ILLINOIS POLLUTION CONTROL BOARD
    January 14,
    1976
    AMERICAN NATIONAL BANK
    &
    ALVIN
    W.
    DEJONG,
    Petitioners,
    v.
    )
    PCB 75—75
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Alvin W.
    DeJong, Attorney,
    appeared for the Petitioners;
    John
    T.
    Bernbom, Attorney, appeared for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by
    1’lr.
    Zeitlin):
    Petitioners American National Bank,
    as trustee under Trust
    No.
    23251,
    and Alvin
    W.
    DeJong,
    individually, originally filed a
    Petition for Variance on September
    9,
    1974,
    in case No. PCB 74-334,
    seeking relief from Environmental Protection Agency
    (Agency) actions
    denying the Wheaton Sanitary District
    (Wheaton) permission
    to issue
    certain permits
    to Petitioners.
    On September 12,
    1974, this Board
    found
    that Petition inadequate and ordered an Amended Petition be
    filed.
    Subsequent
    to the filing of an Z’~mendedPetition on
    October
    16,
    1974,
    the Board again found information lacking and on
    October 24,
    1974,
    again ordered that farther additional
    information
    be submitted.
    The Agency’s Recommendation in PCB 74—334 was filed
    on December
    2,
    1974.
    On January 16,
    1975,
    the Board dismissed
    PCB 74—334.
    Petitioners’ Motion to Reinstate PCB 74—334,
    filed February
    5,
    1975,
    was granted in a Board Order dated February 14,
    1975,
    to the extent
    that the Board took the Motion and the earlier Petition and Amended
    Petition as the instant case,
    and renumbered
    it
    PC13 75-75.
    The
    Agency’s Recommendation in this case was filed on March
    13,
    1975.
    A hearing was held on August
    13,
    1975,
    at which no testimony was
    taken, although the parties submitted
    a Stipulation of Fact.
    After denying Petitioners’ Motion for Oral Argument
    in an Interim
    Order dated September
    18,
    1975,
    the Board on September 29, 1975,
    entered a further Interim Order remanding the matter for an additional
    hearing and the submission of evidence on specified issues.
    The
    required hearing was held November
    12,
    1975, at which time considerable
    new testimony and evidence was received.
    19—641

    —2—
    Although none of the pleadings submitted by Petitioners so
    state,
    it is plain that the relief sought here is
    variance from
    Rule 962 of the Water Pollution Regulations,
    which prohibits the
    Agency
    from
    issuing permits for the construction or operation of
    wastewuter sources
    or sewers where such source or sewer would cause
    or contribute
    to violation of the Act or other portions of the Water
    Pollution Regulations.
    PCB Regs.,
    Ch.
    3: Water Pollution.
    Petitioner
    seeks to construct and operate a Denny’s Restaurant,
    which will result
    in
    a load upon the Wheaton Sanitary District sewage treatment plant
    (STP)
    of approximately
    80 population equivalents
    (PE).
    The Agency has
    had the Wheaton STP on critical review since
    1972,
    based on its findings
    that the Plant could not meet applicable effluent limitations.
    Petitioners based their case for Variance on four major points:
    1.
    The proposed restaurant will have a very
    slight impact on the STP effluent,
    if any;
    the very
    low PE load generated will
    in fact be reduced by the
    installation of a grease trap or,
    if necessary, holding
    tanks.
    2.
    The Wheaton STP
    is a
    “borderline” case and
    usually approaches the applicable effluent limitations,
    when the limitations are not in fact met.
    3.
    The Wheaton STP has now been approved and
    funded for major expansion.
    Constructior~onmajor
    expansion which will provide more than sufficient
    capacity is expected
    to start in January,
    1976, with
    completion scheduled within 600 days thereafter.
    It
    is also expected that ongoing construction will provide
    significant additional capacity at the STP within 400
    days,
    or by early
    1977.
    Petitioners’
    restaurant project
    will not be completed before fall of 1976,
    if the
    requested variance is granted
    (R.68).
    4.
    As
    a result of representations made by an
    employee
    of the Respondent Agency,
    it
    is estopped from
    denying Petitioner
    a permit for construction and
    operation of its restaurant
    as a wastewater source.
    SpecificaLLy~ as
    a result of statements made by an
    Agency Official to Petitioner DeJong in the Chicago
    office of the Agency,
    to the effect that the Wheaton
    STP would
    imminently be granted 5,000 additional PE
    in permit issuing authority,
    which statements Petitioners
    relied on, Petitioner DeJong expended in excess of $29,000
    on improvements to the site of the proposed restaurant,
    including grading and installation of a sewer connection.
    19—642

