ILLINOIS POLLUTION CONTROL BOARD
July
22, 1976
CITY OF DECATUR
AND
SANITARY DISTRICT
OF DECATUR,
Petitioners,
v.
)
PCB 76-2
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Mr.
Gus Greanias, of Greanias
& Burton,
appeared on behalf of
the City of Decatur
Mr.
Joseph Svoboda appeared on behalf of the Environmental Protection
Agency
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr.
Goodman)
This
matter
comes
before
the
Pollution
Control
Board
(Board)
upon the Petition filed by the City of Decatur
(City)
and the
Sanitary District of Decatur
(District)
on January
5,
1976,
appealing
from a permit denial or,
in the alternative, requesting a variance.
The Agency filed its Answer to Permit Appeal and Recommendation on
March
8,
1976.
A hearing was held in this matter on April
29,
1976
in Decatur,
Illinois.
On March 20,
1975, Decatur filed an application with the Environ-
mental Protection Agency
(Agency)
for a permit to construct
a pro-
posed McKinley Avenue Diversion Control Facility.
On April
17,
1975,
the Agency denied the permit on the basis that the proposed facility
would not comply with Sections 12 and 39 of the Environmental Pro-
tection Act
(Act).
Specifically,
the Agency found that the proposal
would violate Rule 602(c) (2) of the Board’s Water Pollution Regu-
lations
(Chapter 2).
Decatur requested review of its submittal, and
on May 19, 1975, -the application was redenied.
In its May
19,
1975,
letter, the Agency based its redenial upon Rule 602(c) (2)
as well as
upon Rule 602 (a), which prohibits the installation of new combined
sewers except where sufficient retention or treatment is provided.
23
—
127
—2—
The City has jurisdiction over the combined,
lateral and storm
water sewers,
and the District has jurisdiction over the interceptor
sewers and treatment plant serving the Decatur community.
Petitioners’
facilities include a 42-inch North Side Interceptor which serves
an
interceptor chamber receiving flow from the 72-inch McKinley Avenue
combined sewer.
A 48-inch Stevens Creek Interceptor receives flow
from the North Side Interceptor as well as from a
30-inch North
Stevens Creek Interceptor.
In 1974, the Agency informed the City that
it had received coin-
plaints of basement sewer back-ups from occupants of five homes
connected to the Stevens Creek Interceptor.
Investigation revealed
that all five homes had basement floors which were built below or
only a few inches above the crown of the interceptor.
Furthermore,
the Agency informed the District that the Stevens Creek Interceptor,
which serves 1/3 of the Decatur community, was being placed on
Critical Review Status.
Engineers engaged by the Petitioners agreed that one cause
of
the basement back—ups was the surcharging of the Interceptor serv-
ing the homes.
According to Petitioners,
this surcharging was the
result of an existing diversion structure permitting excess
flow
from the 72-inch combined sewer into the 42-inch North Side Inter-
ceptor during exceptionally high storm periods.
In order to allevi-
ate the problem, Petitioners proposed to construct
a new diversion
facility upstream from the existing diversion structure which would
limit the flow into the North Side Interceptor to
3 1/2 times dry
weather
flow.
The new diversion structure would be constructed up-
stream in order to obtain a gravity flow condition where the sewer
is not surcharged so that the flow may be measured through a Parshall
flume
(R.22).
One of the Agency’s witnesses testified that the pro-
posed diversion facility would consist of a new concrete structure on
the existing combined sewer,
including twenty feet of new sewers and
a new control structure with approximately eighty feet of sewer tribu-
tary to the Parshall flume
(R.ll2).
Any excess
flow over
3 1/2 times
the dry weather flow would overflow into Spring Creek, which is
tributary to Stevens Creek and eventually to the Sangamon River.
The
discharge to Spring Creek,
therefore, would be diluted sewage from a
combined sewer.
Permit Appeal
The issues raised by Petitioners on appeal are:
1)
Is the
proposed facility a new combined sewer and, therefore, subject to
Rule 602(a),
and
2) Did the Agency have the authority to deny the
permit application based upon Rule 602(c) (2) when compliance with
that Rule was not required, pursuant to Rule 602(d)
,
until
7
1/2
months after the permit denial?
23
—
128
—3—
Rule 602(a)
provides that:
“the installation of new combined sewers
is prohibited,
except where sufficient re-
tention or treatment capacity is provided
to ensure that no violation of the effluent
standards
in Part IV of this Chapter occurs.”
Rule 602(c) (2)
provides:
(c)
All combined sewer overflows and treatment
plant bypasses shall be given sufficient
treatment to prevent pollution or the vio-
lation of applicable water quality standards.
Sufficient treatment shall consist of the
following:
(2)
Additional flows,
as determined by the
Agency but not less than ten times the
average dry weather flow for the design
year,
shall receive
a minimum of primary
treatment and disinfection with adequate
retention time;
Rule 602(d)
states that compliance with Rule
602(c)
is
to be achieved by December
31,
1975.
