ILLINOIS POLLUTION CONTROL BOARD
November 26, 1975
FIRESTONE TIRE
&
RUBBER COMPANY,
Petitioner,
v.
)
PCB 75—343
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD (by Mr. Zeitlin):
Firestone Tire & Rubber Company (Firestone) filed its
Petition for Variance on September 3, 1975, seeking relief
from Rule 109, “Circumvention,’ as it applies to Rule 204(d)
of Chapter 2: Air Pollution, of the Pollution Control Board
(Board) Rules and Regulations. PCB Regs., Ch. 2, Rules 109,
204(d). The relief is asked to allow the burning of mixed
natural gas and No. 6 residual fuel oil in boilers at Firestone’s
Decatur, Illinois manufacturing facility. A recommendation
was filed by the Environmental Protection Agency (Agency) on
October 10, 1975. No hearing was held.
BACKGROUND
Firestone uses three boilers to provide building heat
and process steam for its Decatur tire manufacturing facility.
These boilers are normally
fired
with natural gas, with
residual fuel oil as a standby fuel for periods of natural
gas service interruption. Two boilers are normally used,
with the third for standby use.
During 1974, Firestone purchased considerable quantities
of 1.8 sulfur fuel oil for standby use in its boilers, in
expectation of 80 days of natural gas service interruption.
Firestone planned to consume this high sulfur fuel oil by
May 30, 1975, after which date Rule 204(c) (2) (A) limited sulfur
dioxide emissions from residual oil—burning sources to a total
of 1 lb. per million btu, a limit which could not be met with
1.8 sulfur oil. Firestone planned to use low sulfur (0.9
-
0.95 sulfur) fuel oil after May 30, 1975. However, as a result
of unexpectedly few gas service interruptions during the last
heating season, Firestone now has remaining in inventory approxi-
mately 820,000 gallons of the high sulfur fuel oil, in addition
to considerable quantities of the low sulfur fuel oil.
19
—
333
—2—
Firestone now proposes that it be allowed to use its stocks
of 1.8 sulfur fuel in combination with natural gas, during
periods of gas availability. Firestone would, under this plan,
continue with its original plan to use the low sulfur oil during
periods of gas service curtailment, to minimize SO2 emissions.
Unfortunately, our Rules make no provision for an emission
source burning a combination of residual fuel oil and natural
gas, and Firestone has brought this Variance Petition before
us.
Firestone’s Petition is novel, and the relief it asks has
not, to our memory, been requested before. Firestone specifically
asks for a Variance from Rule 109, “Circumvention,” as that
rule applies to Rule 204(d), “Combination of Fuels.” Firestone
asks that it be allowed to include the btu heat input from
natural gas within the portion of the equation in Rule 204(d)
that would apply to residual fuels. If we allow that procedure,
SO2 emissions from Firestone’s Decatur plant will never exceed
the limits in Rule 204. During periods of gas availability, the
use of natural gas to provide 55 of the btu heat input for the
boilers will allow compliance with Rule 204(d). During periods
of gas unavailability, use of low sulfur fuel oil will allow
compliance with Rule 204 (c) (2) (A).
HARD
SHIP
It would appear that Firestone acquired its stock of
high-sulfur residual oil in good faith, and with no intent to
“circumvent” the emission regulations. Rule 204 (c) (2) (A),
which would require the use of low sulfur oil at the Firestone
plant, did not become effective until May 30, 1975; Firestone
fully expected to use all of its high sulfur oil before that
date.
Now, as a result of warm weather and other factors during
the last heating season, Firestone has a large inventory of high
sulfur oil which it cannot burn legally nor sell. Firestone’s
Petition indicates that it simply has not been able to obtain a
buyer for the 820,000 gallons of 1.8 sulfur oil, which it acquired
at a cost of $210,000. In addition, the storage costs for this
oil are
$1,950
per month. Firestone has had to lease facilities
in Meridosia to store 320,000 gallons of the high sulfur fuel
oil. Storage at its own plant prevents Firestone from stocking
large quantities of low sulfur oil for use during future gas
service curtailments, so that additional off—site facilities
would be required. Firestone states that it has not been able
to arrive at a salvage value or disposal cost for the high
sulfur oil, in the event that the Variance is not granted.
19—
334
—3—
EMISSIONS
Rule 204
(C)
(2) (A) allows emissions of 1 lb./million btu
for SO~,where residual oil is used as a fuel. Firestone
estimates that at peak firing, it would be allowed emissions
of 97.50 lb. ~ for each operating boiler under that~Rule.
