1. IT IS SO ORDERED.
      2. I, Christan L. Moffett, Clerk of the Illinois Pollution
      3. Control Board, hereby certify the above Opinion and Order were
      4. ChristanL. Moffett, perkIllinois Thllution Control Board

ILLINOIS POLLUTION CONTROL BOARD
April
~4,
1975
CATERPILLAR TRACTOR COMPANY,
Petitioner,
v.
)
PCB
75-54
ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
Mr.
Richard
J.
Kissell,
Martin,
Craig,
Chester
&
Sonnenschein,
appeared on behalf of petitioner;
Mr.
John
T.
Bernbom,
appeared on behalf of respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Dumelle):
This petition
for variance from
the Water Pollution
Regulations
(Chapter
3)
was filed on February
4,
1975.
Petitioner,
Caterpillar Tractor Company seeks
an extension
of
a variance previously granted
to
it on October
24,
1974
(Caterpillar
v.
EPA,
PCB 74-233,
14 PCB
237).
In PCB
74-
233,
the Board granted
a variance from Rules
205,
404(a),
404(b) (ii),
902,
903,
and 1002 from June
19,
1974 until
January
1,
1975.
In this petition Caterpillar requests
a
variance from Rules
404(b) (ii),
902 and 1002 effective
January
1,
1975 until July
1,
1977.
The Environmental Protection Agency filed
its Recommendation
which supported
the petition on March
12,
1975.
No public
hearing was held.
Caterpillar owns and operates
a manufacturing plant
on
Route
6 in Joliet.
The plant,
which employes approximately
6,000 persons, produces earth—moving
and construction machinery
and equipment.
Caterpillar discharges
its effluent
from the
Joliet Plant
into the Des Plaines River which has
a 7-day,
10-year low flow of
1,000 MGD.
Caterpillar,
which discharges
an average
flow of
.77
MGD
alleges that even based upon
a
maximum excess BOD5
discharge
of
70 ppm,
its effluent
would contribute only
0.3 percent additional
BOD load
to the
Des Plaines River.
In its original variance request, granted
in PCB
74-
233, Caterpillar alleged inability
to comply both with the
then applicable
BOD standard of Rule 404(a)
(30 mg/l)
and
16—473

—2—
with the more
stringent BOD requirement of Rule 404(b) (ii)
(20 mg/l)
effective December
31,
1974.
Caterpillar alleged
that
it had retained
a consulting firm
for the purpose
of
recommending
a plan
to correct
the effluent problem.
Our
Opinion
in PCB 74-233 granted the variance until January
1,
1975
so that Caterpillar could receive and review its consultant’s
recommendation.
In the instant petition,
Caterpillar again
alleges
its inability
to comply with the BOD standards
of
404 (b) (ii)
.
Caterpillar also states that its consulting
engineers
submitted
a report on November
7,
1974,
recommending
that
an activated sludge plant
be installed to facilitate
BOD removal.
The
recommendation was based on three factors:
1.
Treatability studies indicated that activated
sludge will provide stable and efficient operation;
2.
Activated sludge offers greater flexibility than
other treatment alternatives available,
including aerated
lagoon,
synthetic media trickling
filter,
biological
fixed
film rotating
disc and submerged
(upflow)
biological
filter;
3.
Activated sludge
is cost competitive with the
other biological treatment methods
studied.
As
a result
of this recommendation,
Caterpillar now proposes
the following
time schedule
for completion of the activated
sludge
system:
Commence
final design
May
1,
1975
Completion
of final design
-
December
31,
1975
Award of construction grant
-
June
1,
1976
Completion
of construction
July
1,
1977
Caterpillar provides
the following data regarding the
average monthly
levels of BOD
in
its effluent at
its Joliet
Plant.
DATE
BOlD
(mg/i)
June,
1974
116
July,
1974
56
August,
1974
91
September,
1974
86
October,
1974
69
November,
1974
69
December,
1974
62
January,
1975
127
These figures
are considerably higher than the earlier
averages presented
in PCB 7~233 and recorded in our Opinion
therein.
This
is understandable
in view of the fact that
the improper laboratory procedure which yielded low BOD

