ILLINOIS POLLUTION CONTROL BOARD
    March
    26, 1975
    CITY OF FAIRFIELD,
    Petitioner,
    V.
    )
    PCB 74—383
    ENVIRONMENTAL PROTECTION AGENCY,)
    Respondent.
    Mr.
    Richard
    C.
    Cochran, attorney for Petitioner.
    Mr.
    Michael Ginsberg, attorney for Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Dr.
    Odell)
    On October
    25,
    1974,
    the City of Fairfield filed its
    Petition for Variance with the Illinois Pollution Control Board
    (Board).
    On October 31,
    the Board passed an Interim Order re-
    questing information on the environmental impact of the particulate
    emissions on the community.
    Petitioner was given 45 days to submit
    this information with the 90-day requirement for final Board action
    under Section
    38 of
    the Illinois Environmental Protection Act
    (Act)
    to run from the filing of the required additional information.
    On
    November
    1,
    1974,
    the Illinois Environmental Protection Agency
    (Agency) objected to the grant of
    a variance and filed a Motion for
    Hearing.
    Fairfield sought
    a time extension from the October 31
    Interim Order date on December 12,
    1974.
    Th~±
    ~3oardgranted
    a 15—
    day extension on December 19.
    Fairfield’s Amended Petition was
    received by the Board on January
    2,
    1975.
    The Agency filed its
    Recommendation of denial on February
    4,
    1974,
    ten days before the
    hearing took place.
    In City of Fairfield v.
    Environmental Protection Agency
    PCB
    73-355;
    10 PCB 53
    (November
    8,
    1973)
    the Board granted the Petitioner
    a one year variance to operate its coal-fired boilers
    #1,
    #2, and #3
    in excess of the allowable particulate emission rates under the Air
    Pollution Regulations
    (Chapter Two).
    The Order provided that:
    “1.
    The subject boilers shall be operated only in
    unusual, emergency situations wherein the
    primary generating machines and the interconnection
    tie line are incapable of pr~~cingthe power de-
    manded;
    “2.
    Petitioner shall
    file quarterly reports with the
    Agency.
    Said reports shall indicate all opera-
    tions of boilers #1 and/or
    #2 and/or #3, the date
    of said operation, kilowatts generated by each
    generator on each day of operation, generators
    forces out of service on each day of operation of
    boilers
    #1 and/or
    #2 and/or
    #3 and the reason for
    16
    —201

    —2—
    the forced outage and the power demand to
    supply customers on each day of operation of
    boilers
    #1 and/or #2 and/or #3.”
    The rationale for not ordering compliance was that the boilers were
    only operated in emergencies and that compliance would cost $300,000
    to $450,000.
    Fairfield presently owns and operates the Fairfield Municipal
    Electric Power Plant which supplies the electrical needs of the
    companies and 6,000 residents within a two—mile radius of the City.
    Fairfield has four coal-fired boilers which drive four steam tur-
    bines.
    The City also has two diesel generators.
    An interconnection
    tie-line with Southern Illinois Power Cooperative
    (SIPCO)
    is
    an
    additional source of electrical power.
    Petitioner sought a one-
    year variance from Section
    9(a)
    of the Act, Rule 103(b)
    of Chapter
    Two which requires an operating permit, Rule 104 of Chapter Two
    which requires a compliance plan,
    and Rule
    203 (q) (1) (B)
    of Chapter
    Two which limits particulate emissions to 0.20 pound per million
    BTU input per hour.
    Petitioner also sought a one—year variance
    from Rule
    2-2.53 of the Rules and Regulations Governing the Control
    of Air Pollution.
    This Rule limits emissions to
    0.8 pound
    of
    particulates per million BTU input per hour.
    The variance was re-
    quested to permit the intermittent operation of
    its four coal—fired
    boilers during periods of emergency or when its two diesel genera-
    tors and the SIPCO tie—line could not supply the needs of consumers.
    The tie-line can normally provide 10,000 KW although Fairfield is
    only guaranteed 6,825 KW.
    The diesel generators have
    a combined
    electrical capacity of 4,000 KW.
    The four coal—fired boilers have
    a capacity of approximately 12,500
    1KW.
    The Petition for Variance included various tables showing
    the kinds of fuels and the hours of production of the electrical
    sources utilized by Fairfield over the last
    five years to supply
    its consumers.
    The tables indicate a shift towards less use of
    the coal—fired boilers.
    The quantities
    and percent of energy
    provided by each fuel
    for the past
    five
    (5)
    years and five
    (5)
    months are as
    follows:
    Fiscal Year
    Percent of Total Energy
    Ending
    Coal
    Fuel Oil
    Gas
    Provided by Each Fuel
    April
    30th
    Pounds
    Gallons
    MCF
    Coal
    Fuel Oil
    Gas
    1970
    71,214,100
    53,323
    38,624.0
    94.5
    0.9
    4.6
    1971
    74,118,480
    118,276
    59,580.0
    91.4
    1.9
    6.7
    1972
    74,155,000
    171,012
    63,733.7
    90.3
    2.6
    7.1
    1973
    53,982,600
    202,038
    25,964.0
    95.5
    0.3
    4.2
    1974
    31,315,000
    99,012
    18,841.2
    91.3
    3.7
    5.0
    1st
    5 Mo.
    of 1975
    2,316,100
    1,969
    500.3
    97.0
    1.1
    1.9
    16
    202

