ILLINOIS POLLUTION CONTROL BOARD
    March 25,
    1976
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Complainant,
    v.
    )
    PCB 75—232
    CITY OF SPRINGFIELD,
    )
    Respondent.
    -
    and
    -
    CITY OF SPRINGFIELD,
    Complainant,
    v.
    )
    PCB 75—275
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    Larry Eaton and Anthony Cameron appeared on behalf of the Environ-
    mental Protection Agency.
    George Gilimor, Eugene Bernstein and Charles Bane,
    of Isham, Lincoln
    & Beale appeared on behalf of the City of Springfield.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Goodman):
    On June
    3,
    1975,
    the Environmental Protection Agency
    (Agency)
    filed a Complaint against the City of Springfield
    (City).
    This
    Complaint, ?CB 75-232, alleged construction of
    a new coal-fired
    electric generating unit,
    known as Dallrnan Unit
    3, without a construc-
    tion permit,
    in violation of Rule 103(a) (1) of the Air Pollution Regu-
    lations
    (Chapter 2).
    On July
    16,
    1975, the City filed a Permit
    Appeal, PCB 75-275, alleging that the Agency improperly denied
    its
    application for a construction permit for Dailman Unit
    3.
    These
    two proceedings, as well as another proceeding, PCB 75—242, were
    consolidated for hearing.
    At public hearing on November 17,
    1975,
    however, PCB 75-242 was severed from these proceedings by order
    of the hearing officer.
    PCB 75-242
    is now an entirely separate
    matter and will not be considered herein.
    Hearings on PCB 75-232 and PCB 75-275, consolidated, were held
    on November
    4,
    5,
    6,
    7,
    8,
    and
    17,
    1975,
    in Springfield, Illinois,
    20
    33g

    —2—
    and produced a voluminous record of some 1350 pages.
    No citizen
    witnesses testified during the hearings.
    The City filed a waiver
    of its right to a decision on the Permit Appeal within
    90 days from
    the filing of said Appeal.
    Springfield operates an electric power generating supply system
    servicing 48,000 ratepaying customers in the Springfield area
    (R.
    384).
    Power production
    is administered by a department of the City govern-
    ment known
    as City Water, Light
    & Power
    (CWLP).
    The City built and
    began operating its
    first power station at its premises abutting Lake
    Springfield
    (Lakeside I)
    in 1935
    (R.
    223).
    Lakeside II was built
    in
    the 1940’s, but was added to until 1963
    (R. 224).
    The units of
    Springfield’s V.Y. Daliman power plant complex were begun in the
    early 1960’s on the same general premises where the Lakeside stations
    were located.
    Daliman Unit
    1 went on-line in 1968 and Dallman Unit
    2
    went on-line
    in 1972
    (R.
    224).
    Dailman Unit
    3,
    the subject of these
    proceedings,
    is currently projected to become operational in the
    spring of 1977
    (R.
    353).
    Mr. Edward Campbell, Regional Supervisor
    in the Field Operations Section of the Agency’s Air Pollution Control
    Division, testified that in April,
    1975, he and another member of
    the Agency inspected the Daliman Unit
    3 site
    (R.
    46).
    They esti-
    mated that,
    at that time,
    construction was approximately
    10 percent
    complete
    (R.
    50).
    The site had been excavated,
    concrete had been
    poured, and steel was being erected
    (R.
    50).
    Daliman Unit
    3 is
    to be
    a 192 megawatt. unit, representLng 72
    of the capacity of the City’s existing electrical system
    (R.
    396).
    The capital cost for the Dailman Unit
    3 construction program in its
    present form is slightly under $56 million
    (R.
    340).
    The City applied for a construction permit for Dailman
    3 on
    June 10,
    1974.
    The Agency denied the application due to failure to
    show compliance with several of the Chapter 2.r~guiat~ons~:
    ~,particu-
    lates,
    Rule 203(g) (1) (d)
    ,
    sulfur dioxide, Rule 204(a)(l),
    and, nitrogen
    oxides,
    Rule 207(a).