Rule 204(d), as applicable here, would normally allow
only the same emissions per million btu of fuel oil heating,
with no allowance for the gas used, because the heating value
of th~naturalgas could not be used in arriving at the allowable
emission value. Firestone asks in its Petition that the
Variance allow the inclusion of the natural gas, resulting
in an allowable emission of 97.5 lb. SO2 per hour. Actual
emissions from the combination of fuels will be 80.51 lb,/hr.
of SO2.
TRAIN
This Board has previously stated that it cannot grant a
Variance where such Variance will result in a failure to attain
or maintain national ambient air quality standards, under the
rule of Train v. N.R.D.C. 43 U.S.L.W. 4467 (U.S., April 16, 1975).
See King-Seeley
V.
EPA, PCB 75-159, (April 24, 1975) (Interim
Order); Shell v. EPA, PCB 75-90 (May 22, 1975). Firestone’s
Petition contains considerable atmospheric modeling which
indicates that under the most stringent of stability conditions,
at maximum emission levels from the Firestone plant, and
assuming considerable ambient background SO., concentrations,
the areas most affected by Firestone’s plant would not experience
a violation of those standards. In addition, the Agency concludes
in its Recommendation that Firestone’s emissions “would not have
a significant adverse effect on ambient air quality in the area.”
We note that the Agency’s 1974 Annual Air Quality Report,
at page 140, states that “tjhe air quality standards for sulfur
dioxide were not exceeded at any of the monitoring sites in
this region.” (The statement was made for the “West Central
Illinois Interstate Springfield
-
Quincy Air Quality Control
Region 75.”)
19—335
—4--
THE VARIANCE
Examining both the hardship and the effect of the proposed
emissions on the area to be affected, we feel that a Variance
is warranted. We agree with the Agency that Firestone has
requested the wrong relief in asking a Variance from Rule 109
as it applies to Rule 204(d); however, we disagree with the
Agency’s statement that relief should be granted from Rule 109
as it applies to Rule 204 (c) (2) (A). A Variance from Rule 109
is not an appropriate action; a Variance from Rule 204 (c) (2) (A),
by itself, will be sufficient. As a condition to the Variance
we will require that the high sulfur oil be used only in
conjunction with natural gas, as proposed in the Petition.
We agree with the Agency that Firestone has requested the
Variance for an excessive period of time, Instead of the nine
months requested, the Agency feels that regular use of the
combined fuels would allow complete exhaustion of the high
sulfur fuel oil within 3-1/2 months. The Agency’s Recommendation
does not allow for any future gas service interruptions. We
therefore shall allow five months for Firestone to use its
existing stocks of high sulfur oil.
We shall also require that Firestone notify the Agency upon
completion of its program to use the combined fuels, and of the
amount of high sulfur oil used each month during the Variance
period. As a final condition, we shall require a standard
Certification form.
This Opinion constitutes the findings of fact and
conclusions of law of the Board in this matter.
ORDER
IT IS THE ORDER OF THE POLLUTION CONTROL BOARD that
Petitioner Firestone Tire & Rubber Company be granted a Variance
for a period of five months from the date of this Order from
Rule 204(c) (2) (A) of Chapter 2: Air Pollution, of the Pollution
Control Board Rules and Regulations, to allow the use of existing
stocks of high sulfur oil in the boilers at its Decatur plant,
subject to the following conditions:
19— 336
—5--
1. Petitioner’s existing stocks of 1.8
sulfur residual fuel oil may only be used in
conjunction with natural gas, such that the
natural gas provides 55 of the actual heat
input to its boilers, the remaining 45 of
actual heat input to be provided by the 1.8
sulfur residual fuel oil.
2. Petitioner shall burn the above
combination of fuels during all periods of
natural gas availability.
3. Petitioner shall, by the 10th day
of each month during the term of this Variance,
report to the Environmental Protection Agency
the amounts of 1.8 sulfur residual fuel oil
used and the remaining stocks of 1.8 sulfur
residual fuel oil, and shall report immediately
upon exhaustion of its existing stocks of 1.8
sulfur residual fuel oil.
4. Petitioner shall, within 30 days of
the date of this Order, submit to this Board and
to the Environmental Protection Agency a
Certificate of Acceptance in the following form:
I, (We),
_________________________
having read
the Order of the Illinois Pollution Control Board
in case No. PCB 75-343, understand and accept said
Order, realizing that such acceptance renders all
terms and conditions thereto binding and enforceable.
SIGNED
TITLE
DATE
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify the above Opinion and Order w re
adopted on the ~
day of
~
~
by a vote of
_____
Illinois Pollution
19—337