    —3—
    Petitioners have shown considerable hardship which may result
    if the Variance is not granted, and have adequately borne their
    burden of showing that the environmental harm likely to result from
    the grant of the Variance is in comparison very small.
    While we agree with the Agency that Petitioners’
    claim that the
    restaurant should be allowed
    in this instance because its discharge
    will have no measurable effect on the STP effluent
    is not sufficient
    to allow the grant, we also agree with the Petitioners that the
    restaurant’s
    impact will be slight.
    Petitioners’ claim of
    “no
    measurable effect”
    is fallacious.
    As the Board has held in analagous
    cases,
    if the STP
    is violating effluent standards, any additional
    load
    will contribute
    to such violation.
    See,
    e.g., Cohn~T EPA, PCB 75-102,
    17 PCB 321
    (1975), and cases cited. ~
    ~h Tho~
    asaso
    held that
    where the additional load
    is small,
    and the period of time short, a
    sufficient showing of hardship will allow the grant of a Variance from
    a “Sewer Ban.”
    See, e.g.,
    Nixon v.
    EPA,
    PCB 75-354
    (October,
    1975);
    Hawthorne Lodge
    V.
    ~
    16,
    1975); Macoupin v.
    EPA,
    P~B75—273
    (Oct.
    9,
    1975)
    The Agency witness at the second hearing agreed with Petitioners’
    contention
    that the Wheaton STP
    is a “borderline” case, and that
    it
    usually meets or exceeds the applicable standards for its effluent,
    (R.73).
    The Agency also agreed that the quality of effluent from the
    Wheaton STP often exceeds the water quality
    in the receiving
    stream
    upstream of the discharge,
    (R.70,
    71)
    .
    While the record is not
    entirely clear as to the efficacy of the grease trap to be used by
    Petitioners,
    it is clear that this will have some effect
    in reducing
    the amount of contaminants generated by the restaurant,
    (R.38,48,62-65).
    In addition, Petitioners have agreed that,
    if necessary,
    they will
    construct holding tanks for the restaurant,
    and discharge to the
    Wheaton Sanitary District’s sewers
    (and therefore to the STP)
    only
    during off-peak-load hours,
    (R.65,66).
    These facts
    do lead to the conclusion that the additional
    load
    placed on the “borderline” plant will indeed be small.
    That conclusion,
    taken with the uncontroverted testimony by
    a representative of the
    Wheaton Sanitary District that the STP
    is now beginning a major
    expansion,
    increasing the plant capacity from 53,000 PE to 89,000 PE,
    (R.
    17) within~thenext 600 days,
    (R.46-48),
    lead to the conclusion
    that the additional load which Petitioners’
    restaurant will add to the
    existing problems with the STP effluent will be both minute and short-
    lived.
    In addition,
    it
    is expected that many customers using the
    restaurant will b~from nearby apartments also tributary to the Wheaton
    STP,
    (R.33).
    In essence,
    the environmental damage which might be caused
    by the grant of the Variance
    is minimal.
    19— 643