    A second application was rec~iy~:bytheAgency
    on August
    10,
    1974.
    On October
    5,
    1974, thesecond app1i~ca14onwas
    denied due to failure to show compliance withRu1es~204(a)(:stack
    height)
    and 204(a) (1) (sulfur dioxide).
    The principal issue presented in this case
    is whether Daliman
    Unit
    3 is
    a new or existing emission source.
    .Resoi~t~on~.p~f
    t~at
    issue resolves two related questions:
    whether a pq~i~4~
    is required
    for Dailman Unit
    3 under Rule 103(a)
    (1): and~whether~O~1-manUn~Lt
    3
    must comply with the sulfur dioxide 1imitati~on~fp~r~
    ~
    Rule 204(a) (1),
    in force
    at the time of the City’s application,
    or
    for existing sources under Rule 204(c) (1) (B).
    According to the
    Agency’s calculations, Daliman Unit 3:will ~
    SO2
    20—340

    —3—
    per million btu’s of actual heat input
    (R.
    143)
    .
    This figure indi-
    cates that Dallman Unit
    3,
    if found to be an existing source, would
    comply with Rule 204(c)(l)(B).
    If found to be a new emission source,
    however, Dailman Unit
    3 would not comply with the limitation of
    1.2 pounds per million btu’s,
    required by Rule 204(a) (1).
    Whether an emission source
    is considered new or existing depends
    upon whether construction or modification of the source “commenced’t
    after or prior to the effective date of Chapter
    2, April
    14,
    1972.
    Rule 101 defines
    1’commence”
    as
    the act of entering into a binding agreement
    or contractural obligation to undertake and
    complete, within
    a reasonable time,
    a continuous
    program of construction or modification.
    The Pollution Control Board
    (Board)
    in its Interim Order of July
    31,
    1975,
    interpreted this definition as applied in the present case in
    order to account for the possibility of the City being its own
    general contractor,
    as follows:
    Whether Springfield had bound itself to
    a course
    of conduct to undertake and complete, within a
    reasonable time,
    a continuous program of construc-
    tion.
    In adopting the definition of a new source the Board,
    on April
    13,
    1972,
    commented that the definition
    recognizes that once binding contracts have
    been entered for construction of
    a facility,
    there
    is
    a significant reliance interest in treating the
    source as an existing one.
    Reliance,
    then,
    is the key to the distinction between new and exist-
    ing sources.
    The date for determining whether Dailman Unit
    3
    is
    a new or
    existing emission source
    is April
    14,
    1972.
    Therefore,
    it
    is im-
    portant
    to examine what occurred prior
    to that date.
    As mentioned
    previously,
    Dailman Units
    1 and
    2 went on-line in
    1968 and 1972,
    respectively.
    In 1970 Springfield requested the engineering firm
    Burns
    &
    McDonnell to make a study of the City’s generation needs and
    financing ability
    (R.
    251).
    That report was submitted in ~4ay,1970,
    and a supplemental report was submitted in July,
    1970
    (R.
    252-3).
    Burns
    & McDonnell recommended that the City proceed immediately with
    Dallman Unit
    3.
    At that time,
    however, Dailman
    3
    was
    still
    in the
    planning stages and had not yet been designed
    (R.
    253).
    The first
    20 —341

    —4—
    contract for the construction
    of
    Daliman
    3 was awarded on September
    29,
    1970
    to General Electric for
    a steam turbine generator
    (R.
    256)
    Burns
    &
    McDonnell submitted specifications for coal-handling facili-
    ties,
    specifically,
    for foundations and construction of
    2 underground
    coal hoppers, on July
    2,
    1971.
    The contract was awarded on September
    7,
    1971,
    to Franklin Cress Company
    (R.
    267).
    A related contract for
    an underground conveyor and drive mechanism was awarded to Fertilizer
    Engineering Company on February
    1,
    1972
    (R.
    283-4).
