ILLINOIS POLLUTION CONTROL BOARD
    October 24,
    1974
    CON AGRA,
    INC.
    Petitioner,
    v.
    )
    PCB 74—311
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    Mr. Thomas J.
    Immel, attorney for Petitioner.
    Mr. Roger Zehntner, attorney for Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Dr.
    Odell)
    On August 22,
    1974, Con Agra,
    Inc. filed with the Pollution
    Control Board
    (Board)
    a Petition For Variance from Rule 203(b)
    of
    the Air Pollution Regulations
    (Chapter Two).
    Petitioner sought
    a
    six-month variance for emissions resulting from the operation of
    a hammermill
    at its flour mill in Chester, Illinois.
    Petitioner
    has headquarters
    in Omaha, Nebraska;
    it purchased the Chester,
    Illinois facility in January, 1972.
    The plant processes wheat into
    flour and pulverizes with
    a harnmerrnill the remaining by-product
    chaff and unusable shrivelled wheat into pellets for cattle feed.
    The grinding action of the hammerraill creates
    large volumes of air
    and entrains significant quantities
    of particulate matter.
    This
    air is vented through two 1946 cyclones into
    a common stack and
    out into the atmosphere.
    Petitioner estimated that total emissions
    from the hammermill
    ——
    which processes
    600 lbs/hour of by-product
    ——
    were 2.6 lbs/hour
    (Exhibit “C”).
    Rule 203(b)
    limits emissions to
    1.83 lbs/hour.
    Petitioner stated, that the haxnmermill
    is the only
    equipment that can successfully accomplish the pulverizing process.
    To achieve compliance, Con Agra,
    Inc. intends
    to install a
    Buhier model ASF-24 air shock stocking filter costing $10,500.00.
    Petitioner estimates that emissions from the filter will be zero;
    the equipment has already been ordered.
    However, application has
    not yet been made for a construction permit from the Environmental
    Protection Agency (Agency).
    In fact, Petitioner did not apply for
    an operating permit for its wheat cleaning house until sometime in
    early 1974,
    although Rule 103(b) (2) (A)
    requires Petitioner to have
    had a permit for its milling operations by January
    1,
    1973.
    The
    fact that the permit for the hainrnermill operation was denied in
    1974 is the reason that a variance is now necessary.
    Petitioner
    has an annual payroll of $800,000.00 and more than 50 full-time
    employees.
    Con Agra,
    Inc. stated that neighbors had not complained
    about emissions caused by the operation of the facility.
    14—295

    —2—
    The Agency filed its Recommendation on October
    1,
    1974.
    It disapproved of the method in which Petitioner calculated its
    emissions and found the total particulate emission rate to be
    5.22 lbs/hour.
    The Agency argued that since Con Agra,
    Inc. had
    failed to comply with Rule
    203(b)
    on April 14, 1972,
    that under
    Rule 203(c)
    ,
    it must meet the requirements of Rule 203(a)
    of Chapter
    Two.
    Rule
    203(a)
    limits emissions to 1.35 lbs/hour.
    We agree with
    the Agency.
    Rule 203(a)
    is applicable to this Petitioner because it
    neither met the Rule 203(b) standard on the effective date of the
    Rule (April 14, 1972), nor satisfied both of the conditions set out
    in Rule 203(c) (1)
    and
    (2)
    of Chapter Two.
    The Agency estimated that the Buhler model ASF—24 air shock
    stocking filter would reduce emissions
    to
    .01 lb/hour.
    While
    acknowledging the effectiveness of this program of compliance, the
    Agency recommended that the variance be denied because:
    11)
    In light of Petitioner’s failure to obtain an
    operating permit
    (for its facility) by February 1,
    1973,
    (sic)
    as required by the Pollution Control Board Regulations,
    and the failure to seek either an operating permit or
    Variance during the course of the next year,
    the Agency does
    not view the Petitioner’s Variance request with favor.
    By
    its dilatory actions, Petitioner chose to run the risk of
    enforcement and has openly admitted continuing violation.
    The Agency will not now approve of such lack of diligence
    by recommending that Petitioner’s Variance request be
    granted.
    12)
    Moreover, the Agency emphasizes the fact that
    Petitioner did not apply for a construction permit prior
    to the decision to order its proposed control device.
    The Agency agrees that the device,
    in all probability,
    will work successfully
    so as to meet the Regulations.
    Probability of success, however, does not relieve the
    Petitioner from its duty to obtain the requisite permits.
    The construction permit procedure is designed to insure
    compliance, particularly before an applicant becomes
    detrimentally bound to a specific control program.
    The
    procedure is dependent upon good faith companies respecting
    the function and validity of such procedure.
    Entering into
    binding contracts for proposed control equipment prior to
    receipt of Agency approval
    (as evidenced by a valid con-
    struction permit) does not indicate such respect.
    If the
    permit system is to succeed
    (or pollution control generally),
    a company such as Petitioner’s must not be allowed to com-
    ply in its unbridled discretion or its own due time.”
    14— 296

