ILLINOIS POLLUTION CONTROL BOARD
    November 22, 1974
    ILLINOIS CENTRAL GULF RAILROAD,
    )
    Petitioner,
    v.
    )
    PCB 73—547
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Mr. Joseph W. Phebus, attorney for Petitioner.
    Mr. Michael Ginsberg, attorney for Respondent.
    Order of the Board (by Dr. Odell)
    On December 21, 1973, Illinois Central Gulf Railroad
    (Illinois Central) filed with the Pollution Control Board
    (Board) a Petition For Variance from Rules 202(b), 203(b),
    and 205(f) of the Illinois Air Pollution Regulations (Chapter
    Two). Illinois Central sought a one—year variance from Rule
    205(f) and a variance until June 30, 1976, from Rules 202(b)
    and 203(b) of Chapter Two. Petitioner operates an open air
    spray painting operation in Centralia, Illinois. The Illinois
    Central paints approximately 3000 railroad cars yearly at the
    facility. Some cars are painted inside and out, some are
    stencilled for identification. In its Petition, Illinois
    Central stated that a new painting facility was in the pre-
    liminary design stage; it was not sch~du1edto be completed
    until June 30, 1976.
    On January 25, 1974, a Centralia resident filed with
    the Board an objection to the grant of a variance claiming that
    the spray painting operation was turning the town orange and
    that “we no longer wash our windows, we scrape them.” The
    Environmental Protection Agency (Agency) recommended on February
    13, 1974, that a six-month variance be granted from Rule 205(f)
    of Chapter Two and that a one—year variance be granted from
    Rules 202(b) and 203(a). On March 8, the Illinois Central inde-
    finitely waived the 90-day requirement of final Board action
    under Section 38 of the Environmental Protection Act (Act).
    The Petitioner filed an Amended Petition For Variance on
    June 26, 1974, requesting a variance from Rule 202(b) and 203(b)
    of Chapter Two to extend from January 1, 1974, through December
    31, 1975. Petitioner estimated that it would have its new in-
    door facilities completed by the end of 1975. Construction was
    scheduled to begin on October 1, 1974, with completion fifteen
    14
    489

    —2—
    months later. A construction permit had been granted by the
    Agency on May 25, 1974. At the present time, to minimize the
    overspray problem, Illinois Central was building temporary
    shielding walls around its outdoor operation. These walls
    were expected to be completed by July 1, 1974. On an average
    day 12.4 railroad cars are painted at the facility; the average
    car receives 21.9 gallons of paint weighing 203.67 pounds.
    Therefore, the average hourly process weight was calculated at
    315.68 lbs,’hour.
    The Agency filed its Amended Recommendation on August 21,
    1974. The Agency felt that under Rule 203(c), Petitioner had to
    comply with Rule 203 (a) not 203 (b). Since the Petitioner under
    Rule 203(c) was in violation of Rule 203(b) on the effective date of
    the Chapter Two Regulations, Illinois Central was required to
    meet the Rule 203(a) standard by December 31, 1973. Based on
    Illinois Central1s process weight of 315.68 lbs/hour, the allow-
    able emission rate of particulates under Rule 203(a) is .95 lbs/
    hour. The Agency stated that Petitioner’s proposed spray paint
    facility with its four spray booths would limit particulate
    emissions to .79 lbs/hour. The Agency noted that citizens
    contacted did complain about spray paint from Illinois Central’s
    operation on their automobiles and homes. However, the Agency
    stated that the temporary painting facility would minimize over-
    spray. The Agency did not state how effective the temporary
    facilities would be in reducing the impact on area residents.
    The Agency recommended that the Petitioner be granted a
    variance from Rule 202(b) and Rule 203(a) of Chapter Two until
    May 30, 1975, subject to certain reporting requirements as well
    as the successful operation of the temporary overspray shielding
    walls. The Agency stated that the December 1975 date was reason-
    able.
    A hearing was held on September 25, 1974, in Marion County,
    Illinois. Respondent began the hearing by amending its Amended
    Petition in two respects. First, Respondent agreed with the
    Agency that Rule 203(a) not 203(b) was the applicable rule regard-
    ing the particulate emissions. Second, Respondent sought a
    variance until March 1, 1976, instead of the original December 31,
    1975, date in the Amended Petition. Respondent called one witness
    to establish arbitrary or unreasonable hardship under Section 35
    of the Act. The Agency called no witnesses and no citizens came
    forward to testify during the hearing. The testimony by the
    Illinois Central employee established that the December 1975 dead-
    line could not be met, because no bids had been submitted on
    Petitioner’s original contract proposal; changes were made in
    this contract, and all bid submissions were due by October 31,
    1974 (R. 7). It is not known whether any contractors bid on this
    revised contract. The witness testified that other facilities
    were not available to do the paint work done at Centralia (R. 18).
    The temporary shielding walls have been installed. Twenty-five
    feet high walls have been constructed in an area relatively remote
    from the homes of area residents on plant property to permit paint
    spraying and undercoating.
    14 —490