    The City antici-
    pates awarding
    a total of
    45
    contracts
    for Dallman
    3
    (R.
    304).
    How-
    ever,
    these
    3 contracts
    -
    for the steam turbine generator and coal-
    handling facilities
    -
    were the only contracts for the construction of
    Dailman
    3
    awarded prior to April
    14,
    1972.
    Four other contracts re-
    lated to Daliman
    3 were also entered into prior to April 14,
    1972:
    two
    contracts for oil circuit breakers, one for steel towers,
    and one for
    a volt tie transformer
    (R.
    493—5)
    The steam generator itself
    is
    to house the boiler and, therefore,
    the furnace.
    Specifications for the steam generator were submitted
    by Burns
    &
    McDonnell
    on May 21,
    1971.
    These specifications called
    for a bid on a scrubber for SO2, which was an alternate to the base
    bid
    (R.
    312)
    .
    Bids were received on August 17,
    1971.
    Two
    scrubber
    bids were submitted
    (R.
    313)
    .
    The ordinance
    to
    award the contract was
    filed in September,
    197.1.
    At
    that time an ordinance for a new rate
    structure was also on file.
    However, due to
    the
    President’s economic
    freeze on wages and prices,
    the contract and rate increase were
    tabled by the City Council and bid bonds were returned
    (R.
    276).
    The 1971 rate increase proposal included $10 million for air
    pollution control equipment.
    City, Water,
    Light
    &
    Power
    (CWLP),
    urged
    the City Council
    to adopt the rate structure in 1971 with the money
    included for SO2 control equipment so that CWLP could issue bonds
    if
    necessary
    (R.
    316).
    The City Council approved the rate structure in
    January,
    1972.
    However,
    even
    though the approved rate structure in-
    cluded the original
    $10 million,
    the City Council required ~WLP not
    to include in the increase money needed to
    finance gas cleaning equip-
    ment
    (R
    314)
    Specifications
    for the
    steam generator were submitted again in
    1973.
    These specifications differed
    from
    those submitted in 1971
    in
    that they included a 2400 pound rather than 1800 pound boiler and
    did
    not include specifications for a scrubber for
    SO2
    (R.
    313)
    .
    The
    steam
    generator
    contract
    was
    awarded
    on
    August
    8,
    1973.
    The
    Agency
    argues
    that,
    because
    SO2
    will
    be
    created
    within
    the
    furnace,
    which
    is
    within the steam generator,
    the contract for the
    steam
    generator
    is
    the
    critical
    contract:..
    Because
    this
    contract
    was
    awarded
    in
    Auqust,
    1973,
    Dallninn
    Unit
    3
    is,
    according
    to
    the

    —5—
    Agency,
    a new source.
    We must reject this argument.
    To single out
    one piece of equipment in an entire unit as the “emission
    source’t
    is
    to deny the interdependence of most of the individual pieces of equip-
    ment which comprise an electric generating unit such as Daliman Unit
    3.
    Contracts for the turbine generator and coal handling facilities were
    entered into prior to April
    14,
    1972.
    However,
    these facilities would
    be unable to serve their intended purpose in the absence of the steam
    generator producing the steam necessary to drive the turbine—generator
    while utilizing the coal-handling facilities.
    Similarly,
    the steam
    generator depends on these facilities
    to accomplish its purpose.
    We,
    therefore,
    find that Dallrnan Unit
    3 as
    a whole, rather than any indi-
    vidual element thereof, constitutes the “emission source,”
    for the
    purposes of this case.
    Although we find that prior to April
    14,. 1972,
    the City had
    entered into certain binding contracts for the construction of its
    emission source,
    we nevertheless must agree with the ultimate conclu-
    sion that Dailman Unit
    3 is
    a new emission source.
    Our finding is
    based upon the policy behind Rule 101’s distinction between new and
    existing sources:
    that a source is
    to be considered existing if
    the owner or operator of that source binds itself to a course of con-
    struction relying upon the state of the law as it existed prior to
    April 14,
    1972.
