1. 16 523
      2. Supreme Court upheld a $3,500 penalty against a company that
      3. installed and operated equipment after the Agency had denied
      4. its applications for permits.
      5. With respect to the other sixteen units involved in
      6. this proceeding, Edison claims technical inability to meet
      7. the May 30, 1975 deadline. At the outset it should be noted
      8. that one of these units, Powerton 4, was not involved in the
      9. for this unit (March 1, 1973) had contemplated its future
      10. use as a test bed for Edison’s coal gasification project.
      11. Rather than deny the petition, necessitating institution of
      12. the variance process all over again, we granted a six month
      13. variance subject to a megawatt output restriction and the
      14. submittal of a program listing specific dates within which
      15. compliance could be achieved.
      16. Edison claims that that variance should have cleared
      17. the way for the issuance of permits by the Agency in this
      18. matter except for two problems: plans to convert the Sabrooke
      19. station to the use of distillate oil were stymied by the
      20. White House Energy Policy Office; and it could still not get
      21. permits for the Waukegan units because compliance prior to
      22. the May 31, 1975 deadline was not indicated (R. 81—82).
      23. Although Edison alleges that the way should have been cleared,
      24. the record does not indicate that any effort was in fact
      25. made to obtain the permits at that time. Furthermore, from
      26. the time the permits were originally denied, in April, 1973,
      27. 16—527

ILLINOIS POLLUTION CONTROL BOARD
May 8,
1975
ENVIRONMENTAL PROTECTION AGENCY
Complainant,
v.
)
PCB 73-372 through
PCB 73—379
COMMONWEALTH EDISON COMPANY,
Respondent.
Mr. Kenneth J. Gumbiner and Mr. Marvin I. Medintz, Assistant
Attorney Generals, appeared for the Complainant;
Mr. Richard
E.
Powell,
Isham, Lincoln & Beale, appeared for
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Dumelle):
These consolidated enforcement actions were filed
August 31,
1973.
Commonwealth Edison
(Edison)
is charged,
in each of these cases, with failure to obtain necessary
operating permits as required by Rule
103(b) (2)
of Chapter
2,
Part I of the Rules and Regulations Governing Air Pollution
and
Section
9(b)
of the Environmental Protection Act.
The
Regulation requires that the permits be obtained by April
1,
1973.
The published deadline for submittal of permit
applications was February
1,
1973.
The Environmental Protection
Agency
(Agency) granted Edison an extension of the date to
file until March
1,
1973
(R.
74,
90).
In all, nineteen
generating units located at eight different facilities are
involved in the proceedings.
More specifically, the units
involved are:
Case No.
Units
73-372
Kincaid
1 and
2
73-373
Sabrooke
1 through
4
73—374
Powerton
4 and 5
73-375
Waukegan 5 through
8
73—376
Dixon
5
73—377
Crawford
8
73-378
Joliet
5 through
8
73—379
Fisk 19
16—521