    —3—
    The hours of operation for each of the boilers at the Plant over the
    past five
    (5) years and five
    (5) months are as follows:
    Fiscal Year
    Ending
    April
    30th
    Year
    Ending
    April
    30th
    Steam
    Hours Operated
    -
    Boiler No.
    1970
    1971
    1972
    1973
    1974
    1st 5 Mo
    of 1975
    39,129,250
    4,575,000
    39,135,750
    7,661,550
    38,307,750
    8,588,750
    24,112,750
    5,159,850
    12,782,100
    3,096,250
    43,704,250
    89.5
    46,797,300
    83.6
    46,896,500
    81.7
    19,896,351 49,168,951
    49.0
    34,210,188
    50,088,538
    25.5
    10. 5
    16.4
    18
    .
    3
    10.5
    6.2
    6.8
    76.4
    On February
    4,
    1975,
    the Agency recommended that the variance be
    denied.
    The Agency included in its Recommendation the following table
    which details the calculated emissions of particulates and SO2 from
    the four coal—fired boilers:
    Allowable
    Partic-
    Boiler
    ulates
    No.
    Rule
    2—2.53
    lb/lU6BTU
    1
    2
    3
    4
    0.8
    0.8
    0.8
    0.8
    Allowable
    Partic-
    ulates
    Rule 203(g)
    lb/1O6BTU
    0.27
    0.27
    0.20
    0.20
    Allowable
    SO2
    lbs/1O6BTU
    6.0
    6.0
    6.0
    6.0
    Calculated
    Partic—
    ulates
    lbs/1O6BTU
    2.0
    2.0
    1.5
    0.78
    Calculated
    SO2
    lbs/1O6BTU
    3.69
    3.69
    3.69
    3.69
    ___________
    4
    Total
    1970
    1,700
    1,777
    3,424
    5,340
    12,241
    1971
    4,565
    977
    4,493
    4,074
    14,109
    1972
    5,730
    1,644
    5,976
    2,604
    15,954
    1973
    3,408
    1,920
    2,196
    4,224
    11,748
    1974
    3,528
    5,798
    0
    192
    9,518
    1st
    5 Mo.
    of 1975
    0
    0
    1,908
    0
    1,908
    The breakdown of the electrical production comparing the steam plant,
    engine plant and interconnection for the past five
    (5) years and five
    (5)
    months
    is
    as
    follows:
    Fiscal
    Source of Power
    (KW-HR)
    Percent of Total
    Tie-
    Engine
    Tie-Line
    Total
    Steam Engine Line
    3,860,450 1,572,750 17,555,726
    22,988,926
    16.8
    40.5
    68.3
    16
    —203

