ILLINOIS POLLUTION CONTROL BOARD
May 20,
1976
OBEAR-NESTER GLASS CO.,
)
Petitioner,
V.
)
PCB 76—67
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Zeitlin):
This case concerns a Variance Petition submitted to the Board
on March
4,
1976 by Petitioner Obear-Nester Glass Company (Obear-
Nester),
a division of Indian Head,
Inc.
The Petition seeks relief
for a period of
cine year from the noise pollution limitations
in
Rule 202 of Chapter
8:
Noise Pollution,
of the Board’s Rules and
Regulations.
A Recommendation was received from the Environmental
Protection Agency
(Agency) on April 21,
1976.
No hearing was held
in the matter.
Obear-Nester’s Lincoln,
Illinois plant manufactures glass
containers for the food and beverage industries on a round-the-clock
basis.
As a part of the manufacturing operation it is necessary
to use both compressed air and high-velocity cooling air.
To provide
such air, four Buffalo industrial exhauster fans are used, each with
a capacity of 20,000 CFM and 22-1/2 inches of water column static
pressure at 70°F.
These fans are the noise sources for which a
Variance
is sought.
Attached to Obear-Nester’s Petition were the results of Agency
noise monitoring tests indicating that Obear-Nester had a significant
noise problem at its Lincoln plant.
Taken on November
7,
1975,
the
noise tests indicated that various continuous sources of noise at
the Lincoln plant caused violation of the Rule 202 daytime limits
for noise passing from Class C to Class A land at all but one of the
pertinent octave band center frequencies.
In addition,
the Lincoln
plant had serious problems with impulsive noise from its truck
loading docks and the dumping of cullet
(rejected glass containers)
with a front-end loader.
Since the time of those tests, Obear—Nester has taken several
steps
to alleviate the noise problems
--
noise barriers have been
erected to control noise from various fans and other sources; dock
plates used as bridges between the plant’s loading dock and adjacent
trucks have been redesigned to include rubber pads below the plates;
self-dumping hoppers with forklift trucks have replaced the use of
front—end loaders for cullet dumping.
These improvements were all
scheduled to be completed by April
1,
1976.
21 —479
—2—
Obear-Nester has not, however, controlled the noise emissions
from the four fans which are the subject of this Variance.
Obear-
Nester states in its Petition that the design of any noise barrier
for use with those fans
is very important,
and must be such that
it does not interfere with the volume and pressure of air required
for those fans.
The company feels that a one—year periodis neces-
sary for the design and construction of the necessary abatement
device.
The Agency’s Recommendation agrees that
a Variance is warranted
in this case.
The Agency notes that Obear—Nester has taken signifi-
cant steps during 1975 and 1976 to prevent noise pollution.
The
Agency also feels that the steps taken and proposed by Obear-Nester
will be effective.
With regard to the effect of a Variance grant, the Agency inter-
viewed various residents adjacent to the Obear-Nester plant.
Although
some opposed the grant of the Variance, most agreed that it should
be granted, especially if compliance would result by the end of the
period,
(Rec.
Ex.
4-13).
Although the Agency did not agree that no
injury would result from the grant of the Variance
(Rec.
Ex.
15,
p.
4), the Agency did agree that there would be no physical injury
in the sense of hearing loss,
(Rec.
Ex.
16,
p.
1).
The Agency also
felt that the adverse effects of the grant would be found in nuisance,
interference with speech, etc.,
(Rec.
Ex.
16, 16);
in combination
with ambient noise levels as high as 30-40 dB(A), Obear—Nester’s
operation could result
in noise levels as much as 24 dB(A)
higher
than the day or night noise limitations,
(id).
However,
the Agency
also felt that the actions already taken to reduce other noise
emissions from the plant would attentuate these high noise levels.
The Agency also agrees with Petitioner that the failure to
obtain the Variance would impose
a severe hardship.
While the cost
of compliance with the pertinent Regulations would not be too great,
(approximately $5,000 to $10,000),
the fans for which the Variance
is sought must operate properly for the plant to continue operation.
A hastily constructed barrier could easily cause operational inter-
ference.
Obear—Nester has, the Agency feels, proposed a reasonable
time for the planning and construction of abatement methods that
will not interfere with the continued operation of the fans, but
which will provide for complete compliance.
