ILLINOIS POLLUTION CONTROL BOARD
March
6,
1975
WOODRUFF AND EDWARDS, INC.,
Petitioner,
v.
)
PCB 74—444
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION
AND
ORDER OF THE BOARD
(by Dr. Odell)
On November 25,
1974, Woodruff and Edwards,
Inc. filed
its Petition for Variance with the Pollution Control Board
(Board).
The Petitioner sought a variance from the carbon
monoxide limitations in Rule
206(e)
of the Air Pollution
Regulations
(Chapter Two)
from December
1,
1974,
until July 15,
1975.
Rule 206(e) requires that no cupola with a manu-
facturer’s rated melt rate in excess of 5 tons/hour emit more
than 200 ppm CO corrected to 50
excess air.
In Woodruff and
Edwards,
Inc.
v. Environmental Protection Agency PCB 74-112,
13 PCB 247
(August
1,
1974), the Board granted this Petitioner
a Variance from December
2,
1973,
until December 1,
1974,
to
enable it to operate its cupola while installing control equip-
ment to comply with Rule
206(e)
of Chapter Two.
The Board
made the grant of that Variance subject to certain conditions,
including:
“2.
Petitioner shall submit monthly progress reports
to the Environmental Protection Agency.
“3.
Within thirty days after completion of the ex-
perimental modification Petitioner shall per-
form a stack test.
Results of the stack test
shall be submitted to the Environmental Pro-
tection Agency.
“4.
If the stack test does not show compliance
with
Rule 206 (e), Woodruff and Edwards
Company shall proceed to install an after-
burner for control of carbon monoxide
emissions.
Appropriate permit procedures
shall be followed.”
In its Interim Order of December 5,
1974,
the Board
requested that Woodruff and Edwards agree to include the
record of PCB 74-112 into this cause.
Petitioner’s consent
was received by the Board on December 16, 1974,
the date from
which the 90-day decision period began to run.
16—31
—2—
Petitioner operates a grey and ductile iron foundry
containing one cupola with
a process rate weight of 12 tons/
hour.
The facility is located along the west bank of the
Fox River in Elgin, Illinois.
There are other commercial
operations north and south of the plant.
The central down-
town shopping area is immediately across the Fox River to the
east.
On Petitioner’s west, across railroad tracks and a
highway,
is
a residential area.
Tests performed by EEC of Moline, Illinois on October
5,
1973,
showed Petitioner’s cupola to be emitting at the
charge door an average of 219,823 ppm CO corrected to 50
excess
air.
The concentration at the stack was 65,615 ppm.
Additional calculations were made by Petitioner
to show the
impact of these emissions on nearby areas.
The calculations
indicate that Petitioner’s CO emissions increase the ground
level concentrations of CO by 1.2 ppm.
To carry out the Board’s Order of August 1,
1974,
Woodruff and Edwards decided to use the top portion of the
cupola stack as a combustion chamber to convert the CO to
CO2.
The cooling nozzles were removed from the upper cupola.
This permitted the hot exhaust gases to ignite when they mixed
with the excess air entering through the charge door located
on the side of the cupola.
This method was intended to con-
serve energy by eliminating the need for an afterburner.
Petitioner alleged that the test results
sent to the Environ-
mental Protection Agency
(Agency)
establish that CO emissions
were controlled well within permissible limits during much of
the variance term granted in PCB 74-112.
The Agency in its
Recommendation did not dispute this conclusion of the Petitioner.
Woodruff and Edwards alleged, however, that since November
7,
1974,
the system has been experiencing difficulty with com-
bustion in the cupola.
The reasons for the problems were that:
“(a)
There
is
a shortage of coke,
so that we have
been unable to obtain a consistent quality or size
of coke from our suppliers.
As a consequence, we
have been forced in recent weeks to use coke of a
different size than we would normally accept.
With
the smaller size coke,
there
is substantially more
compaction of the melt, which reduces the amount of
air we are able to pull through the melt.
With the
reduced air flow, we have greater difficulty con-
trolling the operating temperatures, resulting in
occasional reductions of the temperatures below
what we require.
This not only creates tremendous
operating problems, but from time to time can
result in incomplete combustion of carbon monoxide
at the top of the cupola.
16—32
—3—
“(b)
At the same time we have been having problems
with our coke, we have also been experiencing
difficulties with the new fan we installed at the
end of the bag house last spring.
Because the new
fan has not been producing the capacity the seller
promised
(30,000 cfm),
it could not overcome the
shortage of air resulting from the compaction of
the coke.
To meet the problem, we have temporarily
re-installed an old fan, until
a second new fan can
be installed to deliver the capacity we require.