    —4—
    The Agency recommended that the Board deny the variance for several
    reasons.
    First, violations have existed
    since 1970.
    Second, the
    Petitioner has violated the Board Order in PCB 73-355 by failing
    to submit quarterly reports to the Agency.
    Third, Petitioner during
    the period of the variance in PCB 73—355 operated its boilers while
    the diesel generators were not utilized,
    in violation of condition
    two of the Board Order.
    Fourth,
    in contrast to Fairfield’s claims
    in Ex. C of its Petition for Variance,
    no pollution control devices
    exist on boilers
    1,
    2, and 3.
    The cyclone on boiler
    4 was estimated
    by the Agency to have an efficiency of 85;
    not 95
    as claimed by
    the City.
    Fifth, the Petitioner failed to substantiate its claim
    that
    it would take $400,000 to $600,000
    to bring the four boilers
    into compliance with Rule 203 of Chapter Two.
    The Agency was of the opinion that none of the four boilers
    will be able to meet the May 30,
    1975,
    Rule 203 particulate standard.
    All four boilers, assuming similiar coal analysis, will be in com-
    pliance with the May 30,
    1975,
    SO2 standards.
    Boiler No.
    4, based
    on calculations,
    is in compliance with existing Rule 2—2.53
    of the
    Rules and Regulations governing the Control of Air Pollution.
    The
    Agency received no complaints from citizens concerning the grant of
    a variance.
    The hearing was held on February 14,
    1975,
    at the Fairfield
    Council Chambers,
    City Hall,
    Fairfield,
    Illinois.
    The coal—fired
    boilers have been idle since September 1974
    (R.
    14)
    and probably
    will not be needed this wincer.
    A table on page
    6 of the Petition
    for Variance indicated the hours of operation during recent periods
    for the four coal—fired boilers:
    Hours of Operation
    Boiler #1
    Boiler
    #2
    Boiler
    #3
    Boiler #4
    December,
    1973
    228
    516
    U
    0
    January, 1974
    U
    744
    U
    0
    February,
    1974
    U
    672
    U
    0
    March, 1974
    U
    122
    U
    0
    April,
    1974
    0
    U
    U
    0
    May,
    1974
    0
    0
    U
    0
    June,
    1974
    U
    U
    U
    0
    July,
    1974
    U
    U
    564
    0
    August,
    1974
    U
    0
    744
    0
    September,
    1974
    U
    0
    600
    0
    The Petitioner did not refute the Agency’s claim that the coal-fired
    boilers were operated during periods when the diesel generators were
    available.
    Petitioner pointed out that
    it
    takes from eight hours to
    three days to successfully start up the boilers and turbines
    (R.26)
    The steam plant was operated at base load generation levels
    (thirty
    to forty percent of
    full rate)
    to enable it to supply estimated
    consumer needs
    (R.44).
    This problem has now been solved.
    Petitioner
    completed installation of a 125 HP diesel engine in October
    1974 to
    provide sufficient low pressure steam to maintain boiler heat
    (R.23).
    This engine cost $20,000 to $30,000
    (R.24)
    16—204

    —5—
    The City signed an agreement with SIPCO in June 1974
    (Pet.
    Ex.
    2) giving the City 6,825
    1KW of firm purchase power.
    The agree-
    ment allows Fairfield to contract with other electric supplies to
    obtain additional power over its tie-line with SIPCO
    (R.
    19,
    20).
    However, the SIPCO tie—line has a carrying capacity of only 10,000
    X1/~
    (R.
    76,
    Tfl.
    it is doubtful
    that
    this line will have additional
    capacity before
    1980
    (R.
    78).
    Although the City has approximately 14,000
    1KW available
    without using its coal-fired boilers,
    it appears unlikely that
    Petitioner will be able to avoid their use for several years to come.
    First, energy demands in the area are increasing;
    projected estimates
    for peak loads during summer 1975 are 17,000 to 18,000 KW
    CR.
    69).
    During the summer of 1975, Petitioner estimated that it will operate
    its boilers
    300 hours
    CR.
    90,
    91).
    Second, under the June 1974 agree-
    ment with SIPCO, the City must provide electricity to SIPCO
    if any
    SIPCO consumers suffer any discontinuity of electrical service
    (R.~
    ~3, 94).
    Petitioner lacks funds to bring its facilities into com-
    pliance with Chapter Two.
    Additional bonds to finance improvements
    to the City’s facilities cannot be floated before 1976
    (R.
    107).
    Fairfield is making every effort to get all its electrical energy
    from SIPCO, not only to comply with the Act and regulations, but also
    because it is cheaper to buy the power than to have its own coal—
    fired boilers supply it
    (R.
    149).
    Petitioner introduced calculations
    to show the effect of its
    emissions on air quality at ground levels
    CR.
    125,
    128).
    The validity
    of the calculations
    is doubtful because of the assumptions underlying
    the calculations as brought out on cross—examination
    (R.
    133—189).
    Petitioner stated that if a variance ‘~eregranted,
    it ~i1l attempt to
    satisfy all Agency conditions suggested in its February
    4,
    1975,
    Recommendation.
    The City also agreed to undertake
    a study to deter-
    mine the accuracy of the estimated cost figure of $400,000
    to $600,000
    to achieve compliance
    CR.
    52,
    150).
    We
    grant the variance for one year as requested by the
    Petitioner, but subject to the terms recommended by the Agency. Al-
    though a specific compliance plan does not exist, recent good faith
    efforts plus the complexity of the problem convince us that
    a variance
    is warranted.
    Studies will be immediately undertaken to determine the
    feasibility of compliance.
    We believe
    it would impose an unreason-
    able hardship on the City to require it to curtail essential sei~ices
    to local citizenry when the impact of the additional emissions does
    not appear substantial.
    While previous City administrations have
    failed to live up to their responsibilities under the Act, the
    interest of local citizens prompts us to give the Petitioner one
    final opportunity to make good faith efforts
    to control its air
    pollution problem.
    ORDER
    Petitioner, City of Fairfield, is granted a Variance from
    Section
    9(a)
    of the act, Rules 103, 104, and 203(g~l~~of Chapter
    Two,
    and Rule 2-2.53 of the Rules and Regulations Governing the
    Control of Air Pollution from November
    8,
    1974, until November
    7,
    1975,
    subject to the following conditions:
    16— 205