—3—
levels was not discovered until May,
1974.
Agency grab
samples indicated BOD concentrations
at
the following
levels:
DATE
BOD
(mg/l)
March
1,
1974
95
April
11,
1974
85
July
9,
1974
60
January
16,
1975
15
Caterpillar alleges that failure of the Board to grant
its instant variance request will impose
an arbitrary
and
unreasonable hardship
since
it cannot currently control
the
discharge of BOD to meet applicable
standards;
that enforcement
of the standards will jeopardize operation of the plant;
and
that the discharge will not cause significant harm to the
Des Plaines River.
Our Opinion in PCB 74—233 recognized CaterpillarTs good
faith in engaging a consultant prior
to filing the petition
therein.
The Agency,
in a recommendation to grant the
instant petition, filed on March 12,
1975, expressed an
opinion that Caterpillar has continued to act in good faith
in developing
an abatement program.
We agree that the
compliance plan proposed by Caterpillar continues to evidence
such good faith.
The Agency recommendation points out that on September
30,
1974, approximately three weeks before the Board’s
decision in PCB 74-233, Caterpillar was issued an NPDES
Permit for its Joliet facility (IL000 1732).
The dates
which Caterpillar sets out in this petition for the design,
construction,
and completion of the activated sludge system
are the same dates which are contained in the schedule of
compliance
in the NPDES Permit, and the Agency feels these
dates are a reasonable assessment of the actual time needed
for the completion of the system.
The NPDES Permit does not
specify
a numerical or effluent limitation for BOD for the
period from the date of issuance of the permit until the
proposed date of completion of the activated sludge plant on
June
30,
1977,
but Caterpillar is required to monitor its
effluent daily for gOD.
After June 30,
1977 until the
expiration date of the permit, Caterpillar is required to
meet a daily average BOlD5
limitation of
20 mg/l,
and a
daily maximum of
50 mg/l
We shall set a maximum of 130 mg/l
of BOD on
a monthly average basis.
The Agency
feels that although the compliance schedule
set out in Caterpillar’s NPDES Permit serves as a deterrent
from delay in completion of the activated sludge system,
a
variance issued by this Board should be limited to no more
than one year in order to insure that Caterpillar maintains
16—475

—4—
“good housekeeping and continues to exercise all possible
care to maintain its BOD discharge at the lowest possible
level”
(Agency Recommendation,
p.
6).
We agree that such a
time frame is appropriate.
Caterpillar also seeks variance from the permit requirement
of Rule 902 and
the filing of
a project completion schedule
requirement of Rule 1002.
As we pointed out in PCB 74—233,
Rules 902 and 903 were replaced by Rules 952
arid 953 effective
October 11,
1974 but suspended until the earlier of January
31,
1975,
or the date the U.S.
Environmental Protection
Agency fails
to approve the Illinois NPDES Permit Program.
These rules are now effective and Caterpillar needs the
variance regardless of the fact that it has an NPDES Permit.
Rule 1002
(b) (ii)
requires that a discharger,
“shall file a
project completion schedule” including “a time schedule for
the project’s completion which must meet the applicable
deadlines.”
We also grant a variance from this Rule.
The
Agency would subject such
a variance to the condition that
Caterpillar file a Project Completion Schedule indicating
compliance dates, notwithstanding. that such schedule fails
to meet the required applicable deadlines.
This would
appear to be unnecessary since Caterpillar has already filed
its compliance schedule in connection with its NPDES Permit.
This Opinion constitutes the Board’s findings of fact
and conclusions of law.
ORDER
1.
Variance trom Rules 404(b) (ii),
952,
953,
and 1002
is granted from January
1,
1975 until December 31,
1975
subject to the condition that Petitioner’s BOD discharge
not
be increased in strength or quantity beyond present levels
and in no month shall it exceed 130 mg/i on a monthly average
basis.
2.
The following checkpoint dates shall be met by
the Petitioner:
Commence final design
May 1,
1975
Complete final design
December 31, 1975
Award construction grant
-
June 1,
1976
Complete construction
July 1,
1977
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board,
hereby certify the above Opinion and Order were
adopted on the~’~’ day of April,
1975 by a vote of
4.~-c~
ChristanL.
Moffett, perk
Illinois Thllution Control Board
16 —476

Back to top