Until a new fan is installed, we expect to continue
to have occasional failures in the burnover process,
resulting in some emission of carbon monoxide.”
A seven and one-half month variance was sought to enable
Petitioner to install
a new fan and conduct tests.
The
Petitioner did not indicate whether the new fan has been
ordered, but based on its allegation that delivery takes
26
weeks from the time of order,
it would seem that Petitioner
has ordered the equipment.
The Agency filed its Recommendation on February
4,
1975.
The Agency recommended that the variance be granted, subject
to certain conditions.
The Agency noted that coke of the
desired size should be more plentiful now that the coal strike
is over.
It considered the July date for completion reason-
able and stated that Petitioner should be allowed to continue
its proposed system, because
a successful system will control
CO and conserve energy.
It was not stated whether any citizens
were opposed to the grant of this variance.
Several potential
problems with Petitioner’s proposed system were noted:
1110.
The Agency does not know whether Petitioner’s
proposed system will work.
That determination must await the
stack test which should be made after the new equipment is
installed and adjusted.
Petitioner’s previous experiments
were performed on production equipment which
is no longer in
use,
so the earlier test information
is out of date.
.
“11.
The Agency believes that Petitioner also has a
problem with fugitive emissions from the charge door of its
cupola.
On December
4,
1974,
an Agency investigator observed
emission levels from the charge door of the cupola
.
.
.
in
possible violation of Rule 203(f)(l).
This problem may be
solved when Petitioner restricts
the area of the charge door
which
is opened to the atmosphere.
This is part of Petitioner’s
control program,
so both the carbon monoxide and particulate
problems may be solved at the same time.
“13.
There
is
a potential problem with the safety valve
cap on the top of the cupola.
.
.
.
This cap on top of the
furnace will open if insufficient cooling occurs as the gases
pass from the cupola through the quench system into the bag
house.
When the cap is open,
particulates escape to the ambient
air, rather than being captured in the bag house. There
is the
danger that the high temperatures needed to incinerate carbon
16
—
33
—4—
monoxide will make the existing particulate control system
ineffective.
After the carbon monoxide control system is
completed,
stack tests should be performed for both carbon
monoxide and particulate emissions.”
We agree with the Agency that although problems exist,
Petitioner should be given the opportunity to install its
proposed control system.
Petitioner has made good faith
efforts
in the past to achieve compliance.
Also, we encourage
methods of compliance which involve energy conservation.
Based
on the facts in this case,
it would be an unreasonable hard-
ship to deny Petitioner’s request here.
This Opinion constitutes the findings of fact and con-
clusions of law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that
P’~titionerbe granted
a Variance from the carbon monoxide
limitations of Rule 206(e)
of Chapter Two from December 1,
1974,
until July 15,
1975, subject to the following conditions:
(a)
By March
15,
1974, Petitioner shall submit proof
to the Agency at its office listed in
(b) below of having
ordered the fan needed for its compliance program.
(b)
Petitioner shall continue to send written reports
to the Agency on or before the tenth of each month beginning
April
10,
1975, detailing all progress made toward compliance
during the reporting period.
The reports
shall include any
purchase orders and notices of delays.
The reports shall
also state how much time the cap on top of the furnace
is
open during the reporting period.
Reports shall be sent to:
Environmental Protection Agency, Control Program Coordinator,
2200 Churchill Road, Springfield, Illinois 62706.
(C)
Petitioner shall apply to the Agency for all
necessary construction permits.
(d)
Within twenty-eight
(28)
days of the adoption of
this Order, Petitioner shall execute
a performance bond in
the amount of $10,000 and in a form acceptable to the Agency.
The purpose of said bond
is to assure timely compliance.
Said bond shall be sent to:
Environmental Protection Agency,
Fiscal Services,
2200 Churchill Road, Springfield, Illinois
62706.
(e)
~‘7ithinthirty-five
(35)
days after completion of
the modifications, Petitioner shall perform a stack test for
carbon monoxide and particulates.
Within seven
(7)
days after
they are available to Petitioner, results of the stack test
shall be submitted to:
Environmental Protection Agency,
Control Program Coordinator,
2200 Churchill Road, Springfield,
Illinois 62706.
Petitioner shall provide written notification to
16—34
—5—
the Agency seven
(7) days prior to the stack test, indicat-
ing the time and place of said test and shall allow Agency
personnel to observe said test if they so desire.
Notifica-
tion of the test shall be submitted to: Environmental Pro-
tection Agency, Illinois Naval Armory, East Randolph and the
Lake,
Chicago, Illinois 60601.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify that the ab ye Opinion and Order was
adopted on the
(~‘
day of
______________,
1975, by a vote of
L~ to~
q~ta~L.’ett
16~35