
    “I believe
    it
    might be possible, but it is a function of what else is going on
    in
    the system.” (H.
    51,
    4/15/74)
    The Board feels that particulates are a problem
    to
    the residents of
    the area and should be controlled in as short a time as possible. In
    line with our above reasoning in regards
    to the system availability and
    maintenance requirements, we will not grant variance any longer
    than
    needed to start boiler modifications. In relation to the SQ3 injection
    system, the
    Board must
    differ with Mr. Holyoak’s statements that flue
    gas conditioning technology is
    still in
    the infant stage (R, 23)
    and
    that design of these systems should be staggered. The Board takes jud-
    icial notice of the article,
    entitled “The Performance of Electrostatic
    Precipitators in Relation to Low-Sulphur Fuels,’~*
    in which reports
    of
    the commercial use of this technique date back to 1963. We find no rea-
    son for Edison to defer the design
    and installation of this equipment.
    Variance
    will be granted until October 15, 1975, subject to Edison in-
    itiating
    design and installation of its SO3 system as soon as
    Unit 6 is
    modified and on stream.
    Unit 7 Is a 617 mw unit fired by a dry-bottom boiler which
    utilizes
    pulirerized
    1.6 sulphur coal. This 1.6 coal
    is
    intended for use after
    May
    31, 1975 (H. 139, 4/15/74).
    Sulphur dioxide emissions from this
    unit will thus be approximately 3.2#/mmBTU (based
    on
    10,000 BTU/# coal)
    but will tary with the heat value of the coal.
    Unit 7 is equipped with
    an ESP which was originally rated at 98
    efficiency on high-sulphur coal.
    In
    an
    attempt to increase the ESP efficiency.
    Edison undertook testing
    *By K. Ja
    and C. Win its
    a.d,Second Internat ional Clean Air
    Cbn’-
    gress, pg.
    911 to 922.
    15
    —26

    with an additive known as Mopper K (testing about July 1971), Such
    testing did not increase efficiency and was discontinued. Upon inspect-
    ion of the
    ESP, it was noted that the plates were coated with fly ash
    and Kopper K. This situation decreased the efficiency of
    the ESP
    so
    that further stack tests revealed
    an
    outlet of
    l.27#/rnBTU.
    (Test run
    7/20/71, see 4/15/74 Ex. G,M,—2,)
    The projected repair bill was set
    at $4.8 million, with no assurance that low—sulphur coal may
    be used
    and compliance achieved. Edison then contacted Sargent and Lundy and
    contracted for the installation
    of a hot side ESP which would allow
    compliance with Rule 203 while burning low-sulphur coal. The antici-
    pated completion date for this project is December 1976. The reader
    is referred to 4/15/74, H. 15—17, and Ex.
    11-3
    and
    4 for details on
    this plan. Edison contends that
    the length of time required for
    com-
    pletion is necessitated by the location (120 feet in the
    air)
    of
    the
    new unit. Edison also contends that a recent experience with a retro-
    fit ESP installation on Will County 3 dictates this length of time. Cap-
    ital cost
    is estimated
    at $19
    million (Exhibit F-7 a)
    Upon cross-examination, the
    reasons for the delay were explored (H.
    56-59,
    H. 75-78)
    .
    Although the
    Board
    feels that some excess may be
    built into the schedule, Edison’s recent experience with Will County
    3 leads us
    to believe that the proposed schedule is realistic. We
    will allow the proposed timetable subject to review of progress at any
    further proceedings. Variance will be granted subject to many of the
    conditions detailed in the discussion of the Waukegan 5 and 6 units.
    However, due to the excessive particulates generated by this unit, its
    use will be curtailed,
    Unit 8 is a 360 mw generator fired by a dry-bottom boiler burning
    pulverized 1.6 sulphur coal. Very little discussion is needed on
    this unit. A long series of testing has been undertaken by Edison in
    the use of SO3 injection (details H. 18-21)
    .
    The system should now be
    in operation. It is noted that in Petitioner’s Motion for Modification
    (October 18, 1974) further delays to November 1, 1974, were anticipated.
    This Board has no sympathy in this regard. The operation of this sys-
    tem is an integral part of Edison’s compliance plan and must be pursued
    with all possible vigor. The Petition will be denied.
    Sabrooke Station: This is a small (146 mw) generating station loc-
    ated in Rockford, Illinois. The plant was purchased by Edison from
    Central Illinois Electric and Gas Co. in 1966. The plant is located
    on the east side of the Rock River in the southern part of the City
    of Rockford.
    Units 3 and 4 are presently oil-fired; therefore, they are in com-
    pliance and will not be considered further.
    Units 1 and 2 represent a rather unique problem. Edison’s original
    prayer for relief was as follows:
    “...and in the event that Edison is not able to proceed
    with its plans to convert the Sabrooke Station to oil fir-
    ing by the end of 1974, to such dates beyond May 30, 1975,
    as may be established by a compliance plan to be submitted
    15—27

