ILLINOIS POLLUTION CONTROL BOARD
    July
    24,
    1975
    OTTAWA SILICA COMPANY,
    )
    Petitioner,
    vs.
    )
    PCB 75—99
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    MICHAEL REAGAN,
    Attorney for Petitioner
    WILLIAM ERDMAN, Attorney for Respondent
    OPINION AND ORDER OF THE BOARD
    (by Mr. Henss):
    Ottawa Silica Company filed its Petition for Variance
    seeking relief from Rules
    203(g) (1) (B)
    (particulate emissions)
    and 203(i) (4)
    (compliance dates)
    of the Illinois Air Pollution
    Control Regulations
    from May 30, 1975 until December
    31, 1975.
    Variance
    is sought in order to continue operating five coal—
    fired boilers pending completion of a new operating system
    which includes replacement of the coal—fired boilers.
    A public
    hearing was held in this matter in May 1975.
    No members of the
    public were in attendance at this hearing.
    Petitioner operates a facility near Ottawa,
    Illinois for
    the mining,
    cleaning, drying, sizing,
    and grinding of silica
    sand.
    Products from this facility are marketed nationally and
    internationally
    in the glass,
    foundry, chemical,
    oil well,
    construction and transportation industries.
    Petitioner’s
    Ottawa facility is one of the largest industrial and producing
    facilities
    in the United States.
    Approximately 210 persons are
    employed at this facility.
    Five coal—fired boilers are used at this facility in order
    to produce steam heat for sand drying,
    space heating and other
    miscellaneous purposes.
    Four of the five boilers are identical
    Bros boilers with rated heat inputs of 82.25 million Btu’s per
    hour.
    Particulate emissions from these boilers are controlled
    by settling chambers which are estimated to be 50
    efficient.
    Operating permits for these boilers expired on May 30,
    1975.
    The remaining boiler
    is a Babcock and Wilcox boiler with a rated
    heat input of 138 million Btu’s per hour.
    Particulate emissions
    18
    175

    —2—
    from this boiler are controlled by a mechanical collector with
    an estimated efficiency of 88.
    The operating permit for this
    boiler expired on March 21,
    1975.
    During normal operations Petitioner operates
    two or three
    of the five boilers simultaneously.
    Analysis of the Illinois
    coal used at this facility shows
    that it contains 7.5
    ash,
    3
    sulfur and that it has a heat content of 13,250 Btu’s/lb.
    Emissions from the four Bros boilers are vented to a common
    stack while the Babcock and Wilcox boiler vents
    to a separate
    stack.
    The calculated particulate emission rate from
    a Bros
    boiler
    is 0.70 lbs. per million Btu’s.
    A particulate emission
    rate of 0.17 lbs. per million Btu’s has been calculated for the
    Babcock and Wilcox boiler.
    Rule 203 (g) (1) (B) requires the four
    smaller boilers
    to meet a 0.29 lb.
    per million Btu particulate
    emission rate after May 30,
    1975.
    The larger Babcock and Wilcox
    boiler
    is required to meet a particulate emission rate of 0.15
    lbs.
    per million Btu after that date.
    Petitioner is currently engaged in a compliance program
    that involves the construction of
    a completely new process system.
    Planning for the new system began in January 1971 because of a
    recognized need to reduce noise and air pollution.
    One feature
    of the program will be the replacement and retirement of all
    five coal-fired boilers. Fluidized bed oil—fired sand drying
    systems will be utilized in the new process and two small boilers
    will be installed to meet t’~espace heating requirements.
    Once
    the new facility is in operation the coal-fired boilers will be
    dismantled and sold.
    Preliminary engineering for this compliance program was
    completed in March
    1973.
    The contractor for this project,
    Hunter Corporation, estimated that the entire project would be
    completed on or before November 30,
    1974.
    Shortly after con-
    struction commenced,
    the contractor began to encounter difficulty
    with
    the
    purchase and delivery of the 1400 tons of structural
    steel required for the project.
    Testimony by Hunter’s Project
    Manager indicates that the steel shortage was nation-wide.
    Orders placed with the major steel producers were returned
    cancelled, causing Hunter to search for the steel at various
    warehouses around the country.
    A premium price was paid for
    the “off-the-shelf”
    steel
    in order
    to keep the project going
    CR.
    62).
    In addition, a six week strike at the construction site in
    1974 caused problems for Hunter,
    and this delayed issuance of
    a
    revised completion date until October 1974.
    Driers scheduled
    for delivery in October 1974 were not received on site until
    April 1975 according to the Project Manager.
    Hunter now estimates
    that it can complete the project by August 15,
    1975 barring any
    unforeseen delays.
    Correspondence between Hunter and Petitioner
    confirmed that problems had been encountered
    in steel procurement.
    (Agency Recommendation, Attachment 2).
    18
    176

