ILLINOIS POLLUTION CONTROL BOARD
February
26, 1976
RICHARD
D. MILLER,
)
Petitioner,
)
v.
)
PCB 76—46
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
ORDER OF THE
BOARD
(by Mr. Dumelle):
Petition filed February
18,
1976 is inadequate in that no
information
is given as to the present effects upon the receiving
stream of the discharge from the South Addison sewage treatment
plant.
Data should be presented as to dissolved oxygen levels;
bottom deposits,
if any;
coliform levels; algae growth; unbalanced
benthic populations,
if any; etc.
The Petition shall be amended within 30 days of the date of this
order by providing the above listed information.
A waiver shall be
filed at the same time to make the 90-day decision period set by statute
run from the date of filing of the Amended Petition.
Failure to timely
file the Amended Petition shall make the Petition liable
to
dismissal
for inadequacy.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Po1lution~ontrol
Board, hereby certify the above Order was adopted on the
~_day
of February,
1976 by a vote of
~O
Illinois Pollution
rol Board
20—185