    to the Board by July 15, 1974.” (Pet. 74-il, Pg. 50)
    As Fancier’s testimony of July Il reveals, Edison~has not yet re-
    ceived final word on its appeal to the Federal Energy Office regard-
    ing its request
    to
    burn oil on Units I and 2. Neither has Edison sup-
    plied the Board with
    an alternate compliance plan. The first indica-
    tion that Edison
    wishes
    to change its prayer for relief is revealed in
    Edison’s closing brief as follows:
    “Accordingly, Edison requests a variance for Sabrooke
    Units 1 and 2 for one year, provided that within 60
    days of a ruling by the FEO on Edison’s request to burn
    oil in these units, Edison will submit to the Board and
    Agency a specific program for bringing these two units
    into compliance.”
    (Brief of Petitioner,
    Pg. 42)
    If the Board granted such a prayer for relief, it would condone a
    variance granting leave to
    file a compliance plan hinging on actions
    of a third party (FEQ),
    This we cannot do. Furthermore, the unortho-
    dox manner in which Edison chose to amend its prayer for relief is
    highly questionable (in a closing brief)
    .
    The record, as it pertains
    to Sabrooke,
    is
    fairly complete and may be used in any future proceed-
    ings.
    The
    Board in particular takes
    note of the testimony of Weeks,
    Reeder, Estes,
    and Galinsk,
    all citizens of Rockford
    who
    attested
    to
    the nuisance generated by this facility.
    The Board, however, realizes that Edison’s attempt to achieve com-
    pliance was made in good faith and the failure of such compliance plan
    was not Petitioner’s fault. We
    will thus grant a short variance to
    allow protection (subject to cOnditions)
    ,
    while a resolution of the
    FEO dilemma can be worked out.
    It is realized that
    by January
    30,
    1975, Edison can, if necessary, reinstitute
    proceedings in the Sabrooke
    matter and rely on the record generated in this proceeding.
    Joliet Station:
    This consists of
    two
    separate facilities which lie
    on opposite sides of the Des Plaines River,
    in
    Will County, Illinois.
    Units 5 and 6 are located on one side, while Units 7 and 8 are on the
    opposite side of the river. The two complexes
    are connected by an
    overhead suspension bridge used to transport coal from the unloading
    facilities
    located on the Units 5-6 side of the river.
    The plant is
    about one mile
    from
    the
    city
    of Joliet and Units 7 and 8 adjoin the
    community of
    Rockdale,
    Environmental_Impact:
    As in the case of the Waukegan plant,
    modeling data was discussed by both Fancher (Edison) and Melvin (Ill.
    EPA)
    The cross-examination
    and assumptions used by both witnesses
    followed the same lines as in Waukegan and they will not be detailed
    in this section.
    One major point, however, must be raised: Edison
    bases its statistics
    on Units 5 and 6 burning 3,5
    sulphur coal and
    Units 7 and 8 burning low-sulphur coal by May 31, 1975 (4/22/74, H.
    84)
    .
    Melvin Ex. 2 seemingly uses the same assumption (see Ex. 2, TahIa
    The following are results geherated by Edison’s study:

    (uq/rn3)
    24—hr.
    ~1r. Melvin’s study reveals
    the
    following:
    1.
    Under fumigation conditions,
    the plant has the potential
    to violate the 0.5
    secondary ~
    standard (see
    M-2 Table
    14)
    2. Under fumigation conditions,
    rj1~~t~
    7 and 8 have the pot-
    ential to violate
    the short-term particulate standards (see
    M—2 Table 17).
    3. Under normal conditions, the
    expected
    contribution to the
    24-hr.
    air quality with wind direction aligning Units 5
    and 6 with Units
    7 and
    8
    is
    as foi:Lows:
    0.06 ppm ~
    (Standard 0.14)
    30 ug/ra3 part. (Standard 260
    ag/in5)
    Table 17
    from
    Melvin Exhibit 2 has been included in
    this
    Opinion so
    that the method of presenting data is available for
    examination (Fig. 2:.
    *Once again,.
    the reader is
    reminded that
    this series
    ot studies re-
    flects
    the
    contribution of the plant or:
    the air
    quality.
    In the Joliet
    area, the
    oercent of
    load
    from
    Edison is not as great
    as
    it
    was
    in
    Wauke—
    qan. There are about 11
    majo:r SO2 sources
    in the
    general Joliet area
    (200+ tons SO;,’yr.) between Lemont on the north and Channahan
    on
    the
    south. Total emissions from Edison are
    srojected
    at 153,113 tons/yr..;
    ~son’s
    contributions
    are
    57.5.
    ~ must also be noted
    that these fig-
    are from the Ill, EPA emission inventory and reflect
    emissions
    prior ~
    :1975.
    It is quite possible
    ~in
    the case of Edison reduction
    pur-
    suant ~ compliance plan) that both the total emissions and Edison’s
    con—
    Unit.
    Emission
    Rate #/:nBTU
    Average
    Cone.
    s--ar
    .
    5 (1
    i (1
    stack)
    stack)
    Part.SO2
    502
    Part.
    6.60
    0.08
    6.60
    0.19
    3515
    4.4
    357.9
    10.5
    1.6
    126.5
    3,7
    6
    502
    Part.
    6.60
    0.12
    243.. 3
    4.2
    86.1
    1.5
    ~°2
    Part.
    2.10
    0.90
    74,3
    32.3
    26.3
    11.3
    S
    502
    Part.
    2.10
    0.90
    74.3
    32.0
    26.3
    11.3
    Total
    SOPart,2
    7:15.9
    73,0
    253.0
    25.7
    Standards
    SO~
    Pa~t.
    1300
    -
    365
    260
    15— 29

