ILLINOIS POLLUTION CONTROL BOARD
    July 31, 1975
    JOHN BERG MANtJFACTURING.cO.,
    Petitioner,
    )
    v.
    )
    PCB 75—225
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD (by Mr. Zeitlin)
    Petition for Variance was received by the Boarö. on
    June 2, 1975. The Board, on June 6, 1975, entered an Interim
    Order setting forth ~1efinit±ve reasons as to why the Variance
    Petition was deemed to be inadequate, and requested that
    Petitioner file ar~ Amended Petition within 45 days correcting
    those deficiencies.
    Failure to timely file such Amended Petition has resulted
    in dismissal of this matter as inadquate.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the above Order s~jas adopted on
    the
    ~3/~”
    day of
    ,
    1975 by a vote of
    ~
    Q&~fL.Mofe~t’~2V~
    Illinois Pollution Con.. 1 Board
    18