ILLINOIS POLLUTION CONTROL BOARD
May
6
,
1976
VILLAGE OF SENECA,
V.
Petitioner,
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
ORDER OF THE BOARD
(by Mr. Young):
)
)
)
)
)
)
)
PCB 76—118
On April
27,
1976 Petitioner filed a petition for variance
with the Board.
The petition is inadequate
in that it fails
to comply with the requirements of our Procedural Rule 401.
It
is the Order of the Board that Petitioner shall amend
its petition within 45 days of this Order.
Petitioner is directed
to supply information, including, but not limited to the following
data:
the average dry weather flow of the treatment plant,
the
designed dry weather flow of the treatment plant, the maximum
hydraulic capacity of the treatment plant,
the BOD and Suspended
Solids concentration of the effluent and of the receiving stream.
Failure to timely file an amended petition shall cause the
petition to be denied without prejudice for inadequacy.
The
90-
day decision period set by Section 38 of the Environmental Pro-
tection Act shall run from the date of the filing of the amended
petition.
IT IS SO ORDERED.
I, Christan L.
Moffett, Clerk of the Illinois Pollution
Control Board,
hereby certify the above Order was adopted on
the
_______
day of
_____________________,
1976 by a vote
Illinois Pollution C
ol Board
21
—391