    Petition filed February
    18,
    1976 is inadequate in that no
    information
    is given as to the present effects upon the receiving
    stream of the discharge from the South Addison sewage treatment
    plant.
    Data should be presented as to dissolved oxygen levels;
    bottom deposits,
    if any;
    coliform levels; algae growth; unbalanced
    benthic populations,
    if any; etc.
    The Petition shall be amended within 30 days of the date of this
    order by providing the above listed information.
    A waiver shall be
    filed at the same time to make the 90-day decision period set by statute
    run from the date of filing of the Amended Petition.
    Failure to timely
    file the Amended Petition shall make the Petition liable
    to
    dismissal
    for inadequacy.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Po1lution~ontrol
    Board, hereby certify the above Order was adopted on the
    ~_day
    of February,
    1976 by a vote of
    ~O
    Illinois Pollution
    rol Board
    20—185

    Back to top