    Based upon the facts presented at the hearing on
    this matter, we are unable
    to find any reliance on the part of the
    City of Springfield on its status as
    an existing source.
    In 1971,
    specifications for the steam generator submitted for bids included a
    specification for SO2 control equipment.
    In fact,
    two bids for
    scrubbers were received by the City.
    Although the 1971 bid bonds
    were returned and the 1973 specifications did not include S02 control
    equipment, the 1971 specifications indicate that the City foresaw
    the possibility of being required to reduce S02 emissions from Daliman
    Unit
    3.
    Furthermore, Mr.
    James Henneberry,
    Commissioner of Public
    Property for the City,
    testified as to why the City excluded S02 re-
    moval equipment from its construction permit application.
    He testi-
    fied that inquiry hearings being conducted by the Board on SO2 control
    technology, various pending appeals on the subject, hearings being
    conducted on a national level,
    and
    a permit granted to the Central
    Illinois Light Company
    (CILCO)
    left an aura of uncertainty which
    caused the City to be hesitant before committing itself to the ex-
    pense of SO2 control equipment
    (R.
    1202).
    Commissioner Henneberry,
    however, did not indicate, nor did any other witness, that the City
    failed to plan for 502 control equipment because
    it considered it-
    self to be an existing source and was relying upon that status.
    All
    the testimony reveals quite the opposite
    -
    i.e.,
    that the City
    considered Daliman Unit
    3 to be governed by Rule 204 (a) Cl) but was
    hesitant to invest in SO2 control equipment due to its uncertainty
    as to the status of that regulation.
    Furthermore, the definition of commence that the Board has
    20— 343

    —6—
    adopted requires Springfield to have “bound” itself to a “continuous”
    course of construction prior to April 14,
    1972.
    Yet facts presented
    indicate that the City’s course of conduct was intermittent rather
    than continuous.
    Although bids on the steam generator were received
    in
    1971,
    these were returned,
    and new specifications were not issued
    until February of 1973
    (R.
    276).
    Springfield initiated the project,
    tabled it,
    and then resumed.
    Such conduct is not evidence of being
    bound to a continuous course of construction.
    During the period of
    delay, the Air Regulations in question became effective.
    The lack of
    a showing of reliance on the law prior to April
    14,
    1972,
    coupled
    with a significant interruption in the course of construction during
    the period of time in which the applicable Air Regulations became
    effective,
    lead to the conclusion that Dailman Unit
    3
    is a new
    emission source.
    It was, therefore,
    subject to Rules 103(a) (1)
    and
    204(a) (1)
    at the time the City submitted its application.
    During the hearing, the City presented much evidence about a
    construction permit granted by the Agency to CILCO.
    The Hearing
    Officer reserved to the Board a motion by the Agency attorney to
    exclude all such testimony as irrelevant.
    We hereby grant the
    Agency’s motion.
    The CILCO situation differs significantly from
    the situation in the present case,
    and the Agency’s treatment of
    another facility is irrelevant
    to its treatment of Daliman Unit
    3.
    Finally, although we uphold the Agency’s denial of the City’s
    application based upon Rule 204 (a) (1), we reject its finding that
    the construction permit application did not comply with Rule 204(e).
    Contrary to the Agency’s position, we find that the application did
    include a specification, not merely speculation, of
    a minimum stack
    height of 450 feet
    to achieve compliance with Rule 204(e).
    Having concluded that the Agency properly denied the City’s
    application on the basis of Rule 204 (a) (1), we find that the City has
    allowed construction work to be done toward erection of Dailman Unit
    3 in the absence of a construction permit,
    in violation of Rule 103(a)
    (1).
    However, one more point remains for Board consideration.
    Section
    33(c)
    of the Environmental Protection Act
    (Act)
    requires the Board
    in making its orders and determinations to consider:
    1)
    the degree
    of injury to the public,
    2)
    the social and economic value of the
    pollution source,
    3)
    the suitability of the pollution source to its
    area of location, and
    4)
    the technical practicability and economic
    reasonableness of reducing the emissions.
