ILLINOIS POLLUTION CONTROL BOARD
April 14, 1977
STEPAN CHEMICAL COMPANY,
Petitioner,
v.
)
PCB 76—161
ENVIRONMENTAL PROTECTION AGENCY,
)
)
Respondent.
Mr. Harley Hutchins, Attorney, appeared for the Petitioner;
Ms.
Kathryn Sheehan Nesburg, Attorney, appeared for the Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Zeitlin):
This matter is before the Board on a Petition for Variance
filed by the Stepan Chemical Company
(Stepan) on May 21,
1976.
That Petition requested relief from the particulate standards
in
Rules 203(a)
and 203(b), and the carbon monoxide limitations in
Rule 206(c)
of Chapter
2: Air Pollution,
of this Board’s Rules and
Regulations.
Stepan also sought relief from the organic emission
limitations
in Rule 205(f)
and 205(g) (1) (c), also of Chapter
2, or
in the alternative
a ruling that these limitations do not apply to
the subject facility.
Pursuant to an objection filed by the Envi-~
roninental Protection Agency
(Agency)
on May 27,
1976,
the matter
was set for hearing.
An Amended Petition was filed by Stepan on September 28,
1976,
which extended certain dates contained in the original Petition’s
compliance schedule by several months,
as a result of delays caused
by
a strike.
A further amendment to StepaxYs Petition was entered
at hearing,
(Cornpl.
Ex.
1,
R.
8),
in which Stepan further extended
the period for compliance.
A final amendment was made orally at
hearing,
(R.
5), by which Stepan admitted the applicability of
Rule 205(f)
to the organic emission from its facility, although it
continued to contest the applicability of Rule 205(g) (1) (c),
(id.).
The Agency’s original Recommendation was filed on September
3,
1976.
The Agency’s Recommendation was modified slightly at hearing,
and a
formal Amended Recommendation was filed on March
3,
1977.
25
—
281
—2—
A hearing was held in the matter on January 10,
1977,
at the
Will County Courthouse,
in Joliet.
Witnesses were presented by both
parties, although the Agency’s presentation was limited to expert
testimony on the definition of “petrochemicals,” and the applica-
bility of rules limiting emissions from “petrochemical processes”
and “petrochemical manufacturing processes” to Stepan’s facility.
Although special notice
(in addition to the publication and notice
normally required) was given to one citizens’
group, no members of
the public participated at the hearing.
Stepan’s Petition concerns emissions
from its phthalic anhydride
manufacturing process at its Nilisdale Plant,
located on the Des
Plaines River
in Will County.
Stepan’s Milisdale facility is
described in a prior Variance case, and that description need not
be repeated here.
Stepan Chemical Co.
v. EPA, PCB 74-425,
17 PCB
105
(May
22,
1975).
In fact,
a portion of the relief requested
here is an extension of the Variance granted in PCB 74-425 with
regard to the carbon monoxide limitations of Rule 206 (c).
Phthalic anhydride is produced at the Milisdale Plant by the
partial oxidation of O-Xylene in the presence of a catalyst.
Stepar~
produced 32,935,000 pounds of phthalic anhydride, utilizing
34,456,000
pounds of O-Xylene,
in 1975.
Waste gases from the process, exiting
at approximately 140°F.,with little heat value, are vented to the
atmosphere through a 75-foot stack.
The composition of the waste
gases, and the applicable emission limits, are as follows:
WASTE
GPS
REtWT
REWIRED
OI4PCt~1ENT
EMISSICNS
LIMITATICES
REGUlATION
REDUCTION*
CO
5,000 PPM
200
PPM
206(c)
96
(860 lb./hr.
)
*
(arrected
to
50
excess
air)**
hydrocarbons
398 lb./hr.
*
8
lb./hr.
205 (f)
85
(per
(including
40 lb./hr.
205(f) (1) (A)
as particulate)
hydrocarbons
600
PR4*
100
PPM
205(g) (1) (C)
78
(equivalent
nethane)
particulate
40 lb./hr.
*
29.5
lb./hr.
203 (a)
40
*
Per
EPA
lecximendation,
INI 7-10,
apparently using 2\rrended
Petition,
¶5.
See,
R.
50.
For 100
operation ~nissions,see R.
19-20.
**
The
applicability
of the “50
Excess
Air”
correction
to
this
type of facility
is presently an issue in a
pending
Pegulatory
proceeding, R75—9, R76—8,-12,-13.
25
—
282
_3_.
In PCB 74-425,
the Board found that no technically feasible and
economically reasonable method for compliance with the carbon monoxide
limitation of Rule 206(c)
then existed for Stepan’s phthalic anhydride
plant.
The Board granted a “research and development” Variance,
permitting Stepan to continue its investigation and development of
a ‘cold catalytic” compliance technology.
Stepan was,
at that time,
funding a research program at Northwestern University,
including
bench and later pilot scale study of the new technology.
A more
complete description of that research program, and an analysis of
the inapplicability of incineration as a control measure for Stepan’s
plant, may be found in the Board’s previous Variance Opinion in
PCB 74—425,
supra,
17 PCB at 106—108.
Subsequent to the entry of our Order in PCB 74-425, while the
cold catalytic oxidation study continued, Stepan was approached by
the DuPont Company regarding a new control technology which DuPont
felt would be applicable to the Millsdale Plant.
