ILLINOIS POLLUTION CONTROL BOARD
November 26, 1975
VILLAGE OF STEWARDSON
V.
Petitioner,
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
)
PCB 75—445
ORDER OF THE BOARD (by Mr. Dumelle):
Petition filed November 14, 1975 is inadequate in that no
time schedule for Phase II construction is given nor is the
existence, if any, of algae blooms or problems upon Carlyle
Reservoir documented. The Federal document referred to in
the Petition should be supplied to the Board.
Petitioner shall amend the Petition within 45 days from
the date of this Order to supply the requested information.
Failure to timely file the Amended Petition shall make this
cause liable to dismissal for inadequacy. The 90—day decisipn
period set by statute shall run from the date of filing the
Amended Petition.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Order was adopted on the
~
day
of November, 1975 by a vote of r/-~
Illinois Pollution
19—345