    —3--
    According •to terms of the construction contract, Hunter
    will not be penalized for the delays in completing the project.
    However,
    testimony indicates that Hunter has incurred costs
    of
    $1.2 million
    in excess of anticipated costs
    (R.
    93).
    Robert Lacke, Petitioner’s Director and Vice President of
    Operations, testified that the incentive to complete the project
    rests with Ottawa Silica because of the cost on borrowed money.
    It now costs Ottawa Silica between $140,000 and $170,000 in
    carrying costs for each month the project
    is extended
    CR.
    91).
    Upon completion of the construction phase of the project,
    Petitioner will immediately implement its start—up procedure
    in order
    to bring the new operation on line as quickly as
    possible.
    Petitioner’s Division Manager, Lester Richards,
    testified that the start-up procedure will require a minimum of
    14
    weeks
    thus
    pushing
    the
    actual
    start-up
    date
    for
    the
    new
    process
    to
    late
    November
    1975.
    Serious
    problems
    encountered
    during start-up could result in delays totalling 59 weeks
    CR.
    44).
    Variance
    is sought only until December
    31,
    1975 in the belief that
    no serious problems will develop during start-up.
    Hunter’s
    Project Manager testified that the December
    31,
    1975 date re-
    flects
    a very optimistic view on Petitioner’s behalf
    CR.
    63).
    The coal-fired boilers could be brought into compliance by
    the installation of additional particulate collecting devices.
    James Caselton, Petitioner’s Chief Engineer,
    testified that such
    a project could be completed in
    7 to
    9 months
    (R.
    81)
    at an
    estimated cost of $200,000
    (R.
    80).
    Since the coal-fired
    boilers will not be used in the new process, none of these
    control devices would be of serviceable value once the new
    system is placed on line.
    Caselton testified that Ottawa
    Silica agrees with the Agency on maximizing use of the Babcock-
    Wilcox boiler during the variance period sought because of its
    lower particulate emission rate.
    Data obtained from the Agency’s Ottawa monitoring station
    show that for the period fr~mAugust 1974 through March 1975
    a geometric mean of 41 ug/m
    was achieved.
    Monthly geometric
    means during this period ranged from 27 to
    66 ug/m~. The highest
    reading during this period, 139 u.g/m3, occurred one day during
    August 1974.
    Petitioner was operating its coal-fired boilers
    during the sampling period.
    Petitioner has not received any
    complaints about emi~ionsfrom the, facility for the last
    operating year
    CR.
    41).
    Petitioner calculates that particulate emissions from its
    Babcock and Wilcox boiler exceed the allowable emission rate by
    2.77 lbs./hr.
    An excess emission rate of 23.88 lbs./hr.
    is
    calculated for each of the Bros boilers.
    Petitioner operates
    eight months of the year using the Babcock-Wilcox boiler and
    one of the Bros boilers.
    Based on theoretical calculations,
    18—
    177

    —4—
    Ottawa Silica submits that operation of the coal-fired boile~s
    during the variance period sought would result in a 4.6 ug/m~
    burden on the air at its property line and 0.79 ug/m3 at the
    Agency’s Ottawa monitor.
    The Agency questions whether Petitioner could accurately
    predict the plume rise from the stacks on the basis of only
    five observations and whether the wind speed used in the cal-
    culations,
    5 miles per hour, was accurate.
    The Agency suggests
    that Petitioner should have used information from the National
    Climatic Center showing a “most common wind speed” of 8.0
    to
    11.5 mph for all major weather reporting stations in Northern
    and Central Illinois.
    In the Agency’s opinion,
    a sampling
    period of eight months may not be sufficient upon which to
    base conclusions concerning the annual geometric mean for
    particulates in the Ottawa area.
    Both the primary and secon-
    dary ambient air quality standards for particulates are
    expressed in annual geometric means and 24-hour
    maximum
    con-
    centrations.
    However,
    the Agency does not
    totali.y reject
    Petitioner’s calculations and recommends that the variance be
    granted, subject to certain conditions, until December 31,
    1975
    (R.
    97)
    It is the finding of the Pollution Control Board that
    Petitioner has met its burden of proof.
    Delay
    in completion
    of construction on the new system was beyond the control of
    Petitioner.
    The Board is satisfied that Petitioner has made
    and will continue to make every reasonable effort to complete
    the project as quickly as possible.
    The evidence indicates
    that ambient air quality standards will not be violated by the
    grant of variance in this case.
    The Babcock and Wilcox boiler at Petitioner’s facility
    exceeds the allowable emission rate only slightly.
    Each of
    the Bros boilers emits particulate matter considerably in
    excess of the allowable rate.
    Petitioner admits that it could
    bring the coal-fired boilers into compliance.
    However, to
    require control devices
    to be installed on the boilers at this
    time would clearly be an unreasonable measure and it is most
    doubtful whether the boilers could be brought into com-
    pliance before they reach the end of their useful life.
    Ottawa Silica is near the end of a major project which
    will bring the activity into compliance with the particulate
    emission limitations.
    The Company,
    its employees and neighbors
    will benefit considerably from this project.
    In consideration
    of the fact that Petitioner began planning this compliance
    program at a time preceeding many environmental regulations,
    the Board commends Petitioner for its foresight and diligence.
    18
    178

    —5—
    This Opinion constitutes the findings of fact and con-
    clusions of law of the Illinois Pollution Control Board.
    ORDER
    It is
    the Order of the Pollution Control Board that
    Ottawa Silica Company be granted variance from Rule 203(g) (1) (B)
    and Rule 203(i) (4) of the Illinois Air Pollution Control
    Regulations
    from May 30,
    1975 until December 31,
    1975 for its
    Ottawa Silica plant.
    Variance is granted subject to the
    following conditions:
    1.
    During the period of this variance, Petitioner
    shall make every effort to maximize use of the Babcock
    and Wilcox boiler and minimize use of the Bros boilers.
    2.
    Petitioner shall submit monthly progress reports
    to the Environmental Protection Agency.
    Said progress
    reports shall commence on August 15,
    1975 and shall pro-
    vide details of Petitioner’s programs toward completion
    of the fluidized bed drying system.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the
    bove Opinion and Order was
    a opted
    the
    p4~
    day of
    ___________,
    1975 by a vote of
    -c:~
    Christan L. Moffe
    ,
    erk
    Illinois Pollution
    ntrol Board
    18
    179

    Back to top