ILLINOIS POLLUTION CONTROL BOARD
    May 20,
    1976
    OBEAR-NESTER GLASS CO.,
    )
    Petitioner,
    V.
    )
    PCB 76—67
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Zeitlin):
    This case concerns a Variance Petition submitted to the Board
    on March
    4,
    1976 by Petitioner Obear-Nester Glass Company (Obear-
    Nester),
    a division of Indian Head,
    Inc.
    The Petition seeks relief
    for a period of
    cine year from the noise pollution limitations
    in
    Rule 202 of Chapter
    8:
    Noise Pollution,
    of the Board’s Rules and
    Regulations.
    A Recommendation was received from the Environmental
    Protection Agency
    (Agency) on April 21,
    1976.
    No hearing was held
    in the matter.
    Obear-Nester’s Lincoln,
    Illinois plant manufactures glass
    containers for the food and beverage industries on a round-the-clock
    basis.
    As a part of the manufacturing operation it is necessary
    to use both compressed air and high-velocity cooling air.
    To provide
    such air, four Buffalo industrial exhauster fans are used, each with
    a capacity of 20,000 CFM and 22-1/2 inches of water column static
    pressure at 70°F.
    These fans are the noise sources for which a
    Variance
    is sought.
    Attached to Obear-Nester’s Petition were the results of Agency
    noise monitoring tests indicating that Obear-Nester had a significant
    noise problem at its Lincoln plant.
    Taken on November
    7,
    1975,
    the
    noise tests indicated that various continuous sources of noise at
    the Lincoln plant caused violation of the Rule 202 daytime limits
    for noise passing from Class C to Class A land at all but one of the
    pertinent octave band center frequencies.
    In addition,
    the Lincoln
    plant had serious problems with impulsive noise from its truck
    loading docks and the dumping of cullet
    (rejected glass containers)
    with a front-end loader.
    Since the time of those tests, Obear—Nester has taken several
    steps
    to alleviate the noise problems
    --
    noise barriers have been
    erected to control noise from various fans and other sources; dock
    plates used as bridges between the plant’s loading dock and adjacent
    trucks have been redesigned to include rubber pads below the plates;
    self-dumping hoppers with forklift trucks have replaced the use of
    front—end loaders for cullet dumping.
    These improvements were all
    scheduled to be completed by April
    1,
    1976.
    21 —479

    —2—
    Obear-Nester has not, however, controlled the noise emissions
    from the four fans which are the subject of this Variance.
    Obear-
    Nester states in its Petition that the design of any noise barrier
    for use with those fans
    is very important,
    and must be such that
    it does not interfere with the volume and pressure of air required
    for those fans.
    The company feels that a one—year periodis neces-
    sary for the design and construction of the necessary abatement
    device.
    The Agency’s Recommendation agrees that
    a Variance is warranted
    in this case.
    The Agency notes that Obear—Nester has taken signifi-
    cant steps during 1975 and 1976 to prevent noise pollution.
    The
    Agency also feels that the steps taken and proposed by Obear-Nester
    will be effective.
    With regard to the effect of a Variance grant, the Agency inter-
    viewed various residents adjacent to the Obear-Nester plant.
    Although
    some opposed the grant of the Variance, most agreed that it should
    be granted, especially if compliance would result by the end of the
    period,
    (Rec.
    Ex.
    4-13).
    Although the Agency did not agree that no
    injury would result from the grant of the Variance
    (Rec.
    Ex.
    15,
    p.
    4), the Agency did agree that there would be no physical injury
    in the sense of hearing loss,
    (Rec.
    Ex.
    16,
    p.
    1).
    The Agency also
    felt that the adverse effects of the grant would be found in nuisance,
    interference with speech, etc.,
    (Rec.
    Ex.
    16, 16);
    in combination
    with ambient noise levels as high as 30-40 dB(A), Obear—Nester’s
    operation could result
    in noise levels as much as 24 dB(A)
    higher
    than the day or night noise limitations,
    (id).
    However,
    the Agency
    also felt that the actions already taken to reduce other noise
    emissions from the plant would attentuate these high noise levels.
    The Agency also agrees with Petitioner that the failure to
    obtain the Variance would impose
    a severe hardship.
    While the cost
    of compliance with the pertinent Regulations would not be too great,
    (approximately $5,000 to $10,000),
    the fans for which the Variance
    is sought must operate properly for the plant to continue operation.
    A hastily constructed barrier could easily cause operational inter-
    ference.
    Obear—Nester has, the Agency feels, proposed a reasonable
    time for the planning and construction of abatement methods that
    will not interfere with the continued operation of the fans, but
    which will provide for complete compliance.
    Weighing the likelihood of environmental damage against the
    hardship pleaded by Petitioner,
    we agree with the Agency’s Recom-
    mendation and with the qualifications on
    it.
    As conditions,
    the
    Agency recommends that we impose
    a more detailed compliance schedule
    than proposed in the Petition; that we require the submittal of
    comprehensive reports on the compliance steps taken to date,
    and
    on the progress of its compliance program under the Variance.
    A
    standard certificate of compliance will be required,
    along with a
    performance bond of $10,000.
    21—480

