IL~INOISPOLLUTION CONTROL BOARD
January
14,
1976
ILLINOIS POWER COMPANY~
)
Petitioner,
v.
)
PCB 75—221
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Goodman):
This matter comes before the Pollution Control Board
(Board) upon the petition of Illinois Power Company
(Illinois)
for variance from Rule 203(f)
of the Water Regulations as it
applies to boron and Rule 408 of the Water Regulations as it
applies to total suspended solids
(TSS)
and pH.
Illinois
seeks its variance from the boron standard for a period of
12 months as an extension of the variance granted in PCB 74—
423.
The variance from Rule 408
is sought for a six month
period.
The facility for which the variances are sought is
Petitioner’s fossil-fueled electric power generating station,
Wood River, East Alton, Madison County,
Illinois.
Petitioner’s
final amendment to its petition was filed September 15,
1975.
Illinois uses an ash lagoon system to treat its fly and
bottom ash sluice waters.
After
fuel is burned,
it is
sluiced with water to the lagoon where settling of suspended
solids occurs.
During the retention period water reacts
with the fly ash releasing boron.
The effluent is discharged
into an unnamed tributary of Wood River Creek which flows
into Wood River Creek and eventually into the Mississippi
River.
Rule 203(f)
of the Water Regulations sets a boron
limitation of 1.0 mg/i.
Petitioner states that a 12 month
average of samples taken from the ash lagoon outfall averaged
0.693 ppm.
Nine out of the 23 samples exceeded the standard,
the highest being 1.70 ppm.
In PCB 74—423 the Board granted Petitioner variance
from Rule 203(f) ‘s boron standard while undertaking
a research
project on boron removal.
This variance expired on June
1,
1975.
Two
methods were finally suggested.
The first con-
cerned dry ash collection at an estimated cost of $1,500,000
to $2,500,000.
Illinois has excluded this method as too
costly.
The second method consists of installing
a boron
selective resin,
ion exchange membrane in the ash lagoon.
Illinois estimates this cost to be approximately $915,000.
19— 869
—2—
Petitioner has suggested the control of boron discharge
through routing the effluent to the Mississippi.
Route
“A”
would pass through the “borrow pit” area to the Shields
Branch which runs through twin culverts known as the
Twin
60’s.
However,
during flood times the Twin 60’s are. closed
creating a back up area of 72~3Ofeet.
?rn additional dis-
charge into this area of as much as 5.33 MGD would aggravate
existing environmental problems.
In addition this route
would not result in compliance as Rule 203(f) would still
apply.
Therefore the Board rejects alternate route “A”
as a
viable means of compliance.
See EPA v. Alton Box Company
et al, PCB 73—61 and 74—51.
Petitioner has also suggested alternate Routes “B” and
“C”.
Route
“B” requires
a sump, pumps,
a levee crossing and
a pipeline along the levee to the Mississippi River at a
cost of $349,000.
Route “C” requires
a graded open trench
in
an abandoned portion of the existing ash lagoon,
a
sulnp,
pumps,
levee crossing, and pipe to the Mississippi River at
a cost of $336,000.
In its September 15,
1975,
amendment, Petitioner states
that its existing ash lagoon is becoming too full to provide
adequate storage capacity and retention time for the remain-
ing life of the power plant.
Illinois will construct an
additional lagoon in the “borrow pit” area.
Engineering and
design work for the new lagoon will be complete within one
year.
When the new lagoon is finished, Petitioner suggests
that there are three “obvious” discharge routes from the
lagoon.
The first is the same as alternate route
“A”;
the
second would be over or under the new highway being built
along the Mississippi and the levee; the third would use the
existing route through the unnamed tributary of Wood River
Creek.
We have already rejected the first route.
The third
route would not result
in compliance with 203(f).
There-
fore,
the only viable route would be directly to the Miss-
issippi unless Petitioner obtains a regulatory amendment.
Petitioner states that there is another alternative,
i.e.,
seeking a long term variance pursuant to Commonwealth
Edison
v. Pollution Control Board,
25
Iii. App.
3d 271,
323
NE
2d
84
(1975).
The Board finds that this case does not
support a long term variance.
The First District Court
merely states that where the rules are arbitrary or un-
reasonable as applied, the remedy of the variance procedure
is available.
Commonwealth Edison,
supra at 90.
This would
not relieve Petitioner. of its duty to provide a viable
compliance plan.
In view of the foregoing,
the Board will grant Illinois
a limited variance from Rule 203(f).
Petitioner must submit
a final, corporate approved, compliance plan specifying the
route to the Mississippi which Petitioner will utilize to
comply with 203(f) by March 15,
1976.
Illinois
is also free
to seek a regulatory amendment.
19—610
—3—
Illinois seeks variance from Rule 408 of the Water
Regulations as
it applies
to TSS.
Petitioner will construct
berms within the existing ash lagoon to temporarily increase
retention time thereby decreasing
the TSS.
Permanent com-
pliance will result from the construction of the new ash
lagoon.
Petitioner seeks this variance for six months and
the Board finds that its compliance plan is adequate.
Illinois also seeks variance from Rule 408 of the Water
Regulations as it applies to pH.
However, Petitioner states
that it does not know the cause of the pH problem and has
provided no compliance plan.
Therefore,
the Board must
reject Illinois’ petition as it relates to pH.
This Opinion constitutes the findings of fact and
conclusions of law of the Board in this matter.
ORDER
It is the Order of the Pollution Control Board that:
1.
Illinois Power be and is hereby, granted variance
from Rule 203(f)
as
it pertains to boron of the Water Regu-
lations from June
1,
1975, until March
15,
1976,
subject to
the following conditions:
a.
That Petitioner provide a time
schedule for bringing the facility into
compliance and a detailed description of the
corporate approved program to be undertaken
to achieve compliance by March 15,
1976;
b.
That Petitioner prepare a feasi-
bility report,
including costs, of directing
its effluent from the new ash lagoon directly
to the Mississippi River;
c.
That the discharge not exceed 1.6
mg/l of boron in any
24 hour composite sample;
d.
That no effluent from the ash lagoons
be allowed to enter the Shields’ Branch im-
poundment area;
e.
That a feasibility report or alter-
native means of disposal of the fly ash
including dry storage of all ash be submitted
to the Agency within 90 days.
19—671
—4—
2.
Illinois Power
is hereby granted variance from Rule
408 of the Water Regulations as
it applies to total suspended
solids from September 15,
1975 until March 15,
1976.
3.
Illinois Power be and is,
hereby, denied variance
from Rule
408 of Chapter
3 as it applies to pH, without
prejudice.
Mr. Young abstains.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board,
hereby certify the above Opi ion and Order
were adopted on the
,,“~“
day of
1975byavoteof.3—~
Christan L. Moffett,
rk
Illinois Pollution C
rol Board
19—872