ILLINOIS POLLUTION CONTROL BOARD
    July 22,
    1976
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Complainant,
    )
    v.
    )
    PCB 75—418
    CITY OF BREESE,
    Respondent.
    MR. BARRY FORMAN, Assistant Attorney General, appeared for the
    Complainant;
    MR. BERNARD
    G. HEILIGENSTEIN, appeared for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Dumelle):
    On
    October
    28,
    1975 the Environmental Protection Agency
    (Agency~ filed a Complaint against the City of Breese
    (City),
    located
    in Clinton County,
    Illinois.
    The subject of the Complaint
    is coal-fired Boiler No.
    2 at the City’s power plant.
    The
    Complaint alleges three violations:
    1.
    Violation of the particulate standards of Rule 2—2.53
    of the old Air Regulations and Section 9(a)
    of the
    Act from July 1,
    1970 to May
    30,
    1975;
    2.
    Violation of the particulate standards of Rule
    203(g)
    (1) (B)
    of the Board’s Air Polltuion Control Regulations
    and Section 9(a)
    of the Act from May 31,
    1975 to
    October 28,
    1975;
    and
    3.
    Violation of the permit requirement of Rule 103(b) (2)
    of the Air Pollution Control Regulations and Section
    9(a)
    and(b)
    of the Act from April
    1, 1973
    to October 28,
    1975.
    A hearing was held on December 15,
    1975 in the City Hall of
    Breese.
    Mr. Martin Johnson, the City’s Superintendent of Utilities
    verified the figures on page
    2 of the Comp.
    Ex.
    4~7 (R.
    11) which
    23—
    115

    —2—
    is
    a copy of the Board Order
    in PCB 73-209
    (April
    10,
    1975).
    This case was a variance request concerning Boilers No.
    1 and
    2.
    The variance for Boiler No.
    2 was denied.
    It
    is
    admitted that
    Boiler No.
    2 has no particulate controls
    CR.
    14).
    Therefore,
    given the admission of the accuracy of the calculations of
    particulate emissions at page
    2 of Camp.
    Ex.
    #7, there can be
    no doubt that to the extent of the Boiler’s operations,
    it did exceed
    the standards of both the old Rule 2—2.53 and Rule 203(g) (1) (B), and
    Section 9(a)
    of the Act.
    However,
    the Supreme Court, in Commonwealth
    Edison Company v. Pollution Control Board,
    62 Ill
    2d 494,
    343 N.E.
    2d 459
    (1976)
    remanded to the Board Rule 203(g) (1)
    of the Air
    Pollution Control Regulations.
    It would therefore be inappropriate
    for the Board to find a violation of that Rule in this case.
    It is also established that no operating permit had
    been obtained for Boiler
    #2.
    As the Board Order PCB 73-209 states,
    the City did apply for operating permits but the application was
    denied because of the calculated particulate violations.
    There
    is no doubt that the City did operate in violation of Rule
    103(b)
    (2)
    of the Air Pollution Control Regulations and Sections
    9(a)
    and
    (b)
    of the Act.
    As for the violation of the particulate standard from July
    1,
    1970 through May
    30,
    1975 the chief factor of mitigation is the
    apparent good faith effort which the City made to retire its
    coal—fired boilers.
    The major problem
    was
    solved by the electrical
    interconnection with Illinois Power Company operative on March
    28,
    1976
    (R.
    62). The City has previously attempted to purchase a
    diesel engine to replace the coal—fired boilers but the bond
    issue failed
    (R.
    58).
    Coupled with the high cost of an
    electrostatic precipitator and problems with fuel allocations
    which made conversion uncertain,
    consideration of the 33(c)
    factors show strong mitigation.
    A municipal power plant carries
    a high social and economic value where alternative sources of
    electricity are simply not available.
    Also important is the fact
    that the operation of this boiler apparently did not cause any
    citizen complaint
    (R.
    61).
    Given
    these facts the Board finds
    that a penalty would not aid in the enforcement of the Act in
    this particular case.
    For the same reasons the Board finds
    no penalty advisable
    for the City’s failure to obtain an operating permit.
    It is
    noted that the City did apply
    for a permit on January
    23,
    1973,
    which is prior to the period of the violation found.
    It would be
    unnecessary in this case to penalize the City for failing to
    conform to a standard which has already been found above
    to have
    represented an unreasonable hardship.
    23—116

    —3—
    The City of Breese has shown good faith.
    The City’s inability
    to raise the funds necessary to allow the retiring of Boiler
    #2
    is understandable in view of the financial difficulties encountered
    by most small municipalities.
    The establishing of an interconnection
    was also carried out in good faith.
    The City has now committed
    to converting Boiler #2 to oil
    (R.
    57).
    Respondent’s Exhibit No.
    1
    is an estimated completion schedule for that project.
    Installation
    is estimated to be completed on December 20,
    1976, at which time
    the City should be in compliance with the Board’s Regulations.
    The
    Board will require the City to submit to the Agency, within 60 days,
    a proposal for Boiler #2 so that a variance or a permit may be
    obtained.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law.
    ORDER
    1.
    Respondent City of Breese
    is hereby found
    to have violated
    Rule 2—2.53
    of the old Air Rules, Rule 103(b) (2)
    of the
    Air Pollution Control Regulations, and Section 9(a)
    and
    (b)
    of the Environmental Protection Act.
    2.
    That portion of the Complaint alleging violation of
    Rule 203(g) (1) (B)
    of the Air Pollution Control Regulations
    is hereby dismissed.
    3.
    If Respondent City of Breese operates Boiler
    #2
    prior to its conversion to oil the City of Breese
    shall promptly submit a report to the Agency detailing
    the extent of the emergency and the resulting operations.
    4.
    Respondent City of Breese shall, within 60 days of the
    date of this Order, submit to the Agency a proposal
    regarding the conversion of Boiler
    #2 from coal
    to oil
    fuel so that a permit or a variance may be obtained.
    IT IS SO ORDERED.
    I, Christan L. Moffett,
    Clerk of the Illinois Pollution Control
    Boar~~
    hereby certify the above Opinion and Order were adopted on the
    _______day of July,
    1976 by a vote of
    ~-O
    Christan L. Moffett,
    Illinois Pollution Co
    1 Board
    23
    117

    Back to top