ILLINOIS POLLUTION CONTROL BOARD
    May 8,
    1975
    FAIRBURY STONE COMPANY, INC.,
    Petitioner,
    v.
    )
    PCB 74—463
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Dr. Odell)
    On December 11,
    1974, Fairbury Stone Company,
    Inc.
    (Fairbury Stone)
    filed with the Illinois Pollution Control
    Board
    (Board)
    a Petition for Variance from Rules 103(b),
    202(b),
    and 203(b)
    of our Air Pollution Regulations
    (Chapter
    2)
    for a period of one year.
    Petitioner operates a limestone quarry on U.S.
    24,
    3
    1/2
    miles west of Fairbury,
    in Livingston County,
    Illinois.
    The
    operations consist of removing 12
    to 18 feet of overburden,
    blasting the limestock rock vein that
    is
    12 to
    18
    feet thick,
    transporting the shattered rock to the central processing plant,
    and screening and crushing in the processing plant, followed by
    storage and loadout for distribution via motor trucks to
    customers.
    The quarry produces approximately 225 tons per hour
    of stone in various size-classes.
    Normal production consists of
    one 8-hour shift per day, but during 1974 there have been some
    two 8-hour shifts per day of operation.
    Petitioner employs
    8 to
    10 persons.
    On the basis of factors listed on page 8.2-1 of “Compilation
    of Air Pollutant Emission Factors,
    Second Edition,” Petitioner
    estimated their total particulate emissions,
    if uncontrolled,
    to
    be as follows for various sources:
    Primary crusher
    (225 T/hr x 0.5
    lb/T)
    =
    112.5
    lbs/hr
    Secondary crushing and screening
    (90 T/hr x 1.5 lbs/T)
    =
    135.0 lbs/hr
    Screening,
    conveying, and handling
    (225 T/hr x 2.0 lbs/T)
    =
    450.00 lbs/hr
    Total uncontrolled emissions
    =
    697.5
    lbs/hr
    16
    —587

    —2—
    The suspended emissions from the primary crusher and the secondary
    crushing
    (cone crusher or hammermill and impact crusher)
    and
    screening would amount to the following,
    using the given emission
    factors
    (no factor given for screening, conveying,
    and handling)
    Primary crusher
    (225 T/hr x 0.1 lb/T)
    =
    22.5 lbs/hr
    Secondary crushing and screening
    (90 T/hr x 0.6 lb/T)
    =
    54.0 lbs/hr
    Suspended emissions
    =
    76.5 lbs/hr
    Because of several modifications in processing, which are intended
    to reduce particulate emissions,
    Petitioner believes its actual
    particulate emission rates
    are less than those listed above for
    uncontrolled emissions.
    Fairbury Stone believed that it was operating in compliance
    with applicable regulations when
    it filed an Operating Permit
    Application with the Illinois Environmental Protection Agency
    (Agency)
    on October
    17, 1972.
    This belief was based on the fact
    that after Agency personnel inspected the plant on June 17,
    1971,
    and August
    1,
    1972, the inspector indicated to the plant super-
    intendent that “the plant appeared to be
    in compliance,”
    However,
    between October 17,
    1972,
    and
    June 27,
    1973,
    there were eleven
    exchanges between Petitioner and the Agency concerning the Operat-
    ing Permit Application, which continued under
    review.
    From
    June
    27,
    1973,
    to April 17,
    1974,
    there was no
    communication
    between
    Petitioner
    and
    the
    Aqenc,
    Beginning
    again
    on
    April
    17
    1974,
    the
    Operating
    Permit.
    Application
    was
    under
    active
    cons ideration,
    but
    on
    August.
    30,
    1974,
    the
    Agency
    denied
    the
    Perm:t
    Application
    ‘~asfinal
    action
    because
    the
    application
    0±.
    emission
    factors
    showed
    that
    the
    primary
    crusher
    and
    the
    hammermill
    would
    emit.
    particulate
    matter
    an
    excess
    of
    the
    rate
    allowed
    by
    Rule
    203 (h~
    of
    Chapter
    2
    Thereafter,
    the
    Agency
    informed
    Fairbury
    Stone
    that
    enforcement
    action
    might
    he
    inotiated
    because
    Petitooner
    was
    operating
    without.
    a
    valid
    permit
    and
    Probably
    was
    exceeding
    applicable
    particulate
    emission
    limitations.
    After
    consultations
    with
    the
    Agency
    and
    Myers
    Engineers
    ~concerning
    possible
    particulate
    control
    methods)
    Petitioner
    sent
    a
    letter
    on
    October
    31,
    1974,
    to
    Mr.
    Thomas
    Casper
    ifl
    the
    Agency
    intorm~nn
    horn
    that
    Fairhury
    Stone
    ontenoed
    to
    file
    for
    a
    variance
    and
    install
    a
    control
    system.
    On
    November
    7
    1974
    the
    Agency
    received
    from
    Petitioner
    a
    Construct.ion
    Permit
    Aoplica~
    tion
    for
    a
    liquid
    spray
    dust--suppression
    system
    and
    on
    December
    2,
    1974,
    the
    Agency
    granted
    this
    Construction
    Permit.
    The Agency filed
    its
    Recommendation with Board on February
    7,
    1975.
    The Agency feels that the estimated particulate emissions
    in
    the Petition for Variance are reasonable.
    “The existing control
    equipment at Fairbury Stone consists of
    a rudimentary device, the
    shielding of transfer points on the conveying system; and a more
    efficient system, the recirculation of discharge air on the hammer—
    mill and Stedman mill.
    The Agency estimates that the recirculation
    systems are 50
    and 75
    effective for the secondary crushing and
    Stedman milling processes,
    respectively, when properly maintained.”
    The liquid spray dust-suppression system, which is to be installed
    by Petitioner under the Construction Permit that was granted by
    16
    588

