ILLINOIS POLLUTION CONTROL BOARD
February
3,
1977
NORTH SHORE
SIH1ITJ\R~
DISTRICT,
)
Petitioner,
v.
)
PCB 76—285
ENVIRONMENTAL PROTECTION AGENCY,
Respondent,
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr.
ZeitLin~
This
matter
is
before
the
Board
on
a
Variance
Petition
filed
by
Petitioner
North
Shore
Sanitary
District
(NSSD)
on
November
9,
1976.
Respondent Environmental Protection Agency
(Agency)
filed
its Recorn-
mendation
on January
3,
1977.
No hearing was held.
NSSD~sPetition
is the most recent in a lengthy series seeking
relief
for the area serviced by its Waukegan Sewage Treatment Plant
(STP)
from
a
“sewer ban” imposed
on NSSD by this Board some six
years ago.
League of Women Voters
v,
NSSD,
PCB 70-7,-12,-l3,-l4,
1 PCB 369
(March
31,
1971).
Paragraph
7 of our Order in League of
Women Voters provided that,
“The District shall not permit any additions
to
present sewer connections,
or new sewer connections,
to its facilities until the District can demonstrate
to the Board that it can adequately treat the wastes
from
those
new sources so as not to violate the
Envi ronmen
tn
1
Protc’rl—
ion
/\c
,
or t~h~
Rul
c’s
rind R~ju—
I
I
i
‘t(
)IM
I
~j
(
(i
t
I
it
‘r~
~
i it
-
in
NSSD
V.
EPA,
E~CB71-343,
3 PCB 541 (d~u~..~L, L972’~
Kended~
Order March
2,
1972,
3 PCB 697),
the Board allowed 13,333 Population
Equivalents
(PE)
for the Waukegan STP.
That Variance grant, based
on hardship to persons other than the District itself, was strictly
conditioned and continued a prohibition on connections upstream of
overloaded sewers.
See,
3 PCB at
552,
558;
3 PCB at
702.
The following year the Board extended
the
Variance granted
in
PCB
71-343
for
another
year,
inasmuch
as
only
180
additional
hook—up
permits
(1,460 PE)
for
connections
tributary
to the Waukegan STP
had been issued.
NSSDv._EPA,
PCB
72—451,
7 PCB
107
(Feb.
14,
1973)
24—701
The Board
found that although NSSD had not kept pace with the earlier
Orders with regard to Waukegan,
it was apparently trying
to do
so.
In addition,
the Board
noted
that
the
original
grant of 13,333 PE
had contemplated
a prolonged construction and hook—up period for
r~e~
housing under
the Variance.
Then
in PCB 73—502,
11 PCB 337
(Feb.
21,
1974)
,
the Board
granted an additional one year period for NSSD to use the 13,333
allotted
PE,
Expansion of the Waukegan STP was by then apparently
in progress,
and the Board found on the record there
that NSSD
would probably be able
to meet applicable discharge limitations
upon completion of the additional
facilities.
Again
in 1975,
in PCB
74—344,
15
PCB
197
(Jan.
9,
1975)
,
the
Board continued the Variance, hut cut
the
remaining
PE
connection
allowance from 8,653
PE
(left out of the original 13,333
PE)
to
2,000 PB.
The Board based its cut on the fact that Waukegan’s
continuing discharge to Lake Michigan was
in violation of both the
applicable Board Regulations and the prior Orders,
supra.
The
Board also stated that,
“
Un
wet weather,
the Waukecjan plant may
already now be exceeding
its design capacity.”
15 PCB at 198.
Hydraulic loading and capacity
(along with effluent quality)
were again central
issues in the most recent Variance covering the
Waukeqan STP and our sewer ban in League of Women Voters.
In that
case, PCB 75—301,
19
PCB
589
(Jan.
8,
1976)
,
NSSD
requested
a
lifting
of the general sewer ban
as
it
applied
to
Waukegan
or,
alternatively,
an additional authorization of 5,000 PE for connections tributary
to that plant.
The Board,
however,
found that the record did not
contain sufficient evidence to indicate that the sewer ban could be
lifted,
and instead granted
1,500
PE for the period ending
December
31,
1976,
Finally,
in
this
case,
NSSD
has
incorporated
the
records
of
all
of
the
above
cases,
and
has
asked
alternatively
for
the
following
various
forms
of
relief:
I
.
V
i
r
ii:;
P
i
I
It
,w
ii
I
(
i
I
111
in
I
~~
/~()
PI~,
(roinri
1 n
j11(J
omit
ci
I
lie
I
,
5(H)
PH
qrriuiLed
in FCB 75—301)
2.
Variance
extension
allowing
a
“a
greater
number
of
connections;”
or,
3.
Removalof
all
restrictions
on
connections
to
the
Waukegan
plant.
24
--
702
As the basis
for such relief, NSSD alleges that expansion of
the Waukegan plant will finally be completed in June of
1977.
By
that time,
NSSD claims, the plant effluent should have been diverted
frorr
Lake
Michigan to the Des Plaines River, and that effluent
should
meet Board
standards.
The Agency~sRecommendation
is that our Order in PCB 75-301 be
extended for one year
(to allow the remaining
790 PB
in connections)
and that the sewer ban be lifted with regard to Waukegan on June
30,
1977 or upon the completion of diversion and upgrading at Waukegan.