    —3--
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board in this matter.
    ORDER
    IT IS THE ORDER OF
    THE
    POLLUTION CONTROL
    BOARD
    that Petitioner
    Obear—Nester Co. be granted a Variance from Rule 202 of Chapter
    8:
    Noise Pollution,
    for its Lincoln,
    Illinois glass container manufac-
    turing facility’s four
    (4) Buffalo industrial exhauster fans, more
    fully described in the foregoing Opinion, for a period of one year
    from March
    1,
    1976 until March
    1,
    1977, subject to the following
    conditions:
    1.
    To assure the completion of the work required under this
    Variance, Petitioner shall submit,
    in
    a form acceptable to the
    Environmental Protection Agency,
    a performance bond in the amount
    of Ten Thousand Dollars
    ($10,000.00).
    Said bond shall be submitted
    within thirty
    (30) days of the date of this Order to:
    Environmental Protection Agency
    Control Program Coordinator
    Division of Noise Pollution Control
    2200 Churchill Road
    Springfield,
    Illinois
    62706
    2.
    Noise or sounds emitted by the fans in question shall
    not be increased in intensity during the term of this Variance,
    so
    as to exceed the measurements taken by the Environmental Protection
    ~gency on November 7, 1975.
    3.
    Petitioner shall conform to the following schedule for
    the attainment of compliance by the subject fans:
    a.
    By May 1,
    1976:
    Employ the services of
    a noise consultant,
    person or firm under such con-
    tractual conditions as to require said consultant(s)
    to prepare a recommendation and conceptual plans for
    noise abatement by August 15,
    1976, and to prepare
    detailed plans and specifications within forty-five
    days of being notified to do so by said Petitioner
    upon Petitioner’s selection of one or more of the
    recommendations by said consultant.
    21— 481

    —4—
    b.
    By September
    1,
    1976:
    Choose one or more
    of the methods proposed and direct consultant(s)
    to
    submit detailed plans and specifications for noise
    abatement within forty-five days.
    c.
    By November
    1,
    1976:
    Order all materials
    not presently on hand required by said detailed plans
    and specifications and contract for all specialized
    work not within the capabilities of Petitioner.
    d.
    By December 1, 1976:
    Commence construction.
    e.
    By January 15,
    1977:
    Complete construction.
    f.
    By February 1, 1977:
    Complete noise testing
    and such re-working as is required.
    g.
    By March 1, 1977:
    Achieve compliance with
    Rule 202.
    4.
    Petitioner shall submit written progress reports to the
    Environmental Protection Agency within ten
    (10) days of each of the
    dates specified
    in Paragraph
    3 above.
    5.
    Petitioner shall secure all applicable permits from the
    Environmental Protection Agency.
    6.
    Petitioner shall report to the Agency within ten days of
    the Order herein as to the effectiveness of
    (a)
    the forklift and
    self-dumping Roura Hopper, which will be used to collect and trans-
    port cullet
    (rejected glass containers);
    (b)
    its loading dock noise
    abatement program;
    and
    (c)
    its program to abate noise from other
    sources by erecting barriers.
    7.
    Sounds emitted by
    all sources
    at Petitioner’s Lincoln,
    Illinois plant, other than said fans,
    shall at all times conform
    with Part 2,
    Chapter
    8 of the Board’s Rules and Regulations.
    8.
    Petitioner shall execute and forward to the Illinois
    Environmental Protection Agency, Division of Noise Pollution Control,
    Enforcement Section, 2200 Churchill Road, Springfield, Illinois 62706,
    within twenty-eight
    (28) days after the date of the Board Order
    herein,
    a Certificate of Acceptance and Agreement to be bound to
    all the terms and conditions of the Variance, the form of said
    Certification to be as follows:
    21 —482

    —5—
    I,
    (We),
    _________________________
    having read
    the Order of the Illinois Pollution Control Board
    in case No.
    PCB 76-67, understand and accept said
    Order, realizing that such acceptance renders all
    terms and conditions thereto binding and enforceable.
    SIGNED
    TITLE
    DATE
    I, Christan L. Moffett,
    Clerk of the Illinois Pollution
    Control Board, her~bycertify the above Opinion and Order we e
    adopted on the
    ~p
    ~‘day of
    1976,
    by a vote of
    —O
    ~JLUt1Ofl
    Co
    1
    Board
    21
    483

    Back to top