As
to the first issue,
Petitioners argue that the proposed
diversion facility would not involve construction of new combined
sewers because no additional flow would be introduced into the
system, no new sewer was
involved,
and no new diversions were being
made into Stevens Creek by the diversion.
Petitioners contend that
the proposal would merely be the modification of an existing diver-
sion structure rather than the construction of
a new combined sewer.
The Agency, on the other hand, points out that the proposal
will involve construction of
a new stretch of connecting sewer which
is to receive combined sewage from the McKinley Avenue combined sewer.
Therefore,
the new stretch of sewer is, according to the Agency,
necessarily
a new combined sewer.
The
Board
agrees
with
the
Agency’s
contention.
Rule
104
of
the Water Regulations defines combined sewer as
“a sewer receiving
both wastewater and land run—off.”
The new sewer which would be
a
part of the proposed diversion facilities
is specifically intended
to receive wastewater and land run-off from the McKinley Avenue
combined sewer and is,
therefore,
a new combined sewer.
Because
23
—
129
—4—
Petitioners’ proposal did not provide for sufficient retention and
treatment capacity to ensure that no violation of the effluent
standards would occur,
as required by Rule 602(a),
the Agency was
correct in denying the permit on the basis of that Rule.
We next consider Petitioners’
contention that the Agency lacked
authority to deny the permit on the basis of Rule 602(c) (2)
because
compliance with that regulation was not required until a date seven
months in the future.
We reject this argument.
Petitioners sub-
mitted no plan for treating 10 times the dry weather flow for the
combined sewer overflow from this diversion structure.
Without a
program to
be
implemented
in
a
reasonable
amount
of
time,
no
treat-
ment could possibly have been provided for this diversion’s combined
sewer overflow.
The Agency was correct in denying a permit for con-
struction of facilities which inevitably would result in a violation
of the Board’s Regulations.
The only issues relevant on appeal from denial of a permit are
those related to whether the Agency correctly interpreted and admini-
stered the regulations when it denied Petitioners’ permit application.
Because the proposed facilities would have violated Rules
602(a)
and 602(c) (2), the Agency was prohibited by Sections
12 and
39 of
the Act from granting the requested permit.
The Board finds that
the Agency did correctly administer and interpret the Regulations
and, therefore, upholds the permit denial.
Variance
The Board next considers Petitioners’ request for variance
in
order to permit issuance of the requested permit.
Petitioners are
faced with a Critical Review Status for an interceptor serving 1/3
of their community and with basement sewer back—ups.
They have
proposed a plan which they feel will help alleviate the immediate
problem and have expended engineering costs
in arriving at their
proposal.
Furthermore,
the City has commenced a fifty—four million dollar
storm water improvement and the District is
in the final stages of
an eleven million dollar plant improvement.
Petitioners are also
in the process of preparing an Area Facilities Plan jointly with
two neighboring villages, which will be completed in December,
1976.
Petitioners’
Reply Brief indicates that the Area Facilities Plan
will include an Infiltration and Inflow Study and recommendations
for treatment of all diversion outlets in the area.
Petitioners
state that they are committed to full compliance with the Act at
the earliest possible date their financial ability will permit.
23— 130
—5—
The Agency has recognized the fact that many municipalities
and sanitary districts throughout the State have not met and cannot
presently meet the December
31, 1975 compliance date.
On December
22,
1975, the Agency filed an Amended Petition for Regulatory Change
(R75—l5) with the Board specifically requesting that the date for
complying with Rule 602(d) (3)
be extended until July
1,
1977, pro-
vided a grant application had been filed before December 31,
1975.
The Board has not yet taken final action on this proposal, although
it has published a proposed final draft adopting the substance
of the Agency’s proposal.
The Board finds that denial of the variance
in the present case
would impose an arbitrary and unreasonable hardship upon Petitioners.
Therefore, Petitioners are granted variance from Rules
602(a)
and
602(d) (3), the compliance date for Rule 602(c) (2)
for the proposed
McKinley Avenue diversion facilities.
The Board finds no need
to grant
a variance from the permit requirement itself because
Rule 962(a)
of the Water Regulations provides for the granting of a
permit to applicants who have received a variance from the Board.
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter.
ORDER
It ~s the Order of the Pollution Control Board that:
1.
The denial by the Agency of the application submitted
by the City of Decatur and the Sanitary District of Decatur
for a permit to construct a McKinley Avenue Diversion Control
facility is affirmed.
2.
The Sanitary District of Decatur and the City of Decatur
are granted variance from Rule 602(a) and from the compliance date
for Rule 602(c) (2) (combined sewer overflows)
as established
by Rule 602(d) (3)
of Chapter
3 for the proposed McKinley
Avenue diversion facilities.
Such variance
is granted until
July 1,
1977, or until the Board adopts
an amendment to the
Regulations in consideration of the Agency’s Regulatory
Proposal
(R75-15), whichever is sooner.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, he~ebycertif
th
above Opinion and Order were adopted on
the
‘~‘~
day of
,
1976 by a vote of_____________
Illinois Pollution C~i~/olBoard
23—131