    That minimal environmental damage
    is then measured against the
    considerable hardship which would result to Petitioners
    if the
    Variance is denied.
    While the necessity of foregoing the use of
    land in this situation is,
    in itself,
    insufficient,
    (See,
    e.g.,
    Weinstein,
    et al.
    V.
    EPA, PCB 71-107,
    122,
    192,
    2 PCB
    (197ITTT,
    the
    situation here is readily distinguished.
    Petitioners here stand the
    risk of losing financing commitment for the restaurant project,
    (R.42),
    and have foregone the use of permits to construct much larger projects,
    with
    a PE of up to 2,000,
    in order to continue with the restaurant
    project,
    (Stip.
    p.4).
    While we need not decide whether the principle
    of estoppel would be sufficient here alone
    as grounds for the Variance,
    we do find that statements by the Agency that the Wheaton STP would be
    allowed a considerable number of additional PE has added considerably
    to Petitioners’
    hardship.
    In granting this Variance,
    we shall set a condition which may
    require that Petitioners fulfill their offer
    to construct holding tanks
    for the restaurant.
    Based on Petitioners’ estimate that the restaurant
    will be completed
    in Fall,
    1976,
    and the Wheaton Sanitary District’s
    estimate that considerable additional capacity may be available within
    400 days,
    (R.47), we feel that
    it would serve no purpose to impose a
    holding tank requirement as an absolute condition.
    Instead, we shall
    require that the Agency evaluate the progress on the Wheaton STP in
    September,
    1976,
    and
    if
    in the Agency’s judgment sufficient additional
    capacity to handle the load generated by Petitioners’
    restaurant will
    not be available by July
    1,
    1977,
    Petitioners shall,
    as they offered
    at the hearing,
    (R.65), construct suitable holding tanks to the Agency’s
    specifications.
    This condition will,
    we feel,
    prevent the restaurant
    from adding to the STP’s violations of the applicable effluent standards
    for any unreasonable period.
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board in this matter.
    ORDER
    IT
    IS THE ORDER OF THE POLLUTION CONTROL BOARD that Petitioners,
    American National Bank and Alvin
    W.
    DeJong, be granted a Variance from
    Rule 962 of Chapter 3:
    Water Pollution,
    of the Pollution Control Board’s
    Rules and Regulations,
    to construct and operate as a wastewater source
    a “Denny’s Restaurant”
    as described in the foregoing Opinion,
    subject
    to the following conditions:
    19— 644

    —5—
    1.
    Petitioners
    shall,
    by September
    1,
    1976, obtain
    and forward to the Environmental Protection Agency a
    summary report on the progress of
    tlie Wheaton Sanitary
    District Sewage Treatment Plan expansion project.
    If,
    in
    the opinion
    of the Environmental Protection Agency
    said project will not provide sufficient capacity by
    July
    1,
    1977,
    such that Petitioners’ restaurant will add
    to any violations of this Board’s Rules and Regulations,
    Petitioners shall,
    by November
    1,
    1976,
    construct suitable
    holding tanks for the wastewater from said restaurant,
    such holding tanks
    to meet such specifications
    as the
    Environmental Protection Agency may require;
    the Board
    retains jurisdiction
    in this matter until November
    1,
    1976.
    Petitioners, American National Bank and Alvin
    W. DeJong,
    shall,
    within thirty
    (30) days of the date of this Order, execute and forward
    to the Environmental Protection Agency, Control Program Coordinator,
    2200 Churchill Road,
    Springfield,
    Illinois 62706, a certificate of
    acceptance
    in the following form:
    I,
    (We),
    __________________
    having read
    the Order~rihe Illinois Pollution Control Board
    in case No. PCB 75-75, understand and accept said
    Order, realizing that such acceptance renders all
    terms and conditions thereto binding and enforceable.
    SIGNED
    TITLE
    DATE
    Mr. James Young abstained.
    I, Christan L. Mof
    Control
    Board,
    adopted
    on
    the
    of
    of the Illinois Pollution
    ion and Order were
    by a vote of
    ______
    Christan L. Motte~
    Illinois Pollutio
    trol Board
    19—
    645

    Back to top