—2—
At the first
day
of hearings, October
15,
1973, Edison
stipulated that it had not obtained permits up to that date~
On December
6,
1973 the Pollution Control Board
(Board)
denied Edison~sMotion For Stay and Related Relief pending
judicial resolution of its appeal of the Board~sadoptior. of
numerous
rules
of
Pollution
Control
Board
Regulations,
Chapter
2
(Air Pollution Regulations).
10 PCB 257.
In that
Order we indicated that the variance procedure was available
as
the
means
to
raise
the
issue
of
substantial
hardship.
Edison filed a petition for variance,
PC.
7til6,
for. many of
tOe units in\olved rereum or January
Ii, 1974
A motion to
consolidate the ensorcement and variance cases was denied on
January
17,
1974
(10 PCB 667)
.
However,
on ME.rch
7,
1974 we
granted
a motion to postpone near~nas
~r
th~smatter urt~i
after
t.h.e receipt
Of
transcri..pts in the var.iance proceeding
(11 PCB 461)
.
Accordingly,
the hearings
in this matter
resumed, and concluded,
on November
6,
1974.
Edison initially filed pErmit applicati...ons,
includi...ng
compliance plans,
f..or all of t.±eseunits wi.th
t.he Anency on
March
1,
1973.
Notice of rejection of the.se applications by
the Agency was .eceived
in. earlv April,
1973
(P.
74~74)
Edison
ciLtes two reasons why opera.ting permits nnmrm denied.
thrst, umtn respect
to
~se
~oits (F~saJ9, Cratiora
8 anct
Drmcn
5)
,
it
c~arms
toe
~ncy
nas not
satrsfied wstr
either the amount or
type. of ~data subm~tteti,.and
reg:uired.
the filsog of adoitrmr ~tiormatior
(P.espoodenths Ermef,
p
2).
Permits were~~subsequently iseued for t.hese units on
th.e
dates indicated in the discussion below.
Second, with
respect to the remaining sixteen units, Edison
c aims that
the permits were denied because the compliance plans extend.ed
beyond the May 30,
1975 deadlire for t~~henew particulate and
sulfur dioxide emission standards in Rules 203 and 204.
EdisonCs inability to meet this deadli.ne has been the subject
of other proceedings before the Board.
In PCB 7til6,
decided
on January
3,
1975, we granted Edison variances
f..rom either
or both SO2 and particulate standards for many of the units
involved herein.
The extensive record in that variance
proceeding was incorporated in full in these proceedings by
stipulation of the parties
(R.
61).
We refer the reader to
our opinion in PCB 74~l6for a discussion of the control
technology and compliance difficult...ies~
For purposes of clarity we will first consider the
generating units for which permits were subsequently issued.
These units include Dixon
5, Fisk 19 and Crawford 8.
Edison~scontention that the initial perfrtit denials resulted
from Agency dissatisfaction with either the amount or type
of data submitted is ovethsimplified and misleading.
In the
case of Dixon
5, Edison claims that the permit was denied
for the simple reason that numerical limits were not expressed
in pounds per million BTU,
as required by the Agency
(R,
77).
More importantly, however, the data submitted
show
16
522

compliance with the 1975 standards in only two of eight
tests
CR.
77~-78).
Edison
had
intended
to
achieve
compliance
by use of a special Illinois coal,
By late 1973 it was
determined that this coal was not availa~bieand in March
1974
tests
were
run
using
an
Illinois
coal
of
higher
sulfur
and
ash
content,
Results
indicated
compliance
with
the
1975
standards.
Edison
resubmitted
its
application
on
April
17,
1974
and
a
permit
was
qranted
on
May
25,
1974.
In
the
case
of
the
Fisk
19.
and
Crawford
8
units,
Edison
had
.intended
to
burn
low
sulfur
coal,
but
feared
that
this
would
result
in
precipitator
degradation.
Thus,
rather
than
the
initial
permit
denials
being
a
resu.t
of
Agency
dissatisfaction
with
the
data
submitted,
it
is
clear
that
the
original
applications
did
not
ir~ fact.
demonstrate
compliance
within
the
required
deadline.
A
test
at
Fi.sk
19
in
April,
1974,
howeverr,
indicated
that
the
coal
proposed
for
u.se
would
not
result
in
su.ch
degradation,
and
that
this
would
allow
Edison
to
achieve
comp.liance
with
both
the
particulate
and
sulfur dioxide standards
CR.
78~79)
.
This
was
confirmed by
a test at Crawford 8 in August,
1973
CR.
78,
98).
Transmittal
of these test results
to the
Agenby,
however, did not occur
until new permit applications were filed on October
1,
1973
CR.
98)
.
Permits
were
issued
for
these units in November,
Although Edison was subsequently able to amend its
compliance plans for these three units, enabling it to
obtain permits, substantial delays beyond the required
permit date were involved,
Edsson argues that tnese cases, involving units now in
compliance are essentially moot and ought to be dismissed,
This argument is without merit.
We have consistently held
in the past that late compliance with regulations requiring
permits to be obtained does not moot the issue of violation
of
the
regulation.
EPA
v,
Iowa~Illinois
Gas
and
Electric
Co.,
PCB 72~2l6, 5 PCB 67,69
CJuly 25, 1972); EPA v, Procter
&
Gamble Manufacturing Company, Inc.,
PCB 72~2lO, 5 PCB 165,166
CAugust 15,
1972).
~o hold otherwise would effectively
undermine the heart of a permIt program.
As we indicated in
our opinion accompanying the new emission standards in the
Air Regulations,
~we cannot be content simply to set a
future compliance date and to wait until then before taking
any action to assure that something is being done~
(In The Matter of Emission Standards, R71~23,
4
PCB 298 at
304, April
13,
1972)
In this instance the present enforcement
action was required as a catalyst to precipitate Edison~s
16
523