    —3—
    The highest rail cars painted at the fapility are
    seventeen feet tall (R. 13). The witness was uncertain how
    effective the walls were in controlling the 23 average over-
    spray that occurs (R. 23, 25). He had only visited the site
    once for a brief period (R. 22); he was also unsure of whether
    overspray problems occurred near the ends of the shielding walls
    (R. 22); he did not know how close neighbors were to the spray
    operations (R. 22). The witness estimated that overspray was
    reduced by a factor of five because of the walls (R. 32)
    -
    There
    are no walls at the old stenciling area where cars are sprayed
    for identification purposes. However, only 10 of the total
    caint sprayed at the facility is consumed in the stenciling pro-
    cedure (R. 29). The facility employs 540 people (R. 12).
    We grant the Petitioner a variance from June 26, 1974,
    until May 30, 1975. While we agree with the Agency that a
    variance is warranted, the inadequacies in the record do not
    permit us to decide whether a variance should be granted to a
    later date. Specifically, the record does not disclose the
    effectiveness of the temporary walls in protecting neighbors
    from overspray. While we note that no citizens came forward to
    the hearing to protest the variance grant, under Section 35 of
    the Act, Petitioner has the burden of proof to show arbitrary or
    unreasonable hardship. Second, it is unclear why the variance
    petition was filed as late as December 1973. Chapter Two be-
    came effective in April 1972. While delays after the decision to
    undertake compliance can be explained, the belatedness in start-
    up was not answered. Third, the evidence was unconvincing on the
    issue of whether compliance would be achieved by March 1976. The
    record does not disclose whether the contract has now been let or
    whether the fifteen month completion schedule is a term in the
    contract, not merely an estimate subject to continual revision.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that
    Illinois Central is granted a variance from Rule
    202(b)
    and
    203(a) of Chapter Two from June 26, 1974, until May 30, 1975,
    subject to the following conditions:
    A. Petitioner shall submit monthly progress reports
    to:
    Illinois Environmental Protection Agency
    Division of Air Pollution Control
    Control Program Coordinator
    2200 Churchill Road
    Springfield, Illinois 62706
    The first monthly report is due January 1,
    1975. Each report shall indicate progress
    made toward completing the control program
    outlined in Petitioner’s construction permit.
    14
    —491

    —4—
    B. Petitioner shall operate the temporary paint
    spray facility according to the specifications
    and location detailed in Petitioner’s Exhibit 9
    of the Amended Variance request.
    C. Petitioner shall operate this temporary paint
    spray facility to minimize overspray impact on
    the public until the completion of its new
    paint spray operation.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    ~
    day of
    4
    ~
    ,
    1974, by a vote of
    ___
    to p
    Christan L~fett
    14
    —492

    Back to top