ILLINOIS POLLUTION CONTROL BOARD
    March 11, 1976
    ENVIRONMENTAL PROTECTION AGENCY,
    Complainant,
    v.
    )
    PCB 74—208
    PETER COOPER CORPORATION,
    DIAMOND GLUE DIVISION,
    a Delaware corporation,
    Respondent.
    Ms.
    Kathryn
    Sheehan Nesburg,
    Attorney,
    appeared for the Complainant;
    Mr.
    Henry
    W.
    Sledz, Jr.,
    Attorney, appeared for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Zeitlin):
    This matter
    is before the Board on
    a Complaint filed by the
    Environmental Protection Agency
    (Agency) on June
    5,
    1974,
    alleging
    that Respondent Peter Cooper Corporation
    (Cooper) had operated an
    inedible rendering process
    so as to create odor emissions in violation
    of Section 9(a)
    of the Environmental Protection Act
    (Act)
    and Rule
    802(b)
    of Chapter
    2:
    Air Pollution, of the Pollution Control Board
    (Board)
    Rules and Regulations.
    The facility alleged to be in violation
    is
    Cooper’s Diamond Glue Division plant, located at 2930 South Robinson
    Avenue
    in Chicago,
    in a heavy industrial area of the city.
    The first two hearings in this matter were held in Chicago on
    October 15,
    1974, and May 16,
    1975.
    On June 19,
    1975,
    the parties
    entered a Joint Stipulation and Proposal for Settlement
    (Stipulation
    No.
    1), which was the subject of an Interim Order of the Board on
    July 24,
    1975.
    The Board’s July
    24, 1975 Interim Order rejected Stipulation
    No.
    1 for the following reasons:
    We reject the Stipulation entered into between
    the parties.
    In exchange for the payment of only
    $1,000 Respondent
    is
    in effect given a shield for
    possible violations extending over
    a five—year
    period.
    The record does not indicate the magnitude
    of the interference experienced by residents and
    others who found it necessary to be near Respondent’s
    plant.
    The compliance program is not specified
    in
    sufficient detail to insure that the public is
    adequately protected.
    We don’t know the extent of
    Respondent’s knowledge of its possible pollution
    source.
    No economic data are supplied on Peter
    Cooper’s financial situation.
    The cost of the newly
    constructed brick building is not known nor have
    possible costs of compliance been included in the
    record.
    In light of the record, we find the Stipulation
    unacceptable.
    20—195

    —2—
    The
    Board’s
    July 24,
    1975 Interim Order also details the
    procedural history of this case through that date, the specific
    operations carried on at the Diamond Glue plant, and various efforts
    made by Peter
    Cooper
    to abate the odor problems which were the subject
    of the Agency’s Complaint.
    Those matters need not be repeated here.
    A third hearing was held in Chicago on
    Jan.
    19, 1976.
    The
    parties then entered a new Stipulation and Proposal for Settlement
    (Stipulation No. 2), which was submitted to the Board in signed form
    on February 17, 1976.
    At the January 19,
    1976 hearing the parties
    detailed those changes in Stipulation No. 2 which were made in an
    attempt to correct the deficiencies which the Board found in Stipulation
    No.
    1.
    Inasmuch as the Board’s July 24, 1975 Interim Order rejecting
    Stipulation No.
    1 adequately sn~n~narizes
    that
    first stipulation, we
    shall follow the parties’ lead
    and
    discuss here only those differences,
    as they relate to the acceptability of stipulation No.
    2.
    1.
    The Board’s first objection was that, for a penalty of
    $1,000, Respondent would have been given a shield from enforcement
    for a possible violation extending over a five-year period.
    In
    Stipulation No.
    2, the penalty provision is increased to $1,500, and
    the Agency has dropped all allegation of violation during the period
    July
    1,
    1970 until January 8, 1973, the latter date being the
    time
    of
    the Agency’s first inspection of Respondent’s plant.
    2.
    To answer the Board’s second objection, the record’s failure
    to indicate the magnitude of interference experienced by residents and
    others as a result of odors from Respondent’s plant, Stipulation No. 2
    now
    includes several complaint forms filled out by citizens regarding
    the effects of the odors upon them.
    Those complaint forms
    (Ex. A-L),
    indicate that the degree of interference was indeed significant.
    3.
    The Board’s third objection to Stipulation No. 1 was a
    lack of specificity in the compliance progrcm, needed to insure that
    the public would be adequate?y protected in the stipulated settlement.
    The
    parties have added new material (paragraphs 14 through 19 of
    Stipulation No.
    2) describing in detail the compliance program.
    In essence,
    the compliance program in this enforcement case is
    entirely contingent.
    Cooper has already constructed
    (as noted in
    our
    earlier Interim Opinion) a brick building to enclose the ~tankage,N
    which had previously been stored outdoors, and which
    both
    parties
    agree was the source of the odors in question.
    Although Cooper
    apparently believes that use of this building will be sufficient to
    abate the odor problem, the iqency will nonetheless conduct a 3-month
    investigation, after which the
    Agency may
    require that Cooper install
    either an afterburner or a
    wet
    scrubber to control any odors which
    still escape.
    During the 3-month investigation period, Cooper will
    20—las

