ILLINOIS POLLUTION CONTROL BOARD
March 13, 1975
NATIONAL CASTINGS DIVISION,
MIDLAND ROSS CORPORATION,
Petitioner,
vs.
)
PCB 74—486
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by Mr. Henss):
Midland
Ross
Corporation requests extension of a variance
previously granted in PCB 73-531 for its National Castings
Division. In PCB 73-531 Petitioner was granted variance from
Rule 203(a (particulates) of the Air Pollution Control Regu-
lations until December 31, 1974 for the purpose of installing
air pollution control equipment. Extension of that variance
is sought until March 15, 1975.
Petitioner operates a 400 tons per week steel foundry in
Meirose Park, Cook County, Illinois. Equipment at this foundry
includes a 20 ton electric arc furnace, two core sand mullers,
four core ovens, four mold sand rnullers, a shakeout operation,
a sand reclaimer, and related sand handling and finishing
equipment. Stack tests indicate that particulate emissions
from the shakeout operation are 54.8 lbs./hr. Under Rule 203(a)
Petitioner is allowed 21 lbs./hr. of particulate emissions. All
other processes at this facility are reported to be adequately
controlled.
In order to bring the shakeout process emissions into
compliance, Petitioner is installing an American Air Filter
Type Roto-clone. Under terms of the prior variance, this control
project was to have been completed by December 31, 1974.
Initially, Petitioner reported that a fan essential to the
operation of the control equipment, which was scheduled for
delivery in late November 1974, would not be delivered until
the end of December 1974. This would have necessitated a
corresponding delay in start-up.
16
—
141
—2—
In the Amended Petition for Variance, a further delay in
delivery of the fan until January 10, 1975 is reported, and
after the filing of the Amended Petition Petitioner advised
that delays in equipment delivery had caused a further delay
in completion of the project until February 17, 1975.
An Agency investigator visited the foundry on January 21,
1975. He found that all major components of the control system
(roto—clone, 200 hp motor and fan, pump for roto-clone and
electrical switch boxes) were on site at the facility. Side
hoods and connecting duct work had not yet been installed.
Petitioner’s Superintendent of Maintenance and Engineering
advised the Agency investigator that installation of duct work which
connects the roto-clone to the fan and installation of the fan~s
exhaust stack would begin on January 22, 1975. Installation of
the side hoods and duct work, which can only be done when the
system is shut down, was scheduled for February 14, 1975. In-
stallation of a final side hood was to be completed over a weekend
shutdown. Total system start-up was to be February 17, 1975.
The Agency recommends approval of this short variance
extension. It is the opinion of the EPA that Petitioner has
acted with reasonable diligence within the prior variance time
period. The Board is aware of numerous delays in equipment
delivery now being experienced by companies seeking to achieve
compliance. The delays were beyond the control of Petitioner and
the variance will be granted.
This Opinion constitutes the findings of fact and conclusions
of law of the Illinois Pollution Control Board.
ORDER
It is the Order of the Pollution Control Board that Midland
Ross Corporation is granted variance from Rule 203(a) of the Air
Pollution Control Regulations for its National Castings Division
foundry at Melrose Park, Illinois until March 15, 1975 for the
purpose of installing and testing air pollution control equipment
designed to achieve compliance with Rule 203(a). This variance
is subject to the following conditions:
1. Petitioner shall apply for and obtain all
necessary permits for the installation and
operation of pollution control equipment.
2. Petitioner shall execute an extension of
the performance bond required pursuant to
the Board Order in PCB 73-531. The bond
shall be in a form acceptable to the
Environmental Protection Agency and shall
1f~
—
1A~
—3—
assure installation and operation of the
control equipment within the term of the
variance. The bond shall be mailed to:
Fiscal Services Division, Illinois EPA,
2200 Churchill Road, Springfield, Illinois
62706.
3. Within 30 days after completion of the air
pollution control program, Petitioner shall
have performed a stack test. Results of the
stack test shall be submitted to the Environ-
mental Protection Agency as soon as they are
available to Petitioner. Petitioner shall
notify the Agency five days prior to the stack
test indicating the time and place of said test
and shall allow Agency personnel to observe
said test if they so desire.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
jfI’L
day of
________,
1975 by a vote of g to
0
16
—
143