    SWINARY OF
    CALCULATRO CONTRIBUTION
    TO Asm:EuT
    MS OJJITY
    ~p
    •~,
    V~’~r~~0LOGICALcONDITIONS
    FACILITF .Joliet Units 7 & 8
    FIGURE ~2
    POLLUTANT Particulates
    (ugsr3)
    5Three”hour average
    Wind~peed Class (Knots)
    Cumulative Frequency Distribution of axheum Rourly
    Particulate Concentr~tion~fot the
    Atmospheric
    C
    ..‘~,..~ •~-
    1—3
    4—6
    7—10
    11—16
    17—21
    21
    94
    128
    Stability A
    2
    a*************s ****s**a*****sa**********ss**sa*s*54*****a*,***a**s****,**a,
    34
    68
    85
    Stability 3
    11.5
    5.3
    3.7
    1.110
    2.233
    1.575
    s****~,s******* ***k*~’’*****a*****as*s****s*a**a*a***********s*s*s***a*****
    26
    43
    60
    68
    68
    68
    Stability C
    15 13.5
    8.6
    6.1
    4.9
    4.4
    1.055 2.472
    6.232
    .952
    .034
    .021
    *,.,*,****s****
    ~*****s*************,a*s**a***a*aa*****ss****ss*,**a*s*aa*ss
    9
    9
    9
    17
    17
    17
    Stability D
    15
    15
    15
    15
    15
    15
    1.657 9.705 20.868
    19.382
    2.438
    .555
    ****,*********s
    **********a*5**a*~*********5****,********s*********,’**aa,ss*~
    00
    0
    Stabi1ityE&~
    ——
    7,082 15.862
    6.061
    **a*a*********e s****a*****s*****a**aaa*a****aaaaaaa*ae**~*a~****,**a***aa**#
    196
    222
    Trapping
    3.~
    2,8
    Stability ~B
    ——
    ——
    a****a******s*a
    *********************5*a****5****,.~*****,s**5*Ca*****5****.’.
    63
    68
    Trapping
    15
    15
    Stability 0
    ——
    seas assess aces
    * *******~***** ***********a*e* *5*5*55*5*5*5*5*
    sassass,esasesas
    *
    554
    264
    Fumgation
    *
    2
    .3
    Stability 8
    s*s****s*a***s,
    ~a***s***a,***se****as****s***aa**sa*aa*a*****a***e***a**a**
    100
    80
    S.
    U
    0a
    a
    40
    20
    0
    .
    ,~
    ~-
    1_±11
    0
    KEY
    30
    60
    90
    120
    Particulate Conceat~atjons (u~~~’3)
    Wiudapeed
    Class (Knots)
    Atmospheric
    Class
    Naxicum
    Concentration
    Location of Maxis~asConcentration (Kilometers)
    Frequency of Occurrence (Pcr~.ent)
    150
    !\BLE 17

    From a review of the data oresented,
    it
    us clear to the Board that
    tna short-term SO standard may be violated.
    Edison itself projects
    s maximum of itJ,~ ug/m3 at worst conditiors
    This is ~out
    69,5
    of
    tIe 365 ag/rn3, 24-hr. standard.
    When considering the length of
    Edison’s
    compliance pan for
    SO2
    reduction at this pl’3n~.., shis potential viola-
    ton iill be kept ~irrnlv in mind,
    At hearing cn this faciiity,
    Mrs John Keigoer datailed the huis-
    ance generated by the Joliet plart.
    Mrs. keiqher lived in the neigh-
    nor: ood for 13 years and contends that t~e problem has gotten worse
    a cry year.
    She feels that Edison Is no.: wothing quickly eiough to
    solve the problem.
    Mrs. Keugher reg.Lstexed cc plaints as .~o how the
    air q’ality affects her children, one of
    whom is an asthmatic (H.
    139).
    The complaints registered nave all tne chara~teristics of a Section
    9(a)
    ~omplaint and,
    as such,
    portray a serious nuisance problem. This sit-
    uation further prompts the Board to expedite aoy proposed compliance
    niar
    A discussion of the individual units at Joliet will now follow.
    Joliet S is a 117 mm unit fired by two cyclone boilers burning 3.5
    sulphur coal.
    It is anticipated that this
    3.5
    coal will be used
    aft-
    er May 31, 1975, thereby necessitating
    a variance from Rule 204. Part-
    iculate data
    indicate that no variance from Rule 203 (g) is required
    ~‘ancher
    Ex.
    J—1).
    Edison’s proposed compliance plan calls for the installation
    of
    an
    SO3 injection system on both boilers to be installed during October
    1975. Edison has recently completed installation of
    new boiler tubes
    on both boilers (see discussion on
    Waukegan) to solve the problems
    of
    carbon carryover.
    Modifications are also in progress to upgrade
    the
    coal crushing equipment.
    The Board feels that this compliance
    plan is
    reasonable and will
    endorse
    it.
    It
    is therefore anticipated that Jol-
    iet 5 will be in full
    compliance
    with both Rules 203 and 204
    by
    mid-
    October 1975.
    Joliet6
    is a 344 mw unit fired by a cyclone boiler burning 3.5
    sul~r coal. It
    is anticipated
    that the 3.5 sulphur coal will be
    in
    use after
    May 31,
    1975.
    Emission of about 6.64t/rnBTU will
    necessitate
    variance from Rule 204. Particulate
    testing indicates that no variance
    from Rule
    204 (g) is required
    (Fancher Ex. J-l)
    Edison’s proposed compliance plan calls for installation of a flue
    gas injection system with design starting in January 1975 and complet-
    ion in March 1976. All parties agree that this compliance plan
    is a
    viable one, and the plan would bring anout compliance in the shortest
    possible time.
    The question facing the Board is the reasonableness of
    the
    time frame.
    Under cross—examination, a long exchange was undertaken
    detailing why the March 1976 deadline was reasonable.
    We will not de-
    tail the exchange, but refer to 4/22/74, R. 33-48, H. 58-75.
    -~
    -~-~-
    ~-~-
    ,
    —~
    ibutron will change drasticaliy
    by l97~. Tru~~snote simply reveals
    status prior to 1975.
    15—
    31

