ILLINOIS POLLUTION CONTROL BOARD
February 3~ 1977
ENVIRONMENTAL
PROTECTION AGENCY,
Complainant,
v.
)
PCB 75—267
TERMINAL RAILROAD ASSOCIATION OF
ST. LOUIS,
a Missouri corporation,
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Zeitlin):
This Enforcement matter has been the subject of
a previous
Interim Opinion and Order of the Board adopted on October
28,
1976.
We described there the circumstances which led to the filing of
the Agency’s Complaint regarding noise emissions from Respondent’s
Venice,
Illinois switching yard.
Our discussion
there
of the facts
and procedural matters relevant to this case need not be repeated
here.
In our October 28,
1976 Interim Opinion and Order,
the Board
indicated that
a Stipulation and Proposed Settlement filed in the
case, along with
a Supplemental Stipulation,
were generally accept-
able
in resolution of
the matters raised in the Agency’s Complaint.
We were unable,
however,
to accept the unsupported findings by the
parties
in the Supplemental Stipulation that complete compliance
by Respondent’s retarding operations
at the Venice switching yard
could not,
given the present levels of technical
feasibility and
economic reasonableness,
achieve compliance with the relevant Noise
Pollution Control Regulations of this Board.
Accordingly, we
remanded for further hearing limited
to that subject.
A further hearing was then held on November
30,
1976,
in
Edwardsvi, lie,
11.1
inois
.
BC)
Lb
Comp hi
man
t
and
Pespondeii
L
Liier(~’
introduced
testimony
and
evidence
supporting
their
earlier
conclusion
on
the
subject
of
technical
feasibility,
particularly
with
regard
to the level of proven technology.
We find that record adequate,
and here approve the Stipulation and Proposed Settlement,
and the
Supplemental Stipulation,
in their entirety.
Testimony presented by both the Agency and Respondent indicates
that at the time the Complaint in this matter was filed,
no similar
facility
in the country was known to be in compliance with the
applicable Board Regulations.
This was verified by both literature
search and on-site inspections
in Kansas City and Minneapolis,
(R.
14,
21,
42).
Lubrication systems, costing between $250,000 and
24
—
665
—2—
$500,000 per system
(excluding maintenance and operational costs),
had not been successful.
The substitution of ductile iron shoes
for the steel ones normally used on the retarders would cost over
$100,000, work only
in limited situations with very low speed
(below
6 mph)
humping, and would increase wear on those shoes by
a factor
as high as 10.
Computer control of retarders,
estimated
to cost
$1.5 million, would not reduce noise at all, but might decrease the
frequency of noise emissions,
(e.g.,
R.
18-21,
43,
47).
As noted
in our earlier Opinion,
the abatement technique
actually adopted at the Venice yard was the construction of noise
barriers at each of the retarders.
Although,
as noted there,
these
barriers did not achieve complete compliance with the relevant
Regulations,
all 65 individuals who originally complained about
these noise emissions were satisfied with the noise reductions
achieved,
(R.
32)
.
Those barriers were constructed at a cost of
approximately $82,000, by Respondent, based on an original design
by Agency expert Gregory T.
Zak.
To achieve complete compliance,
these barriers would have had
to achieve a reduction in noise levels of approximately 33 dB, based
on measurements taken 1,000 feet or more from the noise sources,
(R,
26).
The best reduction achieved prior to that time had been
approximately 20 -dB, measured at a distance of 100 feet from the
barrier, at which point the apparent noise reduction would be greater,
(R.
27-28,
42).
Terminal Railroad’s efforts in this case have
achieved
a reduction in noise levels
5 dB greater than ever previously
achieved,
with the measurements taken at a distance which would tend
to
greatly decrease the amount of such reduction,
(R.
28)
.
In fact,
the method used here for abatement is being used and studied for
the solution of similar problems
in other parts of the country,
(Id.).
Based on this testimony and evidence, we find that Respondent
Terminal Railroad has acted in good faith to abate its admitted
violation.
Despite the minor violations remaining, Terminal Railroad
has apparently done all that was possible under the circumstances
to abate its noise emissions and eliminate any difficulties or
inconveniences which those emissions may have
caused
to
the
surrounding
residents.
Based on that finding, and the findings
in
our
Interim
Opinion
and
Order
of
October
28,
1976,
we
shall
enter
our final Order in this matter in accord with the Proposed Settle-
ment submitted by the parties.
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter.
24
—
666
—3—
ORDER
IT
IS THE ORDER OF THE POLLUTION CONTROL BOARD that:
1.
Respondent Terminal Railroad Association of
St. Louis
is found to have operated its railway switching
yard in Madison County,
Illinois,
in violation of Section
24 of the Environmental Protection Act,
and Rules 102(n),
202, and 207 of Chapter
7 of the Board’s Regulations.
2.
Respondent Terminal Railroad Association of St.
Louis shall comply with all provisions of the Settlement
agreement submitted by the parties to this matter.
I, Christan L. Moffett,
Clerk of the Illinois Pollution
Control Board, hereby certif,y the above Opinion and Order were
adopted on the
~
day of
~
1 977,
by
a vote of
~
ci
Christan L. Moffe1~ç’Clerk
Illinois Pollution Control Board
24
—
667