ILLINOIS POLLUTION CONTROL BOARD
    August
    5,
    1976
    QUINCY SOYBEAN COMPANY,
    )
    Petitioner,
    v.
    )
    PCB 76—113
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Dumelle):
    This matter comes before the Board on a Petition for Variance
    by Quincy Soybean Company
    (Quincy)
    from Rule 203(1)
    of the Board’s
    Water Regulations to allow Quincy to discharge its cooling water
    effluent into Curtis Creek
    (Creek) beginning January
    1,
    1977 until
    the City of Quincy makes available a
    36” outfall sewer to the
    Mississippi River.
    The original Petition was filed on April
    26,
    1976.
    On June
    1,
    1976 the Agency filed its Recommendation on
    this matter requesting the denial of the Petition until:
    1)
    Quincy demonstrates that its discharge will not have
    a detri-
    mental effect on the Creek,
    2)
    Quincy presents
    a schedule
    for removal of all process wastes from its cooling water discharge,
    and 3)
    Quincy agrees to remove all process wastes from its cooling
    water discharge by April
    1,
    1977.
    On July 21,
    1976 Quincy
    amended its Petition for Variance with biological surveys of both
    the Creek and the drainage ditch Quincy presently uses,
    a summary
    of the drainage ditch temperature data,
    and several other documents.
    On August
    5,
    1975 the Agency filed an Amended Recommendation.
    Quincy Soybean Company processes soybeans to produce soybean
    oil and soybean meal.
    Quincy presently discharges
    5.5 MGD cooling
    water into the Mississippi River via drainage ditch and pumping
    plant of the South Quincy Drainage District.
    The current contract
    authorizing this discharge expires on December
    31,
    1976 and will
    not be renewed due to inadequate pumping capacity.
    Quincy therefore
    must find an alternative treatment or discharge method.
    The City of Quincy plans to abandon a 36” outfall sewer
    from its sewage. treatment plant
    to the Mississippi River some
    time in 1978.
    At that time it is anticipated that Quincy will
    lease the sewer from the City.
    Thus, Quincy seeks an interim
    23
    243

    —2—
    solution.
    Quincy proposes to construct a pipeline which will
    extend beyond the proposed discharge point at Curtis Creek and
    connect into the City’s
    36” sewer.
    Thus, when the City’s sewer
    becomes available Quincy would stop the discharge into the Creek
    and open the sewer connection.
    The Board must determine whether compliance with the thermal
    discharge standard of Water Rule 203(i) would place an arbitrary
    or unreasonable hardship upon Quincy.
    Quincy proposes a two gear
    discharge of 5.5 MGD of water
    at an average temperature of
    80
    into
    the final
    1,500 feet of Curtis Creek prior to its confluence with
    the Mississippi River.
    Quincy states that the effluent conforms
    to all applicable standards except for the thermal limits to
    Curtis Creek.
    The first issue,
    then,
    is the extent of environmental
    damage which could be caused by the proposed discharge.
    Quincy
    has submitted biological surveys of both Curtis Creek and the
    presently used drainage ditch.
    The Curtis Creek survey describes
    septic odors, depressed oxygen concentrations,
    algal growth and
    silt layers which cover the bottom,
    and the absence of intolerant
    macroinvertebrates.
    The proposed discharge point is downstream
    from the South Park storm and sanitary discharge point,
    industrial
    discharges,
    and the bypass from the City’s treatment plant.
    On
    either side of Quincy Soybean’s proposed discharge point the
    survey states that the
    “.
    .
    .bottom deposits were comprised of
    silts and organic materials resembling partially digested
    domestic sewage.”
    After reviewing the survey data the Board
    finds that there is
    a rather low potential for adverse environ-
    mental impact.
    The main concern of the Board is the possibility
    of a fish kill which could result from a sudden cessation of
    the heated discharge during the winter.
    Quincy’s survey of the South Drainage Ditch,
    into which
    it currently discharges
    its effluent, indicates the presence
    of large numbers of fish and a large diverse population of
    macroinvertebrates.
    The report concludes that the ditch
    is
    a
    more balanced aquatic ecosystem than
    is the lower portion of
    the
    Creek.
    This indicates that Quincy’s two year discharge will not
    have a long-term adverse effect on Curtis Creek.
    The possibility
    of a fish kill exists in either the Creek or the ditch during
    the winter.
    It will be Quincy’s duty to operate its plants
    in
    such a manner
    so as
    to minimize this risk.
    Quincy has submitted, by affidavit, an assessment of alterna-
    tives for cooling the effluent or re-routing by pipeline.
    As
    for cooling methods
    it is clear that design and construction lag
    times would render
    these alternatives useless.
    By the time
    23
    244

    —3—
    construction could be completed the device would probably no
    longer be needed.
    Of course, were there an indication of self—
    imposed delay and bad faith on Quincy’s part such factors would present
    no excuse.
    However,
    in this case no such allegation has arisen.
    The affidavit also considers the construction of
    a pipeline
    to the Mississippi.
    While the cost would not be prohibitive,
    this
    project would require the removal of trees from 30,000 square
    feet of river flood plain.
    There is also question as
    to whether
    such pipeline could be completed prior to January
    1,
    1977.
    There-
    fore, given the absence of long—term adverse environmental effects
    the Board finds that compliance with Water Rule 203(i) would place
    an arbitrary or unreasonable burden upon Quincy.
    However, the
    Board will structure its order to reflect the uncertainty of
    the dates of termination of use of the ditch and the availability
    of the outfall sewer.
    The Opinion constitutes the Board’s findings of fact and
    conclusions of law.
    ORDER
    Petitioner Quincy Soybean Company
    is hereby granted variance
    from Rule 203(i)
    of the Board’s Water Pollution Regulations for
    the discharge of cooling water into Curtis Creek at an average
    rate of 5.5 MGD and an average temperature of 800.
    The discharge
    shall be located not more than approximately 1500 feet upstream
    of the Creek confluence with the Mississippi.
    This variance
    shall commence at the time Quincy Soybean Company notifies the
    Agency that the South Quincy Drainage District has refused
    all reasonable offers
    to extend and/or modify the existing
    contract, but not sooner than December
    31,
    1976.
    The variance
    shall terminate upon the occurrence of any of the following:
    1.
    Extension or modification of Quincy’s contract to
    to discharge to the South Quincy Drainage District;
    or
    2.
    Failure of the City of Quincy to agree to lease its
    36” outfall sewer
    to Quincy Soybean; or
    23
    245

    —4—
    3.
    Availability of the 36” outfall sewer for Quincy
    Soybean’s discharge.
    However, in no case shall this variance extend beyond
    December 31,
    1978.
    This variance does not relieve Petitioner
    from liability associated with any killing of fish or other
    aquatic life caused by its discharges.
    This variance is granted subject to the following conditions:
    (a)
    Petitioner shall investigate and report to the
    Agency by December
    31,
    1976 on the feasibility of
    phasing its plant shut downs to avoid fish kills
    attributable to thermal shock.
    (b)
    Petitioner shall complete its proposed separation
    of process waste, cooling water, and floor drains
    by April
    15, 1977.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Bo
    r
    ,
    hereby certify the above Opinion and 0 der were adopted on the
    ~_day
    of August, 1976 by a vote of _______________________
    Christan L. Mo fett,
    C
    Illinois Pollution Cont
    oard
    23
    246

    Back to top