    24
    After careful deliberation
    on the above exchange, the Board feels
    that Edison’s proposed timetable is excessive. While it would be ben-
    eficial to Edison
    from a cost standpoint to delay design work, it is
    evident that this work must be done and the major components
    will be
    the same, no matter what the result of the design work.
    The Board sees
    no justification for not starting work on
    this program immediately,
    with a target startup
    date of December 1975.
    Joliet 7 and 8
    are
    617 mm units fired
    by dry-bottom boilers burning
    puliT~c~l~
    Both
    units burn low-sulphur coal with emissions cal-
    culated to be no higher than
    2.l#/m.BTU and, with the
    coal
    used, should
    meet the l.8#/rnBTU standard
    the majority of
    the time. A
    variance is
    thus needed to allow the slight abridgement and will be granted. Part-
    iculate data show a 0.9#/mBTU level, which would require variance.
    Edison’s compliance
    plan again calls for the installation of a flue
    gas injection system on both units. Work is scheduled
    to commence in
    June
    1975, with compliance brought
    about by October 1976.
    Once more,
    discussions centered on the time
    frame rather than the method of compli-
    ance. The
    references detailed above (4/22/74, R, 33-48, R. 58-75) are
    the point
    in the record in question.
    Once again, the Board finds that
    Edison’s compliance schedules are unduly exaggerated,
    and therefore we
    will condition our variance on a shorter time frame. The Agency has sug—
    gested (Brief Pg. 38) June 1976 as a reasonable
    date. The intervenor
    has suggested (Brief Pg. 33) December
    31, 1975. In light of the amount
    of work required and the size of the units involved, and being cogniz-
    ant of the environmental impact of these units, the Board must agree
    the Agency that June 1976 is a reasonable date.
    Powerton
    Station:
    The Powerton Station i-s located about one mile
    sou~~TP~in,
    Illinois.
    It is located on the southeast bank
    of the Illinois
    River.
    At this time, there is only one unit in opera-
    tion
    (P.
    5)
    .
    This unit burns high-sulphur Illinois coal which
    is
    washed down to about
    3.7 sulphur. The unit is equipped with an ESP
    which was rated at
    99,5 efficiency. Testing shows that
    the unit meets
    the
    1975 particulate regulations when burning
    the
    3.7
    sulphur coal.
    However, compliance with Rule 204
    is not anticipated
    by
    1975.
    Environmental Impact: As mentioned
    under
    the Waukegan Station,
    the subject of environmental impact was covered by Fancher (Edison) and
    Melvin (Ill, EPA). The results of
    their studies follow:
    15
    32

    Fancher Ex. P—i:
    _________________________*Unjt
    Emission
    Emission#/MBTURate
    Average3-hr.Conc.
    24-hr.ug/m3
    5
    SO
    6.8
    230.35
    81.4
    Pa~t.
    0.05
    1,7
    0.6
    SO2
    6.8
    230.35
    81,4
    Part.
    0.05
    1.7
    0.6
    Total
    So2
    460.7
    162.8
    Part.
    3.4
    1.2
    Standards
    SO2
    1300
    365
    Part.
    260
    Melvin Ex.—2 draws the following conclusions:
    1. Under trapping conditions, Powerton 5 and 6 indicate violations
    (Pg. 13) of the 3 hr. standard.
    2.
    Under normal conditions
    there will be no violation of the 24-hr.
    SO2 standard.
    3, In a study conducted to determine the effect of a large point
    source in a major metropolitan area (Peoria) it was found
    that Powerton 5 could be anticipated to contribute a signifi-
    cant portion of the S02 in the area, for example, at the maxi-
    mum receptors.
    Receptor
    Total Expected Read.
    Powerton
    5
    Cont.
    Mr. Jay
    2
    31
    Norco also
    testified
    1000565
    569 ug/m
    ug/m
    ug/m3
    3
    3as
    to the effect of252
    309
    525each
    ug/m
    ug/mug/mEdison
    3
    33
    plant
    on air quality. Norco Exhibit #2 was entered to show the difference
    in
    the air quality
    if Edison were to be in compliance
    vs.
    if
    they were not
    in compliance by 1975. The validity of the assumptions was challenged
    upon cross—examination, and again distracted from its credibility. How-
    ever, the Board feels that the exhibit has much value as an indication
    of what Edison’s contributions
    to the total contaminant loading would
    be, and has used this as part
    of its consideration on all stations. The
    Norco Exhibit 2 will
    be included in this Opinion as Fig. 3.
    The Board feels that Powerton has the potential to exceed
    the short-
    ~standardsandwilltai1oritsOrdertoreducethis
    impact.
    *Once again,
    it is
    noted that this is the contribution of the plant.
    Ed-
    ison contributed about 65 of the SO2 in the Peoria area. Subject to change
    after
    1975.
    **Unit 6 is not a subject of this Petition. However, it is anticipated
    15
    33

    FIGURE
    3
    ~.NNTALAVCB~P.IR QU1~LITYCONCE2~TPATICNS
    POINT OF MAXI?dJM CrNTRIBUTICN FRCM EDISON SOU21ES
    May
    30, 1975
    Commonwealth •Edisor
    PCB 74—16
    Norco Exhthit
    2
    ~iegan
    5-8
    :11th 5—8
    r~mrton5
    0-maid 1
    &
    2
    _________
    1975
    EX~~TEID
    ~
    ~nC~
    (ug/m3)
    P21. STD,*
    (up/rn3)
    ppj, ma.
    40.46
    1.31
    1.96
    2.45
    40.45
    1.29
    7.65
    9.56
    40.12
    .34
    6.9
    8.62
    40.1
    .29
    7.21
    9.01
    _________
    1975 1~LIL~V\BLE
    ______
    5p3c-—-oTusrnaTr
    r~~zmm~mmr
    (ug/rn3)
    P21, SID,
    (ug/rn3)
    PRI.SID~
    40.16
    .46
    1.30
    1.63
    2.14
    2.68
    1.83
    2.29
    3,64*5
    455
    Ccerparisons ~2 oniy
    Conc, D~~’5iI3T7~5
    3)
    .66
    .82
    5.51
    6.88
    5.07
    6.33
    357
    4.46
    * For per ticulates, the assumed background is 40 ug/rn3 Geometric Mean. The ~x,ntribution
    of Edison sources is,
    therefore, calculated
    as the
    of th~difference bstween the
    standard (75) and ths backgrcund (40),
    or
    35.
    “~
    Exhibit
    10
    of
    Edison’s Petition had assumed a 6,0 1.bs/M3t~sulfur dioxide croission
    limitation; with
    the
    current
    stack height of the
    Kincaid Station, Rule
    204
    Ce) limits
    sulfur
    dioxide emissions to
    4.34
    lbs/NBtu. This Ethibit reflects the lca.’er
    limitation.
    Primary
    .‘tinual
    Air Quality
    Standards:
    Particulates
    75
    ug/rn3 (gecreatric mean)
    Sulfur Dioxide
    -‘
    80
    ug/m3 (arit1inetic mean)

