ILLINOIS POLLUION CONTROL BOARD
    February 26, 1976
    CPC INTERNATIONAL, INC.
    Petitioner,
    v.
    )
    PCB 75—176
    ENVIRONMENTAL PROTECTION
    )
    AGENCY,
    Respondent.
    ORDER OF THE BOARD (by Mr. Goodman):
    CPC International, Inc. seeks variance from the particulate
    emission standard of Rule 203(g) (1) and compliance date of Rule
    203(1) (4) (Chapter 2) for a coal-fired steam generator at its Pekin,
    Illinois corn wet milling plant. In the case of Commonwealth Edison
    Company v. Pollution Control Board, the Illinois Supreme Court re-
    versed and remanded the Board’s adoption of Rule 203(g) (1). Rule
    203(i) (4) is meaningful only in conjunction with Rule 203(g). A
    request for variance from the above—cited specific rules is, there-
    fore, inappropriate at the present time. The petition for variance
    is hereby dismissed without prejudice.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, ~er by certify the above Order was ad2pted on the____________
    day of...~’
    ,
    1976 by a vote of ~p
    *
    Illinois Pollutio ntrol Board
    20—157