ILLINOIS POLLUTION CONTROL BOARD
April
24,
1975
AIRWAY PRODUCTS CORPORATION,
)
)
Petitioner,
)
)
)
PCB 74—472
)
ENVIRONMENTAL
PROTECTION
AGENCY,
)
)
Respondent.
)
Mr. Richard
H.
Sanders, Attorney, appeared for the Petitioner;
Mr. Peter
E. Orlinsky, Attorney, appeared for the Respondent.
OPINION AND ORDER OP THE BOARD
(by Mr. Zeitlin)
Airway Products,
Inc. (Airway),
on December 13,
1974, filed
a
Petition for Variance from the requirements of Rule 205(f)
of
the Air
Pollution Regulations of the Pollution Control Board
(Board).
The Variance
is sought until December 31,
1975,
and would essentially constitute an
extension of a Variance previously granted by this Board, which expired
on December 31,
1974.
PCB
73—554,
11 PCB 495(1974).
Rule
205(f) limits the emission
of organic materials
to a discharge
of
8 pounds per hour.
It was shown in the prior Variance case that
Petitioners Schiller Park,
Illinois plant emits
up to 67 lbs./hour of
nonexempt, photochemically
reactive solvents
11 PCB at 495.
Those
emissions are generated from electrostatic spray booths and bake ovens
used in the painting of grocery store shelves,
tables and check—out
counters manufactured
at Petitioner’s
facility.
Approximately 200
persons are employed by Airway at
the Schiller Park plant.
Airway’s compliance program when
it was granted the Variance in PCB
73—554 consisted of a switch—over
to
exempt, non—reactive solvents.
The
Board
in granting that Variance noted
that such solvents could not be
obtained at that
time.
The Environmental Protection Agency
(Agency)
agreed in its Recommendation,
in
that case,
that such exempt solvents
were not at that time available,
and recommended
that the Variance in
PCB 73—554 be granted.
In the instant Petition, and in an amendment thereto filed January
29,
1975, Airway has once again alleged that exempt solvents are not
available..
Airway now, however, has proposed. alternate compliance
plans.
Airway’s primary plan for achieving compliance with Rule
205(f)
is now a switch—over to water reducible spray painting processes.
Alternatively, Airway proposes that,
if the switch—over
to water reduc—
able spray painting is not feasible,
it will use a high solids liquid
paint
in its coating operations.
16—455
—2—
Airway has also considered several other methods for achieving compliance,
but alleges that none are practical at the present time.
It is unable to
obtain gas necessary to operate an afterburner; adsorption systems employing
activated carbon are rejected due to its large total exhaust volume;
it is
still waiting for a feasibility study regarding a wet scrubbing system.
In
the amendment to its Petition,
Airway proposed timetables for
achieving compliance using the
two alternate methods which it prefers
—
water reducible spray painting and high solids liquid paint.
The target
dates submitted for its primary compliance effort, water reducible spray
paints, indicated compliance by July 30,
1975.
The target date submitted
for
the high solid liquid paint alternative was also July 30,
1975.
(It
should be noted that Airway
is presently proceeding with the compliance
schedules employing both of these alternate methods.) Citing these
target dates in
its Recommendation,
the Agency while recommending the
requested Variance—felt that it would not be necessary that the Board
grant a Variance past the July 30,
1975 completion
date scheduled for
either of these alternate control methods.
At a hearing held on
this matter on March
19,
1975, Airway presented
testimony indicating that the time schedules submitted for compliance,
using either method
,
are very tight
(R.
10).
Other unchallenged testi-
mony presented at
the hearing indicated clearly that Airway is attempting
in complete good faith to achieve compliance with Rule 205(f), and that
it fully expects
to be in compliance by July 30, barring unexpected
delays.
A timetable submitted by Airway indicates that it is at least
even with its proposed schedule for switch—over to water reducible
paint,
and is only slightly behind schedule
in its testing and review of
high solid liquid paint.
(The schedule slippage with regard to high
solvent liquid paint does not seem particularly important in light of
Airway’s “85
per cent” certainty that the water reducible process will
be successful(R.
7)
).
Weighing the factors in this matter,
the Board is again disposed
to grant Airway the requested Variance.
Airway has successfully shown
that, despite its extensive good faith efforts,
it has been unable to
comply with the compliance plan which was considered in
the earlier
Variance case.
Further, Airway has clearly shown that it
is presently
making considerable efforts to achieve compliance, including a laudable
program of pursuing alternative methods
of compliance at
the same time.
The
same hardships which allowed our grant
of the earlier Variance are
still present, and once again the Agency has recommended that the Variance
be granted.
As
to the length of
the Variance, however,
the Board feels that the
Agency has successfully shown that a grant beyond July 30,
1975 would be
unwarranted.
Petitioner failed to show the likelihood of any material
delays in its compliance program,
and merely speculated that such delays
might happen.
Where a Petitioner has shown that,
as
is expected,
it is
complying with a reasonable compliance schedule, the Board cannot base
further Variance extension on mere speculation. Although Airway is
to be
lauded for
its attempt thus far,
it simply has not demonstrated any need
for a Variance beyond July
30,
1975.
This Opinion constitutes
the findings of fact and conclusions of
law of the Board
in this matter.
16 —456
—3—
ORDER
IT
IS THE ORDER of the Pollution Control Board that Petitioner
Airway Products
Inc. be granted a Variance from Rule 205(f)
of Chapter
2:
Air Pollution Regulations, from January
1,
1975 until July 30,
1975,
subject
to
the following conditions:
1.
Petitioner shall continue, as required under the prior Variance,
to utilize as much exempt solvent
as can be furnished by its suppliers.
2.
Within
30 days of the adoption
of this Order, Petitioner shall
submit a definite compliance program to
the Illinois Environmental
Protection Agency, specifing which method of compliance will be utilized,
interim construction dates,
and the final dates
on which compliance will
be
achieved.
Said compliance plan will be submitted to:
Environmental Protection Agency
Division of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield,
Illinois
62706
3.
Petitioner thereafter shall submit monthly progress reports, before the
10th of each month,
to
the Illinois Environmental Protection Agency,
indicating its effort to obtain such exempt solvents, and detailing
progress made toward compliance.
Such reports shall be submitted to:
Environmental Protection Agency
Division
of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield,
Illinois
62706
4.
Petitioner shall apply for and obtain all necessary Agency construc-
tion and operating permits.
5,
Within 35 days of
the adoption of this Order, Petitioner Airway
Products shall execute and forward to the address noted above,
a certifica-
tion of acceptance
in the following form:
CERTIFICATION
I
(We)
________________________
________
having read and fully understood the Order of
the Illinois Pollution Control Board
in PCB 74—472,
hereby accept said Order and the Variance granted
thereby, understanding that such acceptance is
irrevocable and renders binding all terms and con-
ditions therenf.
Signed
____________________
Title
_____________________
Date
_______
16—457
Mr. Dumelle dissents.
I,
Christan
L. Moffett,
Clerk of the Illinois Pollution Contro’, Board
hereby certify the above Opinion and Order were adopted on
the
~
day of _______________________________,
1975
by
a vote of ~to
4~.
16—458