    26
    (Discussions below on SCS and blending reflect this,)
    As mentioned in the previous section of this Opinion dealing with
    coal gasification, the Board feels that
    while
    the program for
    compliance
    suggested by Edison is a good one, the timetable may be excessive. In
    answer to a question raised in the section of this Opinion of F.G,D. (e.g.
    will Edison’s rejection of F,G,D, lead to undue delay and environmental
    damage?), the Board feels that in light of the problems of F,G,D. sys-
    tems, the potential for development of a viable alternate (coal gasifi-
    cation), and the possibility of an SCS system to “shave the peaks” of
    short—term excursions over the standards, Edison’s compliance plan is
    acceptable.
    The date for completion and what interim steps are to be
    taken are the
    only questions
    left to be answered.
    Supplementary Control Systems: No long discussion of this item is
    needed. Th ulk of this subject was covered earlier in this Opinion.
    The Board finds that an S.C.S. system is potentially a viable approach
    to
    be followed on
    an interim basis. Our Order will condition variance
    upon the undertaking of a
    cooperative effort~betweenEdison and the
    Illinois EPA with the expected end result the operation of a workable,
    enforceable S.C.S. system.
    ~~l~i~fls:
    Certainly another option open to Edison is the blend-
    ing of coal to achieve a reduction of SO2 until permanent controls can
    be installed. Mr. Hoffman (IEPA Electric Utility Specialist) testified
    as to the feasibility of this option (5/10/74). Mr. Hoffman pointed
    ~aut that the methods of segregation of coal and conveyor belt mixing,
    or layering coal,
    could be used
    (R,
    31). It was also pointed out that
    such
    methods are now in use by Edison at the
    Waukegan and State Line
    facilities (R. 33)
    Mr. Ramey (7/11/74) was called by Edison to discuss the problems in-
    volved with coal blending. The major points center around the diffi-
    culty of securing additional supplies of low-sulphur coal. Further com-
    plicating
    the matter is the subject of
    contracts for coal which Edison
    now has for Powerton.
    In its Brief,
    the Agency asks the Board to condition any grant of a
    variance on (among other things) a study of coal blending at Powerton.
    The evidence elicited
    at hearing
    indicates that
    coal blending is not a
    feasible alternate and that conducting such a study would serve no
    use-
    ful purpose.
    Date of Compliance: The Agency suggests (Brief
    Pg. 41) that a compli-
    ance date
    of
    early 1980 would be reasonable for a coal gasification
    plant.
    The Board agrees.
    There is no justification
    for the delay pro-
    posed by Edison.
    Much design work can begin earlier than proposed by
    Edison. Compliance by 1980 is a reasonable date, and we
    will so
    condi-
    tion our Order.
    to start in late 1975.
    If it were to
    start
    up uncontrolled as
    to SO2,
    the above predicts
    the combined
    impact on air quality.
    15
    3b

    Kar~caid Station
    The Kincaid Stat~on is located approximately four
    mil~~h~town
    of Kincaid, christia~ Coonty, Illinois
    The pia~t
    is located on the chores of Lake Sar~gchris, which was impounded ~or the
    use of this plant,
    The station consists of t-~o 616 mx coal-fired units,
    each fired by a B &
    W
    cyclone boiler.
    Each bo~1er is equipped with a
    cual Research-Cottreil
    ISP and discharges through twin 500’ stacks
    ESP
    efficiency
    tests while
    burning high-sulphur (4.1 sulphur) coal showea
    results well within
    Rule 203 specitscations
    Thus, no varianco from
    Rule
    203 is required.
    CoaJ is supplied by Peabody Coal Co. from Mine #10, which .:s 1ocated
    adjacen~ t
    he station.
    The plant is cons dered a mine—mo~th tacil’ty.
    P
    otd in
    e reduction of sulphur, ddison has contracted
    w.tn
    Peabody
    ~avu all of the coal washed,
    Washing facilities are expected
    co cost
    n~illion and will be
    paid for
    by Teabody
    These facilities
    are expect-
    be
    operable by November
    1975. The following results are expected
    a.~..terwashing at a 25 volume loss:
    Moisture
    Ash
    Sulphur
    BTU/#
    Raw coal
    14.5
    15.7
    4,2
    9,730
    Washed doal
    17.5
    8.7
    3.5
    10,340
    When analyzing Rule
    204 it
    is apparent that Rule 204 (e)
    is the most
    restrictive (comparison with 6.0#/mBTU). Allowable emissions are
    4.34#/mBTU as per Rule 204 (e)
    .
    If
    one assumes an average heat value
    of 10,000 BTU/#, it is apparent that Kincaid ~o2 emissions will be 8.4#/
    ruBTU
    until November 1975 and
    7,0#/mBTU after November 1975. Thus, a
    variance is required.
    Environmental Impact: Due to
    the relatively isolated location of
    the~I’~aidplant, its environmental impact can be considered as a sin-
    gle entity rather than
    as one
    source among many. This situation allows
    for more accurate predictions as to effect, less complicated impact ass-
    essment, and lends
    itself to an S.C.S. system which would predict
    and
    prevent short-term violations.
    Once again,
    Fancher (Edison)
    and Melvin
    (IEPA) entered evidence as to the potential impact of Kincaid’s dischar-
    ges on the environment.
    Questions as to assumptions used were similar
    to those raised in Waukegan and will not be reiterated.
    The following
    results were reported by Fancher:
    Unit
    ____
    Emission
    Emission#/mBTURate
    Average3-Hr.Cone, ug/m24-Hr._________3
    1
    SO2
    8.60
    373.7
    132.1
    Part.
    0.05
    2.2
    0.8
    2
    502
    8.60
    373.7
    132.1
    Part.
    0.05
    2.2
    0,8
    Total
    SO2
    747.5
    264.2
    Pirt.
    1,5
    Standards
    SO2
    1300
    365
    Part
    260
    (Fancher Exhibit K—I)
    15—36

