ILLINOIS POLLUTION CONTROL BOARD
    January
    14,
    1976
    ENVIRONMENTAL PROTFCTION AGENCY,
    )
    Complainant,
    V.
    )
    PCB 75—382
    CENTRAL ILLINOIS PUBLIC SERVICE
    COMPANY,
    Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Mr. Goodman):
    On October
    2,
    1975, the Environmental Protection Agency
    (Agency)
    filed a complaint against Respondent Central Illinois Public Service
    Company (CIPS).
    The complaint alleged that CIPS violated conditions
    of a construction permit issued by the Agency and §9(b)
    of the
    Environmental Protection Act
    (Act)
    by causing or allowing construct-
    ion work to be done toward erection of a coal-fired boiler whose
    emissions will violate Rule 204 (a) (1)
    of the Air Pollution Regulations
    (Chapter
    2)
    and by choosing a design option which would not result
    in “full compliance” with Chapter 2.
    The complaint further alleged
    that CIPS was erroneously issued a construction permit,
    in violation
    of Rule
    10.3(a) (5) (A)
    of Chapter
    2.
    A hearing was held on December
    11,
    1975,
    in the Jasper County
    Courthouse, Newton,
    Illinois.
    At the hearing a Settlement Proposal
    representing the final agreement of the parties was entered into
    evidence.
    No additional evidence was presented, and no citizen
    witnesses testified.
    On June
    6,
    1973,
    the Agency issued CIPS,
    an Illinois public
    utility corporation,
    a construction permit for one 575 MW pulverized
    coal—fired boiler to be installed at a new electric power generating
    facility located near Newton, Jasper County,
    Illinois
    (Exhibit No.
    1).
    19
    885

    —2—
    The installation of this new 575 MW boiler at the proposed Newton
    generating facility subjects CIPS to achieving compliance with Rule
    204(a) (1)
    of the Air Pollution Control Regulations
    (Chapter 2).
    Rule
    204(a) (1)
    requires CIPS to reduce sulfur dioxide emissions upon start-
    up of said boiler to 1.2 lbs/million BTU.
    CIPS in its construction
    permit application
    (Exhibit
    2)
    for construction of said boiler stated
    that there were design options available
    to CIPS which would enable
    CIPS to be in full compliance with Chapter
    2.
    Condition
    8
    of. the aforesaid construction permit provides,
    in
    pertinent part:
    The equipment shall not be constructed in such
    a
    manner that operation or disposal of air contarni—
    nants will cause a violation of the Environmental
    Protection Act or of applicable regulations.
    Condition
    3 of said permit states:
    There shall be no deviation from the approved plans
    and specifications unless additional or revised plans
    are submitted to the Environmental Protection Agency
    and
    a supplemental written permit issued.
    On October 11,
    1974,
    CIPS applied for
    a construction permit
    for particulate control equipment for the Newton generating station.
    Although the application indicated that emissions of sulfur dioxide
    from the combustion of coal in the new boiler when operated would
    exceed the 1.2 lbs/million BTU sulfur dioxide limitation contained in
    Rule 204(a) (1), the application did not contain any provision for
    sulfur dioxide removal equipment.
    On November 19,
    1974, the Agency
    rejected the permit application due to the lack of
    specifications
    for
    a sulfur dioxide removal system.
    On April
    9,
    1975, CIPS entered into an agreement with Chemical
    Air Pollution Control Company
    (Chemico)
    which provided that Chemico
    would proceed with engineering plans for a sulfur dioxide removal
    system for CIPS~ Unit No.
    1 involving the use of a wet l±nescrubber.
    The contract was limited to a three month period, with the cost not
    to exceed $225,000.
    On or about August 25,
    1975,
    CIPS submitted a proposal
    (No. Al84)
    to the U.S. Environmental Protection Agency for demonstration of
    a
    double alkali flue gas desulfurization system, designed by Envirotech
    Corp., on its Newton power plant,
    Unit No.
    1.
    This proposal was
    based upon the treatment of all of the flue gas from the unit
    (based
    19
    686