    —3—
    On October 4,
    1974,
    the Petitioner responded to the
    recommendation of the Agency.
    In pertinent part, Petitioner
    declared it had not been dilatory in complying with the law,
    because, being an out-of-state company,
    it had taken time for
    it to become familiar with the environmental laws of Illinois.
    Second, Petitioner admitted that control equipment had been
    ordered September 4,
    1974, without a construction permit;
    it
    argued that these efforts were made in good faith to facilitate
    early compliance
    in the face of expected delivery delays. Further-
    more, Petitioner remarked that the regulations only require that
    control equipment be installed after receiving
    a construction
    permit.
    “Whether such equipment
    is purchased, wisely or unwisely,
    is exclusively the concern
    (and the risk)
    of the purchaser”
    (page 4).
    After filing its Petition, Petitioner learned that “five months
    would be required for delivery of all component parts of the control
    equipment”
    (page
    3) instead of
    60 days as had been estimated in the
    August 22, 1974, Petition for Variance.
    On October 18, 1974, the Agency answered the Petitioner’s
    response and reiterated its position that the Variance be denied.
    We grant the Variance.
    While ignorance of the law does not
    excuse delayed compliance, the granting of this Variance will not
    preclude an Agency enforcement action for those earlier periods
    when the Petitioner was allegedly in violation of the Environmental
    Protection Act and the regulations.
    Second,
    Con Agra,
    Inc. has
    demonstrated good faith in its recent efforts to abate the pollution
    problem.
    While we understand the Agency’s policy of requiring permits
    before purchase, Petitioner deserves some credit for its efforts
    -—
    and the self-imposed financial risk
    --
    to expedite equipment in-
    stallation.
    Finally,
    it does not appear that significant environ-
    mental harm will result from the grant of this Variance.
    While we
    are reluctant to grant a variance without data on the environmental
    impact created by the pollution source, the low emission rates and
    the short
    term
    nature of the excessive emissions convince us that
    it would be an arbitrary and unreasonable hardship to deny the
    Petitioner this reprieve from Rule 203(a) of Chapter Two.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board.
    ORDER
    1.
    Con Agra,
    Inc.
    is hereby granted
    a Variance from Rule 203
    (a)
    of Chapter Two from August 22, 1974,
    until March 22, 1975, or
    such earlier date that it can install a Buhier model ASF—24 air
    shock stocking filter to control particulate emissions caused by
    the operation of
    a hammermill at its facility.
    2.
    Petitioner shall apply for all necessary permits from the
    Agency.
    14
    —297

    —4—
    3.
    Petitioner shall submit to the Agency written progress
    compliance reports on January 22 and March 22, 1975, or such
    earlier date that it can install the air pollution control equip-
    ment specified in Order 1,
    above.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, her~bycertify
    h t the above Opinion and Order w~sadopted
    on the.~~day of
    _____________,
    1974, by a vote of ~
    to
    Christan L. Mc2~tt
    14—298

    Back to top