    Melvin Exhibit
    #2
    projects the following:
    1. Under trapping conditions, Kincaid indicates violation of the
    3-hr. SO2 standard (indicates 0,74 ppm
    -
    M. Ex.-2, Pg. 13).
    2. Under fumigation conditions, violations of the 3-hr. SO2 stand-
    ard are also projected.
    3. No 24-hr. violations have been projected, although worst case
    analysis was not made.
    it is the Board’s opinion that adverse environmental impact can
    be
    kept to an absolute minimum at this station by the installation and
    op-
    eration of a viable S.C.S. system~
    Edisn’s compliance plans for this Station call for the installation
    of coal gasification units, with anticipated completion dates of 1982
    and 1983. Other considerations included: building a taller smoke-
    stack to reduce the limitations of Rule 204 (e). This was rejected
    because of the fact
    that
    the 6#/nBTU level could still not be
    obtained.
    Edison again alleges that low—sulphur coal could cause damage to the
    cyclone boilers, and also that such a supply is not available.
    The
    problems with transportation and logistics were also cited. (Kincaid
    burns about 3 x 106 tons of coal per ydar
    ,
    from Melvin Ex. 2,)
    There is very little argument that coal gasification
    is a viable
    ~echno1ogy
    to pursue at Kincaid.
    The questions again center around
    the length of the compliance plan.
    Edison proposed to defer work
    on
    K-i and K-2 until P-5
    is well underway. There is no doubt that this
    conservative methodology is preferable from Edison’s point of view,
    but we
    must balance the delay against the potential adverse environmen-
    tal
    impact. We must also not
    lose sight of the enornious projected
    costs for
    these units, according
    to Edison’s figures:
    Powerton 4
    $19,000,000
    Powerton 5
    $65,895,000
    UNIT Investment
    Kincaid I
    $48,415,000
    (Fancher Ex.
    6 Ed,)
    Kincaid 2
    $48,415,000
    The Board at
    this time feels the compliance dates can be moved up
    significantly. We again express our feeling that preliminary design
    work can start before massive funds are committed, We will, however,
    not tie our variance
    to a
    firm
    date at
    this time, but will
    rather use
    the condition of an S.C.S. system to insure maintenance of the air
    quality in the area.
    Summary: The
    Board will issue a very complex Order in this matter.
    T1.i~~ue
    to
    the extremely complex nature of the system involved.
    In
    writing this Order the Board has very carefully considered all of
    the evidence presented.
    We have then weighed all
    of
    the
    aspects in-
    volved in
    this case. The environmental impact, technology, economics,
    ~d
    good faith efforts
    have all been considered. The Board finds that
    ile Edison has indeed been the forerunner
    in new technology (e.g.,
    ill County scrubber, Powerton gasification),
    this leadership is re-
    quired so as to meet
    the mandate of the citizens of Illinois
    as voiced
    15—37

    --
    29
    by the State
    Legislature when they adopted the Environmental Protect-
    ion
    Act. Such
    efforts are, in fact, to be expected of a major utili-
    ty company, and Edison is indeed by far the
    largest electric utility
    in the
    State.
    The Board further finds that in many instances delay
    was a tool used to forestall the installation
    of equipment when technol-
    ogy could have been pushed. It is mainly
    for this reason that the
    Board has trimmed the dates on the various compliance plans.
    We are
    also very much aware of the enormous sums of money which will be ex-
    pended to bring about compliance. We are further aware that this cost
    will
    eventually be borne by the consumer in the form of increased elec—
    tric bills. This cost to the consumer is the price for the clean air
    he ordered when supporting the Environmental Protection Act and the
    Federal Clean Air Act.
    In many instances compliance plans run beyond
    the one—year term
    granted in this variance. It
    is
    the intent of the Board to carefully
    review the facts in any future proceeding and act accordingly. It is
    also the intent of this Board
    to do everything it can to
    insure the
    viability of these compliance plans.
    To allow undue delay, to not fol-
    ow
    up
    on
    such delay, would truly be to turn our back on our
    responsibil-
    ities.
    This Opinion constitutes the findings of fact and conclusions of law
    of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board
    that:
    1. With respect to the Waukegan Station, Unit 5:
    a) Variance is granted from Rule 3-3.112 from October 15,
    1974,
    to May 31, 1975.
    b) Variance
    is granted
    from Rule 203 (g) from May 31, 1975,
    to
    October
    15,
    1975.
    Subparagraphs (a) and (b) above
    are
    conditioned on the use
    of
    both
    the Unit 5 and the Units 1, 2, and 3 electrostatic precipitators at all
    times that Unit 5 is operating. Subparagraphs (a) and (b) are further
    conditioned on the conducting of stack tests to be performed within
    60 days from the date of this Order. Said stack tests shall be per-
    formed in the presence of Agency personnel, if the Agency desires. Re-
    sults of said stack tests shall be submitted to the Agency and the
    Board within fifteen days
    of
    the completion of such tests.
    c) Variance from Rule 204 is granted from May 31, 1975, to
    October 15, 1975, subject to
    the
    following conditions:
    i) Edison shall not emit sulphur dioxide in excess of
    3.0#/MBTU.
    ii) The installation of an SO3 injection system no later
    than December 31, 1975.
    d) This entire Order I is further conditioned upon the followin~
    15—38