—4—
compliance plans.
Without such action there could. be no
assurance that compliance with deferred standards would be
timely achieved. We impose a monetary penalty in cases
such
as this as an aid to the enforcement of the Act.
In EPA v. Handschy
Chemical Company, PCB 74-477
(April
4,
1975)
we assessed a
$500 penalty where the respondent abandoned its efforts to
obtain an operating
permit after two rejections,
even though
a subsequent grant of the permit indicated compliance with
emission standards.
We
consider
similar
penalties
of
$500
for each of these three units
to
be
appropriate
here,
for
a
total of
$1, 5O0~.
Here, where
compliance
of
emission
standards
was ultimately
achreved
befcre
the
date
recuired,
we
consider
it
a
mitigating
factor
that
no
actual
damage
to
the
public,
in
the
form
of
lower
amb:Lent
air
quality,
resu:Lted
from
the
delays
in obtaining the necessary
permits.
In Southern Illinois Asnhal~
Co
v
Pollution
Control
t3oati
(1975)
,
~
(Do~kethc4T3Lt
I
~lrm~
~s
Supreme Court struck down the Board~s
imposition
of fines
against two companies
--
one that
had failed to apply for a
permit and one that was in violation
of a substantive
standard.
The Court noted, however, that in both
instances the
violations
had ceased long before the Agency instituted its enforcement
action.
In the case of one company, Southern
Illinois
Asphalt,
the Court noted that the failure to obtain a permit
was mere inadvertance,
resulting
from the company’s assumption
that its supplier had
filed
the necessary application forms
for it.
Moreover, the court also noted that as soon as the
company learned of this situation,
it immediately took steps
to remedy
it, and had actually ceased operations
long before
the complaint was filed.
Unlike those cases, the instant
enforcement action was filed before the violations had
ceased.
(In the case of Dixon
5, the complaint was filed as
much as 7-1/2 months prior to the date Edison even reflied
its permit application.)
Furthermore, Edison~sfailure to
obtain the necessary permits was not a matter of mere inadvertance,
but rather the result of a failure to propose a compliance
plan capable of bringing its facilities within the standards
to be applied.
We are of the opinion that the instant case
more resembles the facts in Mystic Tape v. Pollution Control Board
(1975), _____Ill, 2d_______(Docket No. 46543)
,
in which the
Supreme Court upheld a $3,500 penalty against a company that
installed and operated equipment after the Agency had denied
its applications for permits.
With respect to the other sixteen units involved in
this proceeding, Edison claims technical inability to meet
the May 30, 1975 deadline.
At the outset it should be noted
that one of these units, Powerton
4, was not involved in the
variance proceeding
-
PCB 74-16.
The initial permit application
for this unit (March
1,
1973)
had contemplated its future
use as a test bed for Edison’s coal gasification project.
16—524