    —3—
    the Agency on December 2,
    1974,
    should reduce particulate
    emissions from the primary crusher, cone crusher, and hammer-
    mill to the 90
    efficiency level if the system is operated
    properly.
    This would achieve compliance with Rule 203(a)
    of
    Chapter
    2, which the Agency properly pointed out as being applic-
    able in this case, rather than Rule 203(b),
    Although Fairbury
    Stone was an “existing source”,
    it does not meet either of the
    conditions
    of Rule 203(c); therefore,
    Rule 203(a)
    applies.
    Two problem areas remain.
    The Agency felt that the liquid
    spray dust-suppression system could be installed by July
    1,
    1975,
    instead of August 15,
    1975, as the Petition for Variance stated.
    Also,
    the load-out area for Stedman mill limestone was believed
    to have excessive particulate emissions.
    Therefore,
    the Agency
    suggested that additional measures be taken to control
    Stedman
    load-out emissions and suggested alternative methods to achieve
    this.
    Stedman mill limestone, which is the most finely ground
    and therefore easily airborne, comprised approximately 30 tons
    per hour of the total 225 tons per hour maximum which can
    be
    processed.
    Because of these two remaining deficiencies, the
    Agency recommended that the Petition for Variance be denied un-
    less Fairbury Stone submits a better program of compliance.
    In a communication to the Board filed February 28, 1975,
    Petitioner agreed to install
    the
    liquid
    spray
    dust-suppression
    system
    by
    July
    1,
    1975.
    Petitioner also stated that it
    (a)
    is
    engaged in discussions with the Agency regarding possible control
    systems for the Stedman load—out area,
    (b) expects to file an
    amended
    variance
    petition
    in
    this
    matter,
    and
    Cc)
    waives
    the
    right
    to
    a
    decision
    within
    90
    days.
    On
    March
    6,
    1975,
    the
    Board
    considered
    Petitioner’s
    communication
    of February 28 as a Motion
    for Leave to File an Amended Petition and granted this Motion.
    The Amended Petition for Variance was received by the Board
    on March 10,
    1975,
    In it Fairbury Stone agreed “to install a
    dust control system on the Stedman load-out which will consist of
    the use of a spray header to provide a liquid curtain to sur-
    round the Stedman bin discharge as trucks are loaded~
    Said liquid
    curtain will act as
    a wind shield and will limit emissions by wet-
    ting and collecting fugitive particulates
    from the load-out
    operation.”
    A Construction Permit Application and a description
    of this equipment has been filed with the Agency.
    An Amended Recommendation from the Agency was received by
    the Board on April
    8,
    1975,
    Since the Amended Petition for
    Variance resolved the two problems which the Agency objected to
    in its original Recommendation,
    the Amended Recommendation of
    the Agency
    is that Fairbury Stone be granted a variance from
    Rule 203(a) until July
    1,
    1975.
    The Agency stated that it will
    grant the Construction Permit to Petitioner for the dust control
    system for the Stedman load—out area.
    The Agency has received no objections to the granting of
    this variance, which may be partly due to the fact that Fairbury
    Stone facilities are in
    a primarily agricultural area.
    The nearest
    resident is located approximately one-quarter mile northwest of
    Fairbury~Stone.
    16—589

    —4—
    From October 17, 1972, until August 30,
    1974,
    there was
    considerable delay by both the Agency and Petitioner in resolv-
    ing issues associated with the Operating Permit Application of
    Fairbury Stone. However, since October, 1974, Petitioner has
    developed an adequate program to control particulate emissions
    from its facilities.
    Under the circumstances in this case,
    the
    Board agrees that Fairbury Stone should be granted a variance
    from Rule 203(a)
    of Chapter
    2 through June 30,
    1975.
    In the
    absence of
    a specific time schedule in the Amended Petition for
    Variance or in the attached single page from the Construction
    Permit Application for the Stedman load-out dust control system,
    we will grant Petitioner
    a variance from Rules 103(b)
    and 202(b)
    through June 30,
    1975.
    If a variance is needed beyond July
    1,
    1975,
    the requirements set out in Train
    v. National Resources
    Defense Council
    43 LW 4467
    (April 15, 1975) must be met. Peti-
    tioner’s request for a variance from Rule 203(b)
    is dismissed
    for the reasons previously explained.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board.
    ORDER
    IT
    IS THE ORDER of the Illinois Pollution Control Board
    that:
    1.
    Fairbury Stone Company,
    Inc.
    is hereby granted a
    variance from Rules 103(b)
    ,
    202 (b), and 203 (a)
    of Chapter
    2, Air
    Pollution Regulations from December 11, 1974,
    through June 30,
    1975.
    2.
    Petitioner’s request for a variance from Rule 203(b)
    of Chapter
    2, Air Pollution Regulations,
    is hereby dismissed.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was adopted
    on the
    Yç~’
    day of May,
    1975, by
    a vote of
    _____________________
    c~L~
    iA.:~
    ~
    Christan L. Móff&tt, Clerk
    Illinois Pol1utio~(Control Board
    16
    —590

    Back to top