    30
    i) Within 30 days from the
    date
    of this Order, Petitioner
    shall submit to the Agency a detailed schedule for in-
    stalling a flue gas conditioning system on Unit
    5. Said
    schedule shall include
    as a minimum: dates
    for obtaining
    contracts, date of beginning design, date of
    completing
    design, date
    of scheduled delivery, date of
    outage for
    installation, and date of completion of said system.
    ii)
    Petitioner shall
    submit quarterly reports to the Agency
    detailing work performed and progress made during the
    previous quarter and
    work to be performed in
    the follow-
    ing quarters.
    iii) Within fifty
    (50)
    days of
    the date of this Order Petit-
    ioner shall submit a
    performance bond to
    the Agency
    in
    the amount
    of
    $35,000.
    Said bond shall insure completion
    of the flue gas conditioning system by the date detailed
    above in Order 1 (c) (ii),
    iv) Edison shall continue to maintain and operate the
    moni-
    toring system as ordered in PCB 73-40. All data generated
    by said system shall be submitted to
    the Board and the
    Agency as soon as it is available, but in no event later
    than six weeks after the last day of any month.
    v) Edison shall apply for all necessary construction and op-
    erating permits.
    2.
    With
    respect to the Waukegan Station Unit 6:
    a) Variance is granted
    from Rule
    3-3.112 from October 15, 1974,
    to a maximum of 30 days after Petitioner receives the fabri-
    cated furnace tubes from Babcock and Wilcox, but not later
    than June 30, 1975.
    b) Variance is granted from Rule 203 (g) from May 31, 1975, to
    October 15, 1975, subject to the following condition:
    i) Edison shall operate Unit 6 only after boiler modifications
    are completed, which would consist of as a minimum the
    installation of the new specially fabricated furnace tubes,
    c) Variance is granted from Rule 204 from May 31, 1975, to Oct-
    ober 15, 1975, subject to the following conditions:
    i) Order 1 (c)
    Ci) ,
    1(d) (i)
    , 1
    (d) (ii) 1(d) (iv) and
    1
    (d) (v)
    shall
    be
    reapplied
    to
    Unit 6.
    ii) The installation of an
    SO3
    injection
    system no later than
    February 1976.
    iii) Within
    fifty
    (50) days from the date of this
    Order, Pet-
    itioner shall
    submit a performance bond to the Agency in
    the
    amount of $20,000, Said bond shall insure completion
    15
    39

    31
    of the flue gas conditioning system by the date detailed
    above in Order 2 (b)
    (ii).
    3. With respect to the
    Waukegan Station Unit 7:
    a. Variance is granted from Rule 3-3.112 from October 15,
    1974,
    to May 31, 1974.
    b. Variance is granted for Rule 203 (g) from May 31,
    1974, to
    October 15, 1974.
    c. Subparagraphs (a) and (b) above are conditioned in
    that Wauke-
    gan Unit 7 shall
    be operated above 153 mw only after
    all
    other
    available Edison capacity has been
    utilized except Edison’s
    fast start
    peakers and Sabrooke Units
    1
    and 2.
    d. Variance
    from Rule
    204 is granted from May 31, 1975, to
    October
    15, 1975, subject to the following
    conditions:
    1)
    Orders 1(c) (1) , 1(d) (ii)
    1(d) (iv) ,
    and
    1(d) (v) shall be
    reapplied to Unit 7.
    ii)
    Petitioner shall install a hot electrostatic
    precipitator
    no later than December 1976.
    iii) Within 30 days from the date of this Order, Petitioner
    shall submit to the Agency a detailed compliance program
    and project completion schedule for the installation
    of
    a new hot
    ESP. The schedule shall include estimated
    dates of ordering equipment, delivery of equipment,
    inst~-
    ation of equipment, and startup of equipment.
    iv)
    Within fifty (50)
    days
    of the date of this Order, Petitioner
    shall submit a performance bond
    to the Agency in the amount
    of $150,000. Said bond shall insure completion of the hot
    ESP.
    4. With respect to Waukegan Unit 8, the Petition for Variance is dis-
    missed.
    5. With respect to the Sabrooke
    Station Units 1 and 2, variance is
    granted from Rule 3-3.112 until January 30, 1975, subject to
    the
    following conditions:
    a)
    Sabrooke Units 1 and 2 shall be operated only after all avail-
    able Edison capacity has been utilized,
    including Waukegan
    7.
    However, one of the Sabrooke units (1 or 2) may be operated at
    the minimal level necessary to provide steam for water deminer—
    alizers, heating the station, or to prevent stack deterioration
    in the event that Units 3 or 4 cannot be used for such purposes.
    6. With respect to the Joliet Station Unit 5:
    a) Variance from Rule 203 is dismissed.
    15 —40

    32
    b) Variance from Rule 3-3.112
    is
    dismissed.
    c) Variance from Rule 204 is granted from May 31, 1975, to Oct-
    ober 15, 1975, subject to the following conditions:
    i) The installation of a
    flue gas conditioning system
    no
    later than October
    15,
    1975.
    ii) Within 30 days from the date
    of
    this Order, Petitioner
    shall submit to the Agency a detailed schedule for in-
    stalling a flue gas conditioning system. Said schedule
    shall include as a minimum:
    dates for contracts, begin-
    ning design, completing design, date of scheduled deliv-
    ery, date of outage of equipment, and date of completion
    of said system.
    iii)
    Petitioner shall submit quarterly reports
    to the Agency
    detailing work performed and progress made during the
    previous quarter and work to be performed in the following
    quarter.
    iv)
    Within fifty
    (50) days
    from the date of this Order, Pet-
    itioner shall submit a performance bond to the Agency in
    the amount of $35,000. Said bond shall insure completion
    of the flue
    gas
    conditioning system by the date detailed
    above in Order 6(c) (i)
    v) Edison shall apply
    for all necessary construction and op-
    erating permits.
    7.
    With respect to the Joliet Station Unit 6:
    a) Variance from Rule 203 is dismissed.
    b) Variance from Rule 3-3.112 is dismissed.
    c) Variance
    is
    granted from Rule 204 from May 31, 1975, to October
    15, 1975, subject to the following conditions:
    i) The installation of a flue gas conditioning system no
    later than December 15, 1975.
    ii) Within 30 days from the date of this Order, Petitioner
    shall submit to the Agency a detailed schedule for in-
    stalling a flue gas conditioning system. Said schedule
    shall include as a minimum: dates for contracts, begin-
    ning design, completing design, date of scheduled deliv-
    ery, date of outage of equipment, and date of completion
    of said system.
    iii) Petitioner shall submit quarterly reports to the Agency
    detailing work performed and progress made during the
    previous quarter and work
    to be
    performed
    in
    the follow-
    ing quarter.
    15—41

