ILLINOIS POLLUTION CONTROL BOARD
    March 11,
    1976
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Complainant,
    v.
    )
    PCB 75—290
    SCOPE PRODUCTS,
    INC., DEXT
    )
    COMPANY DIVISION, a California
    )
    corporation,
    Respondent.
    MR. JAMES L. DOBROVOLNY, Assistant Attorney General, appeared on
    behalf of Complainant;
    MR. JOHN D.
    DONLEVY, appeared on behalf of Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Nr. Dumelle):
    This case comes before the Board on a Complaint filed by the
    Environmental Protection Agency
    (Agency) on July 25,
    1975.
    The
    Complaint alleges that Respondent has violated Section 9(b)
    of
    the Environmental Protection Act
    (Act)
    and Rule 103 (b)
    (2)
    of
    the Board’s Air Pollution Control Regulations.
    A hearing was
    held on November
    20,
    1975 at which six stipulations of fact
    were entered into
    (R.
    5), and 33 Exhibits were entered into
    evidence
    (R.8).
    Respondent,
    Scope Products, Inc., Dext Company Division,
    owns and operates a facility, which processes surplus food
    materials into granule material which is used as an ingredient
    in animal feed.
    The facility consists
    in part of a rotary drier,
    a cyclone, and an aspirator and is located at 2300 West St. Paul
    Avenue, Chicago,
    Illinois.
    The aforementioned facility
    is a
    food and kindred products industry operation,
    and is capable of
    emitting certain solids,
    gases,
    odor, to the atmosphere.
    During its plant operations involving the specified equipment,
    from February
    1,
    1973 until the filing of the complaint on
    July 25,
    1975, Dext Company had possessed no Environmental Protection
    Agency
    (Agency)
    permits. Stipulations 1—6.
    (R.
    5,
    6)
    20—229

    —2—
    Respondent has admitted each and every fact necessary
    for this Board to find violations of the Act and Rule as alleged.
    However, Respondent raises a defense
    to such finding:
    an alleged
    immunity implied from a prior settlement.
    This defense was raised
    at page
    2 of the transcript of the November 20,
    1975 hearing,
    page
    2 of Respondent’s Brief, and page
    3 of Respondent’s Reply
    to the Agency’s Brief
    (which did not discuss the issue).
    The basis of the defense raised by Respondent rests
    in
    a prior enforcement action, PCB 73-326.
    The Board Order in
    that case,
    issued on May 9,
    1974,
    accepted a settlement entered
    into by the Agency and Respondent.
    The Board there ordered
    Respondent, among other things,
    to obtain all necessary State
    permits for the operation of Respondent’s plant
    (Exhibit 30,
    pp.
    30—33).
    However, Respondent claims that a letter from the Attorney
    General during the settlement negotiations
    (Exhibit
    33,
    p.
    2)
    states an understanding that the money penalty provided for
    in
    the settlement was
    to cover operating permit violations.
    The
    Respondent characterizes this
    as a “prosecutorial commitment”,
    and cites a criminal case decided by the Supreme Court.
    However, by no stretch of the imagination can Exhibit 33 be
    read as
    a commitment.
    The letter is an express rejection of
    Respondent’s proposed settlement of October
    26,
    1973.
    The
    pertinent paragraph reads:
    “The Agency also feels that a monetary penalty is
    appropriate in this matter for violation of Section
    9(a) of the Act, as well as the failure of Dext to
    obtain permits for the operation of this facility”.
    This
    statement does not show any commitment as it is no more
    than correspondence submitted in the process of negotiating
    a settlement.
    The letter is not of sufficient weight to
    permit the Board to look beyond the four corners of the
    final settlement (Exhibit 30, pages
    3—8).
    Further,
    no violation of any permit requirements was either
    alleged in the Complaint in that case (Exhibit
    30, pages 9-14)
    or admitted in the final settlement
    (Exhibit 30, pages
    3-8).
    The absence of permits was not an issue in PCB 73—326 and was
    not included as
    an element of the settlement except to the extent
    that Respondent agreed to, and was ordered
    to, obtain
    “all necessary
    20—230

