ILLINOIS POLLUTION CONTROL BOARD
    June
    18,
    1976
    ENVIRONMENTAL PROTECTION AGENCY,
    Complainant,
    v.
    )
    PCB 75—494
    PIELET BROS. TRADING,
    INC.,
    an Illinois Corporation, and
    Seymour Pielet,
    )
    Respondents.
    Mr.
    M.
    Barry Forman, Assistant Attorney General, Attorney for
    Complainant
    Mr.
    A.
    J.
    Nester, Attorney for Respondent
    OPINION AND ORDER OF THE BOARD
    (by
    Mr.
    Young):
    This matter comes before the Board on a Complaint filed
    December
    19,
    1975 by the Environmental Protection Agency
    (Agency)
    charging that the Respondents, Pielet Bros.
    Trading,
    Inc.
    or
    Seymour Pielet, owned and operated certain air pollution control
    equipment without first obtaining operating permits from the
    Agency as required by Rule 103(b) (1)
    of the Air Pollution Regu-
    lations and in further violation of Section 9(b) of the Environ-
    mental Protection Act
    (Act)
    *
    The subject matter of this Complaint is an automobile
    shredding facility located at 1200 North First Street, National
    City,
    St. Clair County, Illinois.
    As an integral part of the
    aforesaid facility, the Company operates two cyclones to collect
    particulate emissions from the facility’s shredding unit and
    from certain pickup points over the conveyors.
    At
    the hearing held on March 9,
    1976, the parties
    stipulated
    to the following facts.
    Work for the construction of the
    facility
    began in April of 1975.
    No attempt was made to secure an Agency
    construction permit prior to initiating this work,
    and in May
    an Agency representative informed Respondent of a need for a
    construction permit for the installation of the equipment.
    Following correspondence between the parties a construction per-
    mit was issued on November 5,
    1975.
    This installation process
    was completed on August 22,
    1975,
    at which time the facility began
    operation.
    While it is not clear when Respondent first made appli-
    cation for an operating permit, such permit was issued by the Agency
    on February 19,
    1976.
    22
    153

    —2—
    The Complaint in this matter concerns only the operating
    permit violation from September 9, 1975 until December
    19,
    1975
    and on the basis of the record, there can be no doubt that an
    operating permit violation is established.
    Respondent offers several matters in mitigation that require
    attention.
    First, Respondent alleges that the equipment was
    especially fabricated for the project and that no test data was
    available to be submitted to the Agency.
    This argument has abso-
    lutely no merit.
    In fact, specifications and data were available
    for similar equipment, and Respondent used this data in obtaining
    the Agency permits.
    (R.
    17).
    Assuming for the moment that speci-
    fications were not available,
    the Board would still remain unrecep-
    tive to this argument.
    It is just this type of equipment which
    accentuates the value of the construction and operating permit
    system.
    Because the equipment is unique and no specifications
    are available,
    all the more necessitates that the operator obtain
    the permit prior to operation to assure that environmental harm
    will not result from its operation.
    Second, Respondent argues that the Agency did not show that
    particulate emissions occurred in violation of the regulations.
    This argument implies that since the operation of the equipment
    did not cause a violation of the regulations
    (an after the fact
    determination), no penalty should be assessed.
    Acceptance of
    this argument would greatly diminish the value of the permit
    system which has as one of its goals an Agency predetermination
    whether the operation of the equipment will cause a violation of
    the regulations.
    Our cases are replete with operators who have
    side-stepped the permit system producing results causing serious
    environmental damage.
    Thus, while the Board will consider such
    evidence
    in partial mitigation,
    to consider such in complete
    mitigation would totally emasculate the permit system.
    Third, Respondent argues that it acted
    in good faith in
    its attempt to comply with the permit requirements after being
    contacted by the Agency.
    This allegation
    is not supported by
    the record.
    While Respondent did engage in a course of conduct
    which eventually led to the issuance of an operating permit, the
    Board believes that its actions should have been taken with greater
    alacrity.
    Respondent was apprised of the operating permit re-
    quirement in May of 1975, and began operating the facility on
    August
    22,
    1975.
    The Complaint in the instant matter was filed
    on December
    19,
    1975.
    Nonetheless it was not until January
    16,
    1976 that the Agency finally received an application
    for the
    operating permit,
    almost five months after the facility was in
    operation.
    On the basis
    of these facts the Board finds that
    Respondent’s actions were not taken in good faith, but rather
    were dilatory.
    The Supreme Court has upheld the imposition of a
    penalty where equipment was installed and operated after Agency
    denial of the permit application
    (Mvstik Tape
    v
    PCB,
    60
    Ill.
    2d
    330,
    (1975).
    Since Respondent should not be able to place itself
    22—154

    —3—
    in a more advantageous position by merely refusing to applv
    for the requisite permit,
    the Board
    finds that a penalty is
    likewise appropriate in this matter because Respondent delayed
    almost five months after beginning operation before filing an
    operating permit application.
    Although the Respondent alleges that the Agency acted un-
    reasonably with the construction permit application,
    it nonetheless
    failed to file a permit denial appeal with the Board.
    Although
    the Respondent alleges that it was initially unaware of the permit
    requirements, even after being informed of the requirements it
    chose
    to operate without a permit.
    If Respondent had filed a
    variance petition with the Board in May when informed of the permit
    requirements,
    the 90 day decision period would have expired by
    the time the plant was placed
    in operation.
    Both the permit denial
    appeal and the variance procedure could have provided Respondent
    with the relief that it desired and needed.
    At hearing Respondent
    did not satisfactorily explain why it failed to follow either of
    these procedures.
    In view of the foregoing the Board finds that Respondent
    operated its facility without the requisite operating permits and
    the Board will assess $1,000.00 as
    a penalty for such violations.
    Seymour Pielet was charged in the alternative with the Company
    with these violations.
    The record does not support such a charge
    and the Complaint as regards to this Respondent shall be dismissed.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1.
    Respondent,
    Pielet Bros.
    Trading,
    Inc., has violated
    Rule 103(b) (1)
    of the Air Rules and Section 9(b) of the Act and
    shall pay $1,000
    as penalty for such violations.
    Penalty payment
    by certified check or money order payable to the State of Illinois
    shall be made within 35 days of the date of this Order to:
    Fiscal
    Services Division, Illinois Environmental Protection Agency,
    2200
    Churchill Road,
    Springfield, Illinois,
    62706.
    2.
    That portion of the Complaint as it concerns Seymour
    Pielet is dismissed.
    IT IS SO ORDERED.
    22—155

    —4—
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, here
    certify the above Opinion and Order were
    adopted o
    the
    )
    day of
    ~
    ,
    1976 by a
    vote of
    ..~
    Illinois Pollution
    22—156

    Back to top