We had hoped
that this would be our last examination of the
sewer ban insofar as it bears on the Waukegan STP;
that is
unfortunately not the case,
We are left in the same position as
in
PCB 75-301:
There is simply not sufficient information available to
justify
lifting the ban.
First, we have not been shown that the
conditions which led to the sewer ban have been abated.
As far
as
the record now shows, Waukegan
is still discharging to Lake Michigan
an effluent which exceeds allowable standards.
(See,
e.g., NSSD
Report under PCB 75-301 of April 26,
1976,
referenced
at Petition,
p.
2;
Greeley and Hansen Report,
Id., of August
26,
1976.)
Second,
in
light
of the many past delays in construction at
Waulcegan,
we are not inclined to assume that any proposed date
is
firm;
in PCB 75-301,
completion of the plant was assumed by
November,
1976.
Third,
the same questions that were present in PCB 75-301 with
regard to plant flows and capacity are still present.
The Reports
cited above, by NSSD after various problems with regard to those
issues were aired at hearing, indicate that the design capacity of
19.9 MGD at Waukegan may have already been exceeded on a number of
occasions.
We simply cannot lift the ban until these issues have been
resolved.
While we do not particularly relish the prospect of yet
another round of adjudication with roqard
to the
Wrinkoqan
STP,
it
~
in:;
I
Ii
i
t
I
I
w
I
I
I
1)1
I
I i(
C(
I
~
,
ii
I
(‘(‘V(
it
ii
I
I
()
ii
e
r
i
I
I
I I
I
of
I he
ban
-
With
regard to the Agency~scontentions regarding
the Judge
Avenue sewer, we feel that the condition on
all
of the prior Variances,
prohibiting connection
to overloaded sewers,
will be sufficient.
If the Agency
is satisfied that the other sewers tributary
to the
Waukegan STP are adequate for additional loads,
our Order
in PCB 71-343
of January
31,
1972,
as subsequently extended and modified, will
permit use of the allowed additional PE for connections
to such
sewers.
See also,
3 PCB at 552.
24
—
703
In PCB 75-301,
the Board estimated that NSSD would require
approximately 1,500 PB in connection allowances during
1976;
710 PE
were used.
We shall allow
a
totail
1,500 PB for the
coming
year,
providing for
the
apparently untuitilfed needs shown
last year
(including conversion
of some areas from septic fields
to NSSD
service)
,
and some additional growth.
As was the case last year, we shall retain jurisdiction
in this
case
to consider raising that limit,
or possibly lifting the sewer
ban entirely as it affects areas tributary to the Waukegan STP.
To
provide
for
those possibilities, NSSD shall by July
1,
1977,
submit
a report detailing the status of the Waukegan STP.
We shall Order
a
further Recommendation by the Agency
in response
to NSSD~sReport.
A hearing will be ordered at that time, hopefully
for final disposition
of this matter.
All applicable conditions from PCB 71-343,
PCB 72-451,
PCB 73-502,
PCB 74—344 and PCB 75—301 shall remain in effect.
ORDER
IT
IS
THE
ORDER OF THE POLLUTION CONTROL BOARD that:
1.
Petitioner North Shore Sanitary District be granted
a
Variance for its Waukegan Sewage Treatment Plant from Order No.
7
in League of Women Voters
v. NSSD, PCB 70-7,-12,-13,—14
(Mar.
31,
1971),
to allow sewer connections totaling 1,500
PB during the period from
December
31,
1976
to December 31,
1977.
2.
Said Variance grant shall be subject to all applicable
conditions
in PCB 71—343, PCB 72—451, PCB 73—502, PCB 74—344,
and
PCB 75—301.
3.
Said Variance grant shall be conditioned upon the submittal
by Petitioner of
a report detailing all appropriate information on
the status of expansion, construction,
and diversion at
the Waukeqan
Sewage
Trea
I
men
I
P
I
ni
,
I no
I mid
I
Ii’)
I
In
I o id
:;
I
i
I
ii:;
I
;ew
I:;
I
I
ibmi
t
ary
f
0
ra
i
(I
I~
I a
iii
/
uo h
rep~
r
I
1o he
I
I
Ii~d w
I
I
Ii
I lu
lit )a
it
1
a id
I lie
Hnv
i
ron
—
metiLa I Pro LouLi
011
Agency by June
30
,
1977
4.
Respondent Environmental Protection Agency shall file a
response and further Recommendation
in this matter,
based on its own
investigations and the reports submitted
to them as required
in
paragraph
3, above, by July
31,
1977.
5.
The Board shall retain jurisdiction
in this matter for the
term of
the
Variance.
24
—
704
—5—
6.
Said
Variance
grant
shall
further
be
conditioned upon
the submittal
to
the
Environmental
Protection
Agency,
within
thirty--five
(35)
days
of
the
date of
this Order,
of
a
Certificate
of Acceptance
in the following form:
I,
(We)
,
__________________
__________
having
read
the Order of the Illinois Pollution Control Board in
case No.
PCB 76—285,
understand and accept said Order,
realizing that such acceptance renders all terms and
conditions thereto binding and enforceable.
SIGNED
TITLE
DATE
I,
Christan
L. Moffett, Clerk of the Illinois Pollution
Control
Board,
he~eby
certify
the
above
Opinion and Order weçe
adopted on the
day
of
________
,
1977,
by a vote of
5..c~.
Christan L. Moffel~’1Clerk
Illinois Pollution Control Board
24
— 705