    —3—
    State permits...’~ Therefore,
    a finding of violation and the imposition
    of
    a civil penalty for the period of February,
    1973 to July 25,
    1975
    would not be contrary to the settlement adopted in PCB 73-326.
    Respondent next alleges that the approved settlement of
    PCB 73-326 implied that Dext was
    to have a reasonable time
    within which to secure an operating permit.
    Rule 103(b) (2)
    required Respondent to obtain an operating permit by February 1,
    1973.
    Thus,
    by the time of the issuance of the Order in
    PCB 73-326, Respondent had already had over 15 months to
    obtain the permits;
    which is not an unreasonable time.
    The permit
    violations were not an issue
    in PCB 73-326.
    The Board Order there
    requiring Respondent to obtain permits cannot be construed as
    an excusal of Respondent’s past failure to obtain permits, or
    the granting of immunity for as
    long as it took to obtain the
    permits.
    Had the Board wished to grant any immunity from permit
    requirements
    it would have done so expressly by ordering the permits
    to be obtained by a date certain.
    No
    “grace” period can be implied
    from ?CB 73-326.
    Even so, Respondent argues that an additional
    14
    months is not an unreasonable delay in obtaining a permit. Over
    29 months elapsed between the time by which Respondent was required
    to obtain a permit and the date of the instant Complaint.
    Respondent
    sees nothing unreasonable about this.
    Respondent further argues
    (Page
    4 of Respondent’s Brief)
    that its letter of March 17,
    1975
    (Exhibit 14)
    is a confirmation
    of a 30 day grace period granted by the Agency subsequent to
    Respondent’s receipt of Official Legal Notice of the Agency’s
    intent to prosecute Respondent
    (Exhibit 15).
    (R.
    61)
    Respondent
    has failed to show that this alleged 30 day period was anything
    more than the Agency giving Respondent one last chance to submit
    the required information prior to referral of the matter to the
    Attorney General for action.
    In no way could this action be found
    to have been a grant of immunity for the alleged 30 day period.
    Respondent states:
    “It is significant that the July 30
    letter was mailed by Dext only five days after this cause was
    filed.”
    Frankly, the Board fails
    to find any significance
    in this fact except in that it is
    a firm statement that
    Respondent had not complied with the Agency’s requests for
    information prior to the filing of this Complaint.
    Respondent also argues that 14 months after the Order
    in PCB 73-363 was not an unreasonable delay given the complex
    nature of the data requested.
    Several facts quickly dispose
    of that argument.
    Mr. Reardanz,
    the man who had complete charge
    of Respondent’s facility
    (R.
    10) has had no engineering
    training
    (R.
    54).
    However, in spite of the technical nature
    of the forms
    (R.
    55) and the fact that he found the forms
    confusing
    (R.
    26,
    28,
    33,
    40,
    55), Mr. Reardanz was the only
    one authorized by Dext Company to work on the applications
    20—231

    —4—
    (R.
    33,
    34,
    49).
    Mr. Reardanz did not seek outside engineering
    help from a professional engineer
    (R.
    55).
    As the Board finds
    that the cost of obtaining outside help qualified to do this
    work would not have been prohibitive, the delay simply becomes
    unreasonable.
    Even if Mr. Reardanz did make an honest effort
    to comply, it is clear that Respondent Dext Company did not
    provide him with the resources necessary to get the job done.
    The Board finds that the reasons for delay given by Mr. Reardanz
    are simply not persuasive when weighed against the unreasonable
    amount of time involved.
    Thus, while the degree of actual environmental damage
    is small,
    it must be remembered that the permit program is the core
    of the environmental program.
    As such,
    any permit violation poses
    a significant interference with the protection of the general welfare
    of the people of Illinois.
    Respondent has no exceptional social
    and economic value and
    is not unsuitable to the area in which it is
    located.
    However,
    the Board finds that the ease by which Respondent
    could have, with an earnest effort, obtained and submitted the
    required information makes the violation and extraordinary delay
    unreasonable.
    A substantial penalty
    is appropriate here to protect the
    integrity of the permit program.
    It will show both this
    Respondent and other potential violators that the permit require-
    ment is to be taken seriously.
    In this case,
    14 months of the
    29 month-long period of violation passed subsequent to PCB 73-326
    in which the Board ordered Respondent to obtain the permits.
    The
    information necessary to complete the permit application was not
    submitted until after the filing of this Complaint.
    Even though
    there is evidence that the permit has now been granted this
    was in no way caused by any diligent effort on Respondent’s
    part.
    The Board will therefore direct Respondent to pay a penalty
    of $1,500.00.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law.
    ORDER
    1.
    Respondent,
    Scope Products,
    Inc. Dext Company Division,
    is hereby found to have violated Section 9(b)
    of the Environmental
    Protection Act and Rule 103(b) (2)
    of the Board’s Air Pollution
    Control Regulations.
    20
    232

    —5—
    2.
    Respondent,
    Scope Products, Inc., Dext Company Division,
    shall pay,
    for the above violations the sum of $1,500.00 to the
    State of Illinois.
    Payment shall be made by certified check
    or money order within
    35 days of the date of this Order to:
    State of Illinois
    Fiscal Services Division
    Environmental Protection Agency
    2200 Churchill Road
    Springfield, Illinois
    62706
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order were adopted on the
    ‘~~_dayof
    March,
    1976 by a vote of
    ~-O
    IT IS
    SO ORDERED.
    Illinois Polluti
    Board
    20—233

    Back to top