    —3—
    prepare construction permits
    for submission to the Agency should a
    construction program for the afterburner or wet scrubber be necessary,
    and will,
    if additional time for the construction program is indeed
    necessary,
    apply
    to the Board for a Variance during such construction.
    Cooper will submit
    a
    $5,000 performance bond to cover the eventuality
    that such construction will be required.
    4.
    To answer the Board’s fourth question, concerning the actual
    source of the odors from Cooper’s facility, both parties have agreed
    that the handling of tankage
    is
    (or was)
    the source.
    5.
    The Board’s objection concerning
    a lack of knowledge of
    cooper’s financial siutation
    is answered by stipulation to the fact
    that Cooper could and can afford any control technology likely to be
    necessary.
    6.
    The Board’s statement that the cost of the brick building
    constructed by Cooper was not shown in Stipulation No.
    1
    is now
    corrected in Stipulation No.
    2,
    to show a cost of $19,500.
    The cost
    of any future controls is given at $10,000,
    (R.6,
    January 19,
    1976
    hearing).
    In light of the additional information submitted by the parties,
    the Board finds that the settlement now before it is adequate.
    While
    the penalty remains low, Stipulation No.
    2 indicates that the settle-
    ment approved here will serve to abate the problems which have existed,
    if they
    have not
    in fact aireddy been abated.
    In addition,
    the parties
    have shown in mitigation that Cooper has expended considerable sums
    over the last several years
    in an attempt to abate the problem.
    Only two
    issues remain:
    The parties did not,
    in Stipulation No.
    2,
    agree whether,
    (1) Cooper’s Diamond Glue facility
    is
    in
    fact an inedible
    rendering plant, or
    (2) whether there was
    in fact sufficient odor from
    Cooper’s plant to constitute violations of the Act and our Regulations.
    First,
    there can be no c2oubt that the process described in both
    Stipulation Nos.
    1 and
    2,
    at Cooper’s Chicago facility,
    is in fact an
    inedible rendering process.
    Cooper’s process fits squarely within the
    definition given in Rule 801.
    Second,
    the parties did not agree
    in Stipulation No.
    2 as to
    the presence or absence of violation,
    (e.g., paragraphs
    9,
    13).
    In
    light of the matters submitted in Stipulation No.
    2 on the issues of
    interference with individuals, economic and technical reasonableness
    of eliminating odors, and the duration of the problem
    (see,
    e.g.,
    Ex.
    A-L),
    we have no difficuJty finding a violation of Section
    9(a)
    of the Act.
    Based on our finding that Cooper’s facility
    is an inedible
    rendering process, we also find a violation of Rule 802(b).
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board
    in this matter.
    20—197

    —4—
    ORDER
    IT
    IS
    THE
    ORDER
    OF
    THE
    POLLUTION
    CONTROL
    BOARD
    Lhat:
    1.
    Respondent
    Peter
    Cooper
    Corporation,
    I)iamond
    Glue
    Division,
    a
    Delaware
    corporation,
    is
    found
    to
    have
    operated
    an
    inedible
    rendering
    process
    in
    Chicago,
    Illinois,
    in
    violation
    of
    Section
    9(a)
    of
    the
    Environ-
    mental
    Protection
    Act
    and
    Rule
    802(b)
    of
    Chapter
    2:
    Air
    Pollution
    of
    the
    Pollution
    Control
    Board’s
    Rules
    and
    Regulations.
    2.
    Respondent
    shall
    pay
    as
    a
    penalty
    for
    the
    aforesaid
    violations
    the
    sum
    of
    Fifteen
    Hundred Dollars
    ($1,500.00), payment to be made within thirty
    (30)
    days
    of
    the
    date
    of
    this
    Order
    by
    certified
    check
    or
    money
    order
    to:
    Environmental
    Protection
    Agency
    Fiscal
    Services
    Division
    2200
    Churchill
    Road
    Springfield,
    Illinois
    62706
    3.
    Complainant
    Environmental Protection Agency
    and Respondent Peter Cooper Corporation shall comply
    with all provisions of the
    “terms of
    settlements’ of
    the Stipulation and Proposal for Settlement
    in this
    matter filed on February 17,
    1976.
    4.
    To assure any further construction which
    may be required under such terms
    of settlement,
    Respondent shall post
    a performance bond
    in the
    amount of Five Thousand Dollars
    ($5,000.00),
    in a
    form acceptable to the Environmental Protection
    Agency,
    such bond to be submitted to:
    Environmental Protection Agency
    Control Program Coordinator
    Division of Air Pollution Control
    2200 Churchill Road
    Springfield,
    Illinois
    62706
    Mr.
    Dumnelle concurred.
    I,
    Christan L.
    Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the
    bove Opinion and Order were
    adopted on the
    ~
    day of
    -
    ,
    1976,
    by
    a vote of
    4/p
    Illinois Pollution
    ~trol Board
    ~n—198

    Back to top