—5—
The compliance plan submitted extended beyond mid-1975 and
the permit was thus denied
(March 29,
1973).
Consequently
Edison reconsidered and elected to show the unit retired
from coal—fired service in October,
1974.
The application
was refiled on October
1,
1973 and a permit
was
granted
on
January
9,
1974,
Here again,
failure
to
timely
obtain
the
necessary permit
is
not
a
matter
of inadvertance hut
is
rather
the
result
of
a failure to
show
an
adequate
comuliance
plan,
Also,
we
note that the ref
fling
did
not
occur
until
the day after the instant action
was
fi:LE~d,
We
thus
elect
to
treat
LOis
anin.
in toe same
manner
tie
~hle~
dusussed
above.
A penalty of
$500
for this
violation
is
also
assessed.
Of
the
remaining
15
units
involved
in
this
action,
eight
were involved
in
variance
proceedings
previous
i::o
PCB
74-16.
An earlier variance request, filed January 30,
1973,
(and consolidated with an enforcement proceeding filed on
December 14,
1972)
for Waukegan 5,
6,
7, and 8 and Sabrooke
1,
2,
3, and 4 was granted by the Board on October
4,
1973
and amended November 29,
1973
(PCB 73-40;
9
PCB 367;
10
PC]3
143).
In that Opinion we assessed a fine of $1,000 for the
Sabrooke station for violation of the Act, the particulate
standards of the Rules and Regulations Governing the Control
of Air Pollution.
We also granted the Sabrooke units variance
from the particulate standards until oil conversion could be
accomplished on various dates ranging between September 30,
1973 and September 30,
1974.
We assessed a fine of $30,000
for similar violations
at the Waukegan station and we granted
a variance from the particulate standards until April
4,
1974.
With respect to the Waukegan station we noted that
Edison had not given us
a definitive time schedule for
compliance
—-
a serious omission in its variance petition.
Rather than deny the petition, necessitating institution of
the variance process all over again, we granted a six month
variance subject to
a megawatt output restriction and the
submittal of
a program listing specific dates within which
compliance could be achieved.
Edison claims that that variance should have cleared
the way for the issuance of permits by the Agency in this
matter except for two problems:
plans to convert the Sabrooke
station to the use of distillate oil were stymied by the
White House Energy Policy Office;
and it could still not get
permits for the Waukegan units because compliance prior to
the May 31, 1975 deadline was not indicated
(R.
81—82).
Although Edison alleges that the way should have been cleared,
the record does not indicate that any effort was in fact
made to obtain the permits at that time.
Furthermore,
from
the time the permits were originally denied,
in April,
1973,

—6—
Edison made no
attempt
to
request
a
permit
appeal
or
to
file
for
variance
from
the
permit
requirements
on
the
basis
of
the variances granted in PCB 73-40,
Rather,
it merely
waited
until
January
II,
1974
to
file
a
new
variance
petition
PCB 74—16 ——for most of the units involved herein, including
the Sabrooke and Waukegan units.
That date was 1-1/2
months subsequent to our modification of the Order in PCB
73~4Oand 4—1/2 months subsequent to the filing of this
complaint.
Edison’s
lethargy in this regard is exemplified
by the situation involving Sabrooke Units
3 and
4.
These
units
received
authorization
from
the
Energy
Policy
Office
on
June
18,
1974
to
procOed.
with
oil
conversion.
As
a
result
they
are
now
in
compliance
and
the
petition
for
variance for these
u.nits was dismissed in PCB 74-16.
By the
date
of
the
final
hearing
in
this
case
on
November
6,
1974,
however,
almost
five
months
after
the
authorization,
Edison:
could
only
claim
that
“perm.it
applications
for
these
two
units are now being prepared”
(R.
82).
In
li.ght
of. this
history
of
delay
we
remain
rather
incredulous
at
Edison’s
additional
assertion
that
if
variances
are
issued
in
PCB
74—
16 it would expect to “resubmit promptly permit applications
for those stations.”
(R.
83-84).
Except for Wau]cegan
8,
(which was judged to be capable
of
compliance),
the
remaining
units,
including
Waukegan
5,
6,
and
7,
and
Sabrooke
1
and
2,
received
variances
from
the
substantive requirements of either or both the particulate
or
sulfur
dioxide
standards
of
Rules
203
and
204
in
our
recent
decision
PCB
74-16.
That
variance
petition
was
not
filed
until
January
11,
1974,
long
after
the
permits
were
originally
denied
and
subsequent
to
the
initiation
of
this
enforcement
action,
In
addition,
it
appears
that
Edison
does
not
accept
some
of
the
terms
of
that
variance.
A
Petition
for
Modification
or
For
New
Variance,
filed
on
February
18,
1975,
indicated
that
Edison
may
not
be
able
to
meet
the
sulphur
dioxide
limits
imposed
with
respect
to
the
Waukegan
Units
5,
6,
and
7,
and
Joliet
Units
7
and
8,
and
that
the
coal
gasification
plans
for
Powerton
5
and
Kincaid
I
and
2
have
now
been
abandoned.
In
an
Opinion
issued
February
27,
1975
the
Board
ordered
clarification
of
Edison’s
position
and
determined
that
the
Petition
would
be
considered
as
a
new
variance
petition
which
was
subsequently
assigned
a
new
docket
number
~-
PCB
75-100.
Edison
contends
that
the
granting
of variances in
PCB
74~l6
serves as an absolute defense
to
this enforcement action.
This
argument
relies
on
Section
33(c)
of
the
Environmental
Protection Act which requires the Board to consider the
technical practicability
and economic reasonableness
of

