ILLINOIS POLLUTION CONTROL BOARD
    March
    6,
    1975
    WOODRUFF AND EDWARDS, INC.,
    Petitioner,
    v.
    )
    PCB 74—444
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Dr. Odell)
    On November 25,
    1974, Woodruff and Edwards,
    Inc. filed
    its Petition for Variance with the Pollution Control Board
    (Board).
    The Petitioner sought a variance from the carbon
    monoxide limitations in Rule
    206(e)
    of the Air Pollution
    Regulations
    (Chapter Two)
    from December
    1,
    1974,
    until July 15,
    1975.
    Rule 206(e) requires that no cupola with a manu-
    facturer’s rated melt rate in excess of 5 tons/hour emit more
    than 200 ppm CO corrected to 50
    excess air.
    In Woodruff and
    Edwards,
    Inc.
    v. Environmental Protection Agency PCB 74-112,
    13 PCB 247
    (August
    1,
    1974), the Board granted this Petitioner
    a Variance from December
    2,
    1973,
    until December 1,
    1974,
    to
    enable it to operate its cupola while installing control equip-
    ment to comply with Rule
    206(e)
    of Chapter Two.
    The Board
    made the grant of that Variance subject to certain conditions,
    including:
    “2.
    Petitioner shall submit monthly progress reports
    to the Environmental Protection Agency.
    “3.
    Within thirty days after completion of the ex-
    perimental modification Petitioner shall per-
    form a stack test.
    Results of the stack test
    shall be submitted to the Environmental Pro-
    tection Agency.
    “4.
    If the stack test does not show compliance
    with
    Rule 206 (e), Woodruff and Edwards
    Company shall proceed to install an after-
    burner for control of carbon monoxide
    emissions.
    Appropriate permit procedures
    shall be followed.”
    In its Interim Order of December 5,
    1974,
    the Board
    requested that Woodruff and Edwards agree to include the
    record of PCB 74-112 into this cause.
    Petitioner’s consent
    was received by the Board on December 16, 1974,
    the date from
    which the 90-day decision period began to run.
    16—31

    —2—
    Petitioner operates a grey and ductile iron foundry
    containing one cupola with
    a process rate weight of 12 tons/
    hour.
    The facility is located along the west bank of the
    Fox River in Elgin, Illinois.
    There are other commercial
    operations north and south of the plant.
    The central down-
    town shopping area is immediately across the Fox River to the
    east.
    On Petitioner’s west, across railroad tracks and a
    highway,
    is
    a residential area.
    Tests performed by EEC of Moline, Illinois on October
    5,
    1973,
    showed Petitioner’s cupola to be emitting at the
    charge door an average of 219,823 ppm CO corrected to 50
    excess
    air.
    The concentration at the stack was 65,615 ppm.
    Additional calculations were made by Petitioner
    to show the
    impact of these emissions on nearby areas.
    The calculations
    indicate that Petitioner’s CO emissions increase the ground
    level concentrations of CO by 1.2 ppm.
    To carry out the Board’s Order of August 1,
    1974,
    Woodruff and Edwards decided to use the top portion of the
    cupola stack as a combustion chamber to convert the CO to
    CO2.
    The cooling nozzles were removed from the upper cupola.
    This permitted the hot exhaust gases to ignite when they mixed
    with the excess air entering through the charge door located
    on the side of the cupola.
    This method was intended to con-
    serve energy by eliminating the need for an afterburner.
    Petitioner alleged that the test results
    sent to the Environ-
    mental Protection Agency
    (Agency)
    establish that CO emissions
    were controlled well within permissible limits during much of
    the variance term granted in PCB 74-112.
    The Agency in its
    Recommendation did not dispute this conclusion of the Petitioner.
    Woodruff and Edwards alleged, however, that since November
    7,
    1974,
    the system has been experiencing difficulty with com-
    bustion in the cupola.
    The reasons for the problems were that:
    “(a)
    There
    is
    a shortage of coke,
    so that we have
    been unable to obtain a consistent quality or size
    of coke from our suppliers.
    As a consequence, we
    have been forced in recent weeks to use coke of a
    different size than we would normally accept.
    With
    the smaller size coke,
    there
    is substantially more
    compaction of the melt, which reduces the amount of
    air we are able to pull through the melt.
    With the
    reduced air flow, we have greater difficulty con-
    trolling the operating temperatures, resulting in
    occasional reductions of the temperatures below
    what we require.
    This not only creates tremendous
    operating problems, but from time to time can
    result in incomplete combustion of carbon monoxide
    at the top of the cupola.
    16—32