    iv) Within fifty (50) days from the date of this
    Order,
    Petitioner shall submit a performance bond to the Agency
    in the amount of $65,000. Said bond shall insure com-
    pletion of the flue gas conditioning system by the date
    detailed above in Order
    7 (c) (i)
    v)
    Edison shall apply for all necessary construction and
    operating
    permits.
    8. With respect to the
    Joliet Station Units 7 and 8:
    a) Variance
    from
    Rule 3-3.112 is granted from October 15, 1974,
    to May 31, 1975,
    b) Variance from Rule 203 is granted
    from May 31,
    1975, to October
    15, 1975.
    c) Variance from Rule 204 is granted from May 31, 1975,
    to October
    15, 1975,
    to allow
    sulphur dioxide emissions
    up to
    2.l#/14BTU.
    The above Orders 8(a)
    ,
    (b)
    , and
    (c) are conditioned upon the
    following:
    i)
    The installation
    of
    a flue gas conditioning system on
    Un-
    its 7 and 8 no
    later than June 6,
    1976.
    ii) Within 30 days from the date
    of
    this Order, Petitioner
    shall submit to the Agency a detailed schedule for install-
    ing a flue gas conditioning system. Said schedule shall
    include as a minimum: dates for contracts, beginning
    de-
    sign, completing design, date of scheduled delivery, date
    of outage of equipment, and date of completion of said
    system.
    iii) Petitioner shall submit quarterly reports to the Agency
    detailing work performed and progress made during the prev-
    ious quarter and work to be performed in the following
    quarter.
    iv) Within fifty
    (50)
    days from the date of this Order, Pet-
    itioner shall
    submit
    a performance bond to the Agency in
    the amount
    of
    $200,000. Said bond
    shall insure completion
    of the flue gas conditioning system by
    the date
    detailed
    above in Order 8 Cc) (i)
    v) Edison shall apply for all necessary construction and op-
    erating
    permits.
    9.
    With respect
    to the Powerton Station
    Unit 5:
    a)
    Variance from Rule
    3-3.112 and Rule 203 is dismissed.
    b) Variance
    from Rule
    204 is granted
    from May
    31, 1975, to October
    15, 1975, subject
    to the
    following
    conditions:
    15 —42

    34
    i)
    The installation
    of a low BTU coal gasification plant
    to
    fuel Powerton 5 by May 1980,
    ii) Within thirty (30) days from the date
    of
    this Order,
    Ed-
    ison shall begin a
    study
    regarding the installation and
    use of a supplementary control system at the Powerton
    plant. Such study shall seek
    to
    conform to the general
    guidelines of Federal Register, Vol. 38, No. 178, P.
    25698, September
    14,
    1973. Edison shall seek the aid
    of the Agency in this matter and shall file a report of
    its findings with the Agency and the Board within four
    (4) months of the date of this Order.
    iii) The Board retains jurisdiction to reopen hearings on the
    subject of S.O.S. on
    its
    own motion, or the motion of
    any other party during the term of this variance. Such
    hearings may result in further orders regarding the in-
    stallation and operation of such
    S.O.S.
    systems. The
    Board may also issue any further orders regarding the
    proposed S.C.S, without holding hearings
    if
    it deems nec-
    essary.
    iv) Within 30 days of the date of this Order, Edison shall
    submit to the Agency a detailed compliance plan, Said
    plan shall detail the proposed steps and dates for in-
    stallation of a pilot gasification plant for Powerton 4,
    showing compliance no later than October 1976. Said com-
    pliance plan shall also detail the expected dates and
    steps to be undertaken towards installation of the coal
    gasification plant for Powerton 5.
    v) Edison shall
    submit
    quarterly reports detailing its pro-
    gress completed during the previous quarter and its ex-
    pected progress during the following quarter.
    vi) Within fifty (50) days from the date of this Order, Edi-
    son shall submit a bond in the amount of $1,000,000.
    Said bond is to insure the installation of the Powerton
    4 pilot unit by October 1976, and the Powerton 5 gasifi-
    cation plant by 1980.
    vii) Edison shall apply for all necessary construction and
    operating permits.
    10. With respect to the Kincaid Station Units 1 and 2:
    a) Variance from Rule 3—3.112 and Rule 203 is dismissed,
    b) Variance from Rule 204 is granted from May 31, 1975, to Oct-
    ober 15, 1975, subject to the following conditions:
    i) Plans to burn only washed coal at the Kincaid Station
    shall be continued,
    with
    its use commencing by
    i~ovember
    1975.
    15
    —43

    ii)
    Edison shall within six (6) months of the date of this
    Order file a compliance plan with the Agency for the in-
    stallation of a coal gasification
    unit for Kincaid I and
    2.
    Said plan shall inclade an a.iticipated date fcr com-
    pletion of this project,
    Such date will be reviewable
    by the Board at any future requests for variance as re-
    gards these units.
    iii) Within sixty (60)
    days from the date of this Order, Edi-
    son shall submit to the Board and the Agency a he-ailed
    proposal
    for
    implementing a supplemental control system
    at the
    Kincaid generating statior. Such plan snail fol-
    low the general guidelines of Federal Register, Vol. 38,
    178, P25698, September 14, 1973. The Agency shall with-
    in 30 days of the receipo of such proposal submit to the
    Board its comments
    on said proposal. The Board shall
    maintain jurisdiction in this matter and may schedule add-
    itional hearings at the
    request
    of any party
    or
    upon its
    own motion on
    the
    proposed
    S.O.S. The
    Board may also
    is-
    sue any
    further Orders regarding the proposed S.O.S.
    with-
    out holding hearings if
    it deems
    necessary.
    iv) Within
    fifty (50)
    days
    from the date of this
    Order
    Edi-
    son shall submit to
    the
    Agency a performance bond
    in the
    amount of $100,000 to
    insure
    compliance with Order 10
    (b) (i) above.
    Mr. Henss dissents.
    I, Chrastan L. Moffett, Clerk of the Illinois Pollution Control
    Board, certify that the above Opinion and Order was adopted by
    the
    Boand on the 3rd day of January,
    1975,
    by a vote of 4 to I.
    di
    __
    15 —44

    Back to top