Weighing the likelihood of environmental damage against the
hardship pleaded by Petitioner,
we agree with the Agency’s Recom-
mendation and with the qualifications on
it.
As conditions,
the
Agency recommends that we impose
a more detailed compliance schedule
than proposed in the Petition; that we require the submittal of
comprehensive reports on the compliance steps taken to date,
and
on the progress of its compliance program under the Variance.
A
standard certificate of compliance will be required,
along with a
performance bond of $10,000.
21—480
—3--
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter.
ORDER
IT IS THE ORDER OF
THE
POLLUTION CONTROL
BOARD
that Petitioner
Obear—Nester Co. be granted a Variance from Rule 202 of Chapter
8:
Noise Pollution,
for its Lincoln,
Illinois glass container manufac-
turing facility’s four
(4) Buffalo industrial exhauster fans, more
fully described in the foregoing Opinion, for a period of one year
from March
1,
1976 until March
1,
1977, subject to the following
conditions:
1.
To assure the completion of the work required under this
Variance, Petitioner shall submit,
in
a form acceptable to the
Environmental Protection Agency,
a performance bond in the amount
of Ten Thousand Dollars
($10,000.00).
Said bond shall be submitted
within thirty
(30) days of the date of this Order to:
Environmental Protection Agency
Control Program Coordinator
Division of Noise Pollution Control
2200 Churchill Road
Springfield,
Illinois
62706
2.
Noise or sounds emitted by the fans in question shall
not be increased in intensity during the term of this Variance,
so
as to exceed the measurements taken by the Environmental Protection
~gency on November 7, 1975.
3.
Petitioner shall conform to the following schedule for
the attainment of compliance by the subject fans:
a.
By May 1,
1976:
Employ the services of
a noise consultant,
person or firm under such con-
tractual conditions as to require said consultant(s)
to prepare a recommendation and conceptual plans for
noise abatement by August 15,
1976, and to prepare
detailed plans and specifications within forty-five
days of being notified to do so by said Petitioner
upon Petitioner’s selection of one or more of the
recommendations by said consultant.
21— 481
—4—
b.
By September
1,
1976:
Choose one or more
of the methods proposed and direct consultant(s)
to
submit detailed plans and specifications for noise
abatement within forty-five days.
c.
By November
1,
1976:
Order all materials
not presently on hand required by said detailed plans
and specifications and contract for all specialized
work not within the capabilities of Petitioner.
d.
By December 1, 1976:
Commence construction.
e.
By January 15,
1977:
Complete construction.
f.
By February 1, 1977:
Complete noise testing
and such re-working as is required.
g.
By March 1, 1977:
Achieve compliance with
Rule 202.
4.
Petitioner shall submit written progress reports to the
Environmental Protection Agency within ten
(10) days of each of the
dates specified
in Paragraph
3 above.
5.
Petitioner shall secure all applicable permits from the
Environmental Protection Agency.
6.
Petitioner shall report to the Agency within ten days of
the Order herein as to the effectiveness of
(a)
the forklift and
self-dumping Roura Hopper, which will be used to collect and trans-
port cullet
(rejected glass containers);
(b)
its loading dock noise
abatement program;
and
(c)
its program to abate noise from other
sources by erecting barriers.
7.
Sounds emitted by
all sources
at Petitioner’s Lincoln,
Illinois plant, other than said fans,
shall at all times conform
with Part 2,
Chapter
8 of the Board’s Rules and Regulations.
8.
Petitioner shall execute and forward to the Illinois
Environmental Protection Agency, Division of Noise Pollution Control,
Enforcement Section, 2200 Churchill Road, Springfield, Illinois 62706,
within twenty-eight
(28) days after the date of the Board Order
herein,
a Certificate of Acceptance and Agreement to be bound to
all the terms and conditions of the Variance, the form of said
Certification to be as follows:
21 —482
—5—
I,
(We),
_________________________
having read
the Order of the Illinois Pollution Control Board
in case No.
PCB 76-67, understand and accept said
Order, realizing that such acceptance renders all
terms and conditions thereto binding and enforceable.
SIGNED
TITLE
DATE
I, Christan L. Moffett,
Clerk of the Illinois Pollution
Control Board, her~bycertify the above Opinion and Order we e
adopted on the
~p
~‘day of
1976,
by a vote of
—O
~JLUt1Ofl
Co
1
Board
21
—
483