    As to the first factor,
    there has been no direct injury to the public
    as of yet because
    Daliman Unit
    3 has not been completed.
    Injury to the public is in-
    herent, however, when a violation of the permit requirements of the
    Act or Rules and Regulations occurs.
    The social and economic value
    of Dallman Unit
    3 and its suitability to its area of
    location are
    unquestioned.
    As to the last factor,
    at the hearing, much evidence
    344

    —7—
    was presented on the technical practicability and economic reason-
    ableness of reducing the emissions.
    Testimony was presented on the
    various types of SO2 control equipment currently available,
    including
    both the regenerable and throw—away type systems,
    the success of such
    equipment,
    and the cost.
    We have considered the extensive testimony on technical practi-
    cability and economic reasonableness and find that reducing SO2
    emissions from Dailman Unit
    3 is both technically practicable and
    economically reasonable.
    Various SO2 removal systems have been in-
    stalled
    in countries such
    as Japan and Germany and are currently
    commercially available and being installed on facilities
    in this
    country.
    Lead times on the various
    systems vary, but, according to
    testimony produced at the hearing, generally range from
    2
    -
    3 years
    (R.
    716).
    SO2 control equipment has become an accepted form of tech-
    nology.
    The City estimates that SO2 control equipment will cost
    approximately $18.9 million.
    However,
    the high cost of installing
    such equipment is reasonable
    in order to protect the public from in-
    jury.
    Therefore,
    the Board finds that reducing emissions from Dailman
    Unit
    3
    is reasonable both technically and economically.
    In Commonwealth Edison Company
    v. Pollution Control Board,
    decided in January of this year,
    the Illinois Supreme Court reversed
    the Board’s adoption of,
    among others, Rule 204(a) (1) and remanded
    it for further consideration.
    However, because Rule 204(a) (1)
    was
    fully in force at the time of the Agency’s denial of the City’s appli-
    cation,
    the denial may be and
    is hereby upheld on the basis of that
    rule.
    The Board finds that the City of Springfield has acted in
    good faith.
    The City has submitted two applications for a construc-
    tion permit.
    It excluded S02 control equipment from those applications
    due to a sincere uncertainty as to the status of the SO2 regulations.
    Furthermore, the City, prior to the
    filing of the complaint in this
    matter, began to research a plan for complying with Rule
    204(a) (1)
    (R.
    1252—4).
    Therefore,
    the Board finds that the City’s good faith
    behavior mitigates against assessing a penalty
    in this case.
    Further-
    more,
    the Board recognizes that scarce municipal funds should be pre-
    served for corporate purposes.
    EPA v. City of Silvis,
    5 PCB 205.
    The
    City of Springfield will not be assessed a penalty for the violation
    of Rule 103(a)
    found herein.
    This Opinion represents the findings of fact and conclusions of
    law of the Board in this matter.
    20—345

    —8—
    ORDER
    It
    is the Order of the Pollution Control Board that:
    1.
    The City of Springfield is
    found to have allowed con-
    struction toward erection of a coal—fired generating
    unit,
    known as Dailman Unit
    3,
    since December 17,
    1974,
    without an Agency
    issued construction permit,
    in
    violation of Rule
    103(a) (1)
    of Chapter
    2.
    2.
    The City shall apply for and obtain a construction
    permit from the Illinois Environmental Protection
    Agency within 120 days of the date of this Order.
    3.
    The City of Springfield’s appeal from denial of its con-
    struction permit application is hereby dismissed.
    IT IS SO ORDERED.
    Mr. Young abstained.
    I,
    Christan
    L. Moffett, Clerk of the Illinois Pollution Control
    Board, h reby certify the abo e Opinion and Order were adopted on
    the
    day of
    ,
    1976 by a vote of___________
    Christan L.
    offetf
    erk
    Illinois Pollution
    rol Board

    Back to top