ILLINOIS POLLUTION CONTROL BOARD
July 22,
1976
ENVIRONMENTAL PROTECTION AGENCY,
)
Complainant,
)
v.
)
PCB 75—418
CITY OF BREESE,
Respondent.
MR. BARRY FORMAN, Assistant Attorney General, appeared for the
Complainant;
MR. BERNARD
G. HEILIGENSTEIN, appeared for the Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Dumelle):
On
October
28,
1975 the Environmental Protection Agency
(Agency~ filed a Complaint against the City of Breese
(City),
located
in Clinton County,
Illinois.
The subject of the Complaint
is coal-fired Boiler No.
2 at the City’s power plant.
The
Complaint alleges three violations:
1.
Violation of the particulate standards of Rule 2—2.53
of the old Air Regulations and Section 9(a)
of the
Act from July 1,
1970 to May
30,
1975;
2.
Violation of the particulate standards of Rule
203(g)
(1) (B)
of the Board’s Air Polltuion Control Regulations
and Section 9(a)
of the Act from May 31,
1975 to
October 28,
1975;
and
3.
Violation of the permit requirement of Rule 103(b) (2)
of the Air Pollution Control Regulations and Section
9(a)
and(b)
of the Act from April
1, 1973
to October 28,
1975.
A hearing was held on December 15,
1975 in the City Hall of
Breese.
Mr. Martin Johnson, the City’s Superintendent of Utilities
verified the figures on page
2 of the Comp.
Ex.
4~7 (R.
11) which
23—
115
—2—
is
a copy of the Board Order
in PCB 73-209
(April
10,
1975).
This case was a variance request concerning Boilers No.
1 and
2.
The variance for Boiler No.
2 was denied.
It
is
admitted that
Boiler No.
2 has no particulate controls
CR.
14).
Therefore,
given the admission of the accuracy of the calculations of
particulate emissions at page
2 of Camp.
Ex.
#7, there can be
no doubt that to the extent of the Boiler’s operations,
it did exceed
the standards of both the old Rule 2—2.53 and Rule 203(g) (1) (B), and
Section 9(a)
of the Act.
However,
the Supreme Court, in Commonwealth
Edison Company v. Pollution Control Board,
62 Ill
2d 494,
343 N.E.
2d 459
(1976)
remanded to the Board Rule 203(g) (1)
of the Air
Pollution Control Regulations.
It would therefore be inappropriate
for the Board to find a violation of that Rule in this case.
It is also established that no operating permit had
been obtained for Boiler
#2.
As the Board Order PCB 73-209 states,
the City did apply for operating permits but the application was
denied because of the calculated particulate violations.
There
is no doubt that the City did operate in violation of Rule
103(b)
(2)
of the Air Pollution Control Regulations and Sections
9(a)
and
(b)
of the Act.
As for the violation of the particulate standard from July
1,
1970 through May
30,
1975 the chief factor of mitigation is the
apparent good faith effort which the City made to retire its
coal—fired boilers.
The major problem
was
solved by the electrical
interconnection with Illinois Power Company operative on March
28,
1976
(R.
62). The City has previously attempted to purchase a
diesel engine to replace the coal—fired boilers but the bond
issue failed
(R.
58).
Coupled with the high cost of an
electrostatic precipitator and problems with fuel allocations
which made conversion uncertain,
consideration of the 33(c)
factors show strong mitigation.
A municipal power plant carries
a high social and economic value where alternative sources of
electricity are simply not available.
Also important is the fact
that the operation of this boiler apparently did not cause any
citizen complaint
(R.
61).
Given
these facts the Board finds
that a penalty would not aid in the enforcement of the Act in
this particular case.
For the same reasons the Board finds
no penalty advisable
for the City’s failure to obtain an operating permit.
It is
noted that the City did apply
for a permit on January
23,
1973,
which is prior to the period of the violation found.
It would be
unnecessary in this case to penalize the City for failing to
conform to a standard which has already been found above
to have
represented an unreasonable hardship.
23—116
—3—
The City of Breese has shown good faith.
The City’s inability
to raise the funds necessary to allow the retiring of Boiler
#2
is understandable in view of the financial difficulties encountered
by most small municipalities.
The establishing of an interconnection
was also carried out in good faith.
The City has now committed
to converting Boiler #2 to oil
(R.
57).
Respondent’s Exhibit No.
1
is an estimated completion schedule for that project.
Installation
is estimated to be completed on December 20,
1976, at which time
the City should be in compliance with the Board’s Regulations.
The
Board will require the City to submit to the Agency, within 60 days,
a proposal for Boiler #2 so that a variance or a permit may be
obtained.
This Opinion constitutes the Board’s findings of fact and
conclusions of law.
ORDER
1.
Respondent City of Breese
is hereby found
to have violated
Rule 2—2.53
of the old Air Rules, Rule 103(b) (2)
of the
Air Pollution Control Regulations, and Section 9(a)
and
(b)
of the Environmental Protection Act.
2.
That portion of the Complaint alleging violation of
Rule 203(g) (1) (B)
of the Air Pollution Control Regulations
is hereby dismissed.
3.
If Respondent City of Breese operates Boiler
#2
prior to its conversion to oil the City of Breese
shall promptly submit a report to the Agency detailing
the extent of the emergency and the resulting operations.
4.
Respondent City of Breese shall, within 60 days of the
date of this Order, submit to the Agency a proposal
regarding the conversion of Boiler
#2 from coal
to oil
fuel so that a permit or a variance may be obtained.
IT IS SO ORDERED.
I, Christan L. Moffett,
Clerk of the Illinois Pollution Control
Boar~~
hereby certify the above Opinion and Order were adopted on the
_______day of July,
1976 by a vote of
~-O
Christan L. Moffett,
Illinois Pollution Co
1 Board
23
—
117