    —3—
    “(b)
    At the same time we have been having problems
    with our coke, we have also been experiencing
    difficulties with the new fan we installed at the
    end of the bag house last spring.
    Because the new
    fan has not been producing the capacity the seller
    promised
    (30,000 cfm),
    it could not overcome the
    shortage of air resulting from the compaction of
    the coke.
    To meet the problem, we have temporarily
    re-installed an old fan, until
    a second new fan can
    be installed to deliver the capacity we require.
    Until a new fan is installed, we expect to continue
    to have occasional failures in the burnover process,
    resulting in some emission of carbon monoxide.”
    A seven and one-half month variance was sought to enable
    Petitioner to install
    a new fan and conduct tests.
    The
    Petitioner did not indicate whether the new fan has been
    ordered, but based on its allegation that delivery takes
    26
    weeks from the time of order,
    it would seem that Petitioner
    has ordered the equipment.
    The Agency filed its Recommendation on February
    4,
    1975.
    The Agency recommended that the variance be granted, subject
    to certain conditions.
    The Agency noted that coke of the
    desired size should be more plentiful now that the coal strike
    is over.
    It considered the July date for completion reason-
    able and stated that Petitioner should be allowed to continue
    its proposed system, because
    a successful system will control
    CO and conserve energy.
    It was not stated whether any citizens
    were opposed to the grant of this variance.
    Several potential
    problems with Petitioner’s proposed system were noted:
    1110.
    The Agency does not know whether Petitioner’s
    proposed system will work.
    That determination must await the
    stack test which should be made after the new equipment is
    installed and adjusted.
    Petitioner’s previous experiments
    were performed on production equipment which
    is no longer in
    use,
    so the earlier test information
    is out of date.
    .
    “11.
    The Agency believes that Petitioner also has a
    problem with fugitive emissions from the charge door of its
    cupola.
    On December
    4,
    1974,
    an Agency investigator observed
    emission levels from the charge door of the cupola
    .
    .
    .
    in
    possible violation of Rule 203(f)(l).
    This problem may be
    solved when Petitioner restricts
    the area of the charge door
    which
    is opened to the atmosphere.
    This is part of Petitioner’s
    control program,
    so both the carbon monoxide and particulate
    problems may be solved at the same time.
    “13.
    There
    is
    a potential problem with the safety valve
    cap on the top of the cupola.
    .
    .
    .
    This cap on top of the
    furnace will open if insufficient cooling occurs as the gases
    pass from the cupola through the quench system into the bag
    house.
    When the cap is open,
    particulates escape to the ambient
    air, rather than being captured in the bag house. There
    is the
    danger that the high temperatures needed to incinerate carbon
    16
    33

    —4—
    monoxide will make the existing particulate control system
    ineffective.
    After the carbon monoxide control system is
    completed,
    stack tests should be performed for both carbon
    monoxide and particulate emissions.”
    We agree with the Agency that although problems exist,
    Petitioner should be given the opportunity to install its
    proposed control system.
    Petitioner has made good faith
    efforts
    in the past to achieve compliance.
    Also, we encourage
    methods of compliance which involve energy conservation.
    Based
    on the facts in this case,
    it would be an unreasonable hard-
    ship to deny Petitioner’s request here.
    This Opinion constitutes the findings of fact and con-
    clusions of law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that
    P’~titionerbe granted
    a Variance from the carbon monoxide
    limitations of Rule 206(e)
    of Chapter Two from December 1,
    1974,
    until July 15,
    1975, subject to the following conditions:
    (a)
    By March
    15,
    1974, Petitioner shall submit proof
    to the Agency at its office listed in
    (b) below of having
    ordered the fan needed for its compliance program.
    (b)
    Petitioner shall continue to send written reports
    to the Agency on or before the tenth of each month beginning
    April
    10,
    1975, detailing all progress made toward compliance
    during the reporting period.
    The reports
    shall include any
    purchase orders and notices of delays.
    The reports shall
    also state how much time the cap on top of the furnace
    is
    open during the reporting period.
    Reports shall be sent to:
    Environmental Protection Agency, Control Program Coordinator,
    2200 Churchill Road, Springfield, Illinois 62706.
    (C)
    Petitioner shall apply to the Agency for all
    necessary construction permits.
    (d)
    Within twenty-eight
    (28)
    days of the adoption of
    this Order, Petitioner shall execute
    a performance bond in
    the amount of $10,000 and in a form acceptable to the Agency.
    The purpose of said bond
    is to assure timely compliance.
    Said bond shall be sent to:
    Environmental Protection Agency,
    Fiscal Services,
    2200 Churchill Road, Springfield, Illinois
    62706.
    (e)
    ~‘7ithinthirty-five
    (35)
    days after completion of
    the modifications, Petitioner shall perform a stack test for
    carbon monoxide and particulates.
    Within seven
    (7)
    days after
    they are available to Petitioner, results of the stack test
    shall be submitted to:
    Environmental Protection Agency,
    Control Program Coordinator,
    2200 Churchill Road, Springfield,
    Illinois 62706.
    Petitioner shall provide written notification to
    16—34

    —5—
    the Agency seven
    (7) days prior to the stack test, indicat-
    ing the time and place of said test and shall allow Agency
    personnel to observe said test if they so desire.
    Notifica-
    tion of the test shall be submitted to: Environmental Pro-
    tection Agency, Illinois Naval Armory, East Randolph and the
    Lake,
    Chicago, Illinois 60601.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify that the ab ye Opinion and Order was
    adopted on the
    (~‘
    day of
    ______________,
    1975, by a vote of
    L~ to~
    q~ta~L.’ett
    16~35

    Back to top