    INTERIM ORDER OF THE BOARD (by Mr. Goodman)
    This matter
    comes
    before the Pollution
    Control Board
    (Board) upon petition of Midwest
    Metals, Inc., for variance
    from Rules 103(a) and 103(b) of the
    Air Pollution Control
    Regulations.
    The petition is inadequate in that it fails to include
    information pertaining to the criteria required by Train
    V.
    NRDC, Inc., 43 USLW 4467 (Supreme Court No, 73-1742,
    April 16, 1975). Petitioner must show: 1) Whether the
    ambient air quality of the area affected by the variance
    meets the national ambient air quality standards; 2) If
    the ambient air quality does not meet those standards,
    whether the granting of the variance would contribute to the
    areats failure to meet said standards; and
    3)
    If the ambient
    air quality does meet said standards, whether the variance
    would cause the ambient air quality to fail to meet said
    standards.
    It is the Order of the Board that Petitioner
    shall
    amend its petition within 45 days of this Order to provide
    the above described information. Failure to timely file
    the
    amended petition shall cause the petition to be dismissed
    for inadequacy without prejudice. The 90-day decision
    period set by Statute shall run from the date of filing
    the
    amended petition.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of
    the Illinois Pollution
    Control Board, hereb certify the above Order wa~adopted
    on
    the
    ~Q~’
    day of_________ 1975 by a vote of ~
    0
    Christan L. Mof ett, r