    —3—
    upon the unit being rated at
    575MW
    )
    and would allow for the design
    of the system which would comply with Rule 204(a) (1)
    upon start-up
    of said Unit No.
    1.
    CIPS also submitted an alternative double alkali
    sulfur dioxide removal proposal designed to treat approximately 25
    of the flue gas.
    In the proposal submitted to the U.S. Environmental
    Protection Agency, Environtech Corp.
    states that the mechanical comple-
    tion of the double alkali sulfur dioxide removal system is scheduled
    for October
    1,
    1977,
    and commercial,
    operation of the system by
    December 1,
    1977.
    Unit No.
    1 at the Newton generating station is
    scheduled to begin commercial operation on December 1,
    1977.
    In the Settlement Proposal, the parties agree
    to the following
    terms:
    1.
    Respondent CIPS agrees to install
    a system which will
    control sulfur dioxide emissions in accordance with all applicable
    air pollution Regulations and the Environmental Protection Act.
    It
    is the present intention of CIPS
    to install either
    a. lime scrubbing
    system or a double alkali scrubbing system.
    Respondent agrees that
    whatever system is selected it will have a complete SO2 removal
    system installed and fully operational by the time Unit
    1 at Newton
    begins service.
    Respondent agrees that said system will treat the
    flue gas to meet the 1.2 lbs/l06 BTU sulfur dioxide standard.
    2.
    Complainant states that CIPS has been cooperative and has
    dealt with the Agency
    in good faith.
    Therefore, the parties request
    that no penalty be assessed
    in this case.
    3.
    Respondent shall construct and install a SO2 removal system
    designed to meet all applicable Air Pollution Control Regulations
    and the Illinois Environmental Protection Act at its Newton Unit No.
    1
    electric generating plant according to the following schedule:
    A.
    Respondent shall select a vendor for
    a sulfur
    dioxide removal system, designed to meet the
    1.2 lbs/l06 BTU sulfur dioxide limitation of
    Rule 204(a)
    (1) upon start-up of Newton Unit No.
    1, within thirty days of a decision by the
    Federal EPA on proposal No. A184 or
    in no event
    later than February
    1,
    1976.
    B.
    Beginning December
    1,
    1975 and continuing quarterly
    thereafter Respondent shall submit within 20 calendar
    days of the end of each period, progress reports to:
    Environmental Protection Agency
    Division of Air Pollution Control
    Control Program Coordinator
    2200 Churchill Road
    Springfield, Illinois
    62706
    Said progress reports shall include but not be limited
    to progress made on the installation of the flue gas
    desulfurization device during the preceeding quarter
    19
    687

    —4—
    and an estimate of the work to be completed during the
    following quarter.
    Said report shall include an assess-
    ment of the schedule for installation of said scrubbing
    system and
    a certification by Respondent that said
    schedule will enable said system to be operational
    by the date Newton Unit
    1
    is scheduled to begin
    service.
    Said progress reports shall include as
    exhibits all schedules developed for installation
    of said system.
    In the event the Environmental
    Protection Agency deems any report insufficient, CIPS
    agrees to furnish any additional information reasonably
    responsive to the intent of this paragraph.
    C.
    Respondent shall apply for a construction permit pursuant
    to Rule 103(a)
    of the Pollution Control Board’s Air
    Pollution Control Regulations within thirty days from the
    date of a decision by the Federal EPA on Proposal No. Al84
    or in no event later than February
    1,
    1976.
    Information in
    said permit application shall include specifications for
    a flue gas desulfurization system to meet the 1.2 lbs/l06
    BTU sulfur dioxide standard in Rule 204(a) (1)
    upon the
    start-up of Newton Unit No.
    1 and said system shall be
    designed to treat the flue gas upon the start-up of Newton
    No.
    1.
    The Board finds that CIPS has violated Condition
    8 of the con-
    struction permit and Section
    9(b)
    of the Act by causing or allowing
    construction work to be done toward erection of
    a coal-fired boiler
    whose emissions will violate Rule 204(a) (1)
    of Chapter
    2.
    CIPS has
    violated Condition
    3 of the permit and Section 9(b)
    of the Act by
    deviating from the approved plan by choosing a design option which
    would not result in “full compliance” with Chapter
    2.
    Finally,
    Respondent was erroneously
    issued said construction permit in viola-
    tion of Rule 103 (a) (5)
    of Chapter
    2 in that Respondent did not submit
    adequate proof to.the Agency that the emission source or air pollution
    control equipment would be constructed so as not to cause a violation
    of the Act or Chapter
    2 by the plant’s on line date.
    However, due to
    CIPS’
    good faith efforts to comply and lack of any injury to the public,
    the Board accepts the stipulation of no penalty.
    The Board finds
    the Settlement Proposal to be an adequate plan of compliance and
    orders the parties to adhere to its terms.
    This Opinion constitutes the findings of fact and conclusions
    of law in this matter.
    ORDER
    It is the Order of the Pollution Control Board that:
    1.
    Respondent Central Illinois Public Service Company is found
    19
    688

    —5—
    to have violated Section 9(b) of the Act, Rule 103(a) (5)
    of Chapter
    2
    and Conditions
    3 and
    8 of the construction permit issued by the Agency
    for construction of a coal-fired boiler at its Newton Power Plant.
    2.
    Respondent is Ordered to cease and desist from violating
    S9(b)
    of the Act, Rule 103(a) (5)
    of Chapter
    2, and Conditions
    3 and
    8 of said construction permit.
    3.
    Respondent shall comply with the terms of the Settlement
    Proposal submitted by the parties on December 11,
    1975 which is hereby
    incorporated by reference as if fully set forth herein.
    IT IS SO ORDERED.
    I, Christan L.
    Moffett,, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order were adopted on the
    _______________day of
    ,
    1976 by a vote of
    d/..p
    ~&~tanL.
    ~
    Illinois Pollution C
    rol Board
    19
    689

    Back to top