    —6—
    (a)
    Petitioner shall submit
    a detailed cost analysis of a
    control strategy to bring the four boilers
    into compliance with
    Rule 203
    of Chapter Two.
    The study shall include at
    a minimum:
    1.
    Cost of controls;
    2.
    Cost,
    availability, and feasibility of alternate
    sources of power;
    3.
    A timetable for bringing the boilers into compliance;
    4.
    A retirement program for boilers 1-4,
    if necessary.
    This report shalibe submitted to the Agency within 120 days of the
    adoption of this Order.
    This report shall be mailed to:
    Environ-
    mental Protection Agency, Control Program Coordinator, Division of
    Air Pollution Control, 2200 Churchill Road,
    Springfield, Illinois
    62706.
    (b)
    Petitioner shall operate its coal-fired boilers only
    when the following conditions exist:
    1.
    Petitioner’s estimated peak for the day exceeds 10,825
    1KW;
    or
    2.
    Petitioner has obtained all available power from other
    systems through the tie-line with Southern Illinois
    Power Cooperative; or
    3.
    Petitioner is utilizing the tie—line at 6,825 KW and its
    diesel generators at 4,000
    1KW.
    (c)
    Beginning May 1,
    1975, Petitioner shall submit monthly
    reports to the Agency at the address in condition
    (a) above.
    The
    reports
    shall detail:
    1.
    The date of operation of each coal-fired boiler;
    2.
    Kilowatts generated by each boiler on each day of operation;
    3.
    The peak demand on each day of operation of the coal-fired
    boilers;
    4.
    The amount of power provided by the tie-line on each day
    of operation of the coal—fired boilers;
    5.
    The amount of power provided by the diesel units on each
    day of operation of the four coal-fired boilers.
    (d)
    Petitioner shall submit
    a report detailing the City’s
    projected growth between 1976 and 1985 for electricity demand and
    detailing a program to supply the electrical needs of the City dur-
    ing that period.
    This report shall be submitted to the Agency within
    120 days of the adoption of this Order.
    This report shall be mailed
    to the address indicated in condition
    (a)
    above.
    (e)
    Petitioner shall carry out tests to determine the environ-
    mental impact of particulates from the use of the coal—fired boilers
    during the summer months of 1975.
    All tests shall be completed by
    September 1, 1975,
    and submitted to the Agency at the address in-
    dicated in condition
    (a)
    above by October
    1,
    1975.
    IT IS SO ORDERED.
    Mr. Henss dissents.
    16—206

    —7—
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, he~ebycertify that
    he above Opinion and Order was adopted
    on the~j~_~
    day of
    _____________,
    1975,
    by a vote of
    .3
    to
    1.
    ~
    16—207

    Back to top