—7—
reducing
emissions.
What
the
Board
determines
with
regard
to
these
factors
in
a
variance
case
certainly
bears
upon
our
considerations
in
an
enforcement
case
involving
the
same
emission
sources,
but
only
insofar
as
the
enforcement
case
involves
alleged
violations
of
the
substantive
standards
a
respondent
claims
it
is
technically
and
economically
unable
to
meet.
One
of
the
functions
of
a
permit
program,
however,
as
we
said
in
In
The
Matter
of
Emission
Standards,
is
“to
aid
in
obtaining
emission
information
necessary
for
an
evaluation
of
the
control
program...”
(4
PCB
at
302).
Had
Edison
here
filed
a
permit
appeal
or
variance
petition
from
the
permit
requirements
immediately
after
the
initial
denial,
and
raised
such
issues
as
technical
and
economi.c
feasibility,
such
an
evaluation
would
have
occurred
long
betore
it finally d~din PCB 74-16,
and saved tnat much
time
~r
any
comptiance
schedule
f~ralrm
acreed
to
by
abe
Board
Again
we
note
that
these
vic!nt~ons
are
not
result
of
inadvertance.
Nor
were
they
ceased
prior
to
the
filing
of
this
action,
Edison
was
aware
of
t.he
permit
requirement
from
the
beqinning,
but
failed
to
institute
compliance
p1 ans
adequate
to
quali.fy
for
the
necessary
permits.
Edison
neither
appealed
th.e
permit
:der,i.als
nor
sought
a
variance
from
the
permit
requirem.ent
on
the
grounds
of
technical
infeasibility.
Such
an
issue
was
not
raised
urti..I
PCB
74—16
was
filed
—-
nearly
9-1/2
months
after
the
iiiitial permit denials,
8-1/2 months after the date
on which
permits
were
requi:ced,
and
4—1/2
months
after
this
complaint
was
filed,
For
Edison’s
continued
delay
discussed
herein,
and
as
an
aid
to
enforcement
of.
the
Act,
we
feel’
that
more
substantial
penalties
of
$1,000
each
are
wqrranted
for
these
fifteen
generating
uni.ts,
for
a
total
of
$15,000.
Having
considered
the
entire
record
in
this
matter,
it
is
the
finding
of
the
Board
that
Edison
violated
Rule
103(b)
(2)
of
the
Regulations
and
Section
9(b)
of
the
Act
for
each
of
the
nineteen
generating
units
involved
herein.
A
civil
penalty
in
the
total
amount
of
$17,000
is
appropriate.
This
Opinion
constitutes
the
Board’s
findings
of
fact
and
conclusions
of
law.
Mr.
Goodman
dissents,
ORDER
It
is
the
Order
of
the
Pollution
Control
Board
that:
I.
Commonwealth
Edison
shall
apply
for
permits
required
by Rule 103(b) (2)
of Chapter
2,
Part
2
of
the
Rules
and
Regulations Governing Ai,r Pollution and Section
9(b)
of the
Environmental Protection Act.
16—527

—8—
2.
Commonwealth Edison shall pay, within
35 days of
this Order,
the sum of $17,000 as penalty for the violations
of Rule 103(b) (2)
of Chapter
2, Part
2 of the Rules and
Regulations Governing Air Pollution and Section 9(b)
of the
Environmental Protection Act.
Penalty payment by certified
check or money order payable to the State of Illinois shall
be made to: Fiscal Services Division, Illinois Environmental
Protection Agency,
2200 Churchill Road,
Springfield,
Illinois
62706.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, here~ certify the above Opinion and Order were
adopted on the
~
day of May
1975 by a vote of
4/_~j
Christan L. Moffet
Illinois Pollution
r?rol Board
16—528

Back to top