The DuPont Torvex
catalytic reactor utilizes precious metal
(platinum) deposited on
a ceramic honeycomb to remove both carbon monoxide and hydrocarbons
from the exhaust stream,
(R.
70).
This process is not a “cold”
catalytic process;
though it will require elevation of the exhaust
gases above their 140°F.exit temperature,
it will not require the
excessive amounts of fuel for incineration,
as discussed in PCB 74—425.
Instead, the DuPont process
(called a “combustor’~) utilizes waste
heat and steam from the phthalic anhydride process itself, along
with heat exchange,
to achieve operating temperatures of approximately
500°to 525°F., (e.g.,
R.
42).
Except for startup, no additional
fuel is required.
An additional significant advantage of the combustor is that it
will treat the entire emission problem at Stepan’s Milisdale Plant,
rather than only the carbon monoxide emissions,
or only the organic
emissions,
(R.
41).
The combustor will remove carbon monoxide with
an efficiency of
95 per cent or more,
approaching 100 per cent,
(R.
72).
The efficiency with regard to organics
is stated to be “above 85 per
cent,”
(id.).
Because of the operating temperatures involved, all
organics are expected to be in the vapor phase, with the result that
there will
be no particulate emissions,
(fl. 79).
In
fact,
a principal
use of the Torvex unit has been hydrocarbon emission control.
A final advantage of the combustor
is catalyst life.
Unlike
the cold catalytic system researched at Northwestern University,
the catalyst is guaranteed by DuPont for a one-year period, yet the
parties expect catalyst life of five years or better,
(R. 81—83).
25
—
283
—4—
As amended,
Stepan’s timetable for compliance called for a
decision by February
1,
1977, as to whether the combustor or some
other control technology will be used at the Milisdale Plant,
(Pet.
Ex.
6).
Petitioner’s post-hearing Brief indicates that the
combust.or was chosen.
Petitioner’s timetable then calls
for the
following:
April
1,
1977
Complete System Final Design
and Approval Drawings.
April
1,
1978
Equipment Delivery.
July 1,
1978
System Installation.
August 15,
1978
System Start-Up and Debugging.
The effect of Stepan’s present emissions of CO were detailed
in the previous Variance Opinion,
PCB 74—425, supra, and need not
be repeated.
The Agency’s Recommendation in this matter noted that
the nearest monitors for particulates, more than five miles from the
Millsdale Plant,
(Rec.,
¶18), showed the following annual geometric
mean concentrations for 1975:
Rockdale,
97; Wilmington,
69.
The
only Will County monitor for ozone,
located in Joliet, indicated
77 violations of the 0.08 ppm maximum.
As the Board found
in the previous Variance case, supra,
17
PCB at 108:
To deny the variance in the instant action
would require utilization of existing control
technology which not only would be expensive,
but would have an adverse impact upon energy
demand and the environment.
Such a ruling
would impose an arbitrary and unreasonable
hardship upon Stepan while actually injuring
the public and environment.
Throughout
this
proceeding,
as in the
previous
case,
the Agency
has
recommended that the requested Variance be granted.
We agree.
Stepan has demonstrated a continuing effort to achieve compliance
with the carbon monoxide Regulations, to the point of developing new
technology.
It has extended that effort to the other emissions in
jssue here, despite the fact that the applicability of the relevant
Regulations
is honestly debatable.
Stepan has now developed tech-
nology which will allow compliance within a reasonable period of
time,
and is proceeding expeditiously to implement a suitable program.
25
—
284
—5—
With regard to the application of Rule 205(g) (1)
(C)
to Stepan’s
facility, we note that Stepan is
a party to a pending Regulatory
proceeding which could resolve this issue.
In R75-9,
R76-8,--12,-13,
Carbon Monoxide,
the Board has been requested to separately define
“organic chemical partial oxidation” processes.
Since the existence
of such a definition may resolve finally the application of Rule
205(g) (1) (c) to Stepan’s facility, we decline to review our decision
in Sherwin-Williams Co.
v. EPA
(Dec.
18,
1975).
Under the circum-
stances, we need not decide the narrow legal issue of the Rule’s
applicability under the tests set out in Sherwin-Williams.
Id.,
Opinion at
3.
We shall grant the variance, pending decision in
the Regulatory matter.
Finally, we note that Stepan plans to expand phthalic anhydride
production capacity at the Millsdale Plant,
(R.
26).
Inasmuch as
the parties agree that the control system to be constructed using
the DuPont cornbustor technique will be adequate to control the
emissions from such expanded operations,
(R.
51), we find that this
planned expansion does not affect our judgement concerning this
Variance.
We shall grant the requested Variance, conditioned upon the
compliance schedule indicated in Petitioner’s Exhibit
6.
We
shall
continue in effect the $25,000 performance bond required in the
previous Variance,
although it shall now cover construction under
the new compliance plan.
We shall also enter standard reporting
and certification requirements.
In addition, we shall release
Stepan from the research requirements contained in the prior
Variance.
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter.
ORDER
IT IS THE ORDER OF THE POLLUTION CONTROL BOARD that:
1.
Petitioner Stepan Chemical Company be granted a Variance
from Rules
203(a),
205(f),
205(g) (1) (C),
and 206(c)
of Chapter
2:
Air Pollution,
from May 22,
1976 until August 15,
1978,
subject to
the following conditions:
a.
Petitioner shall comply with the construction
schedule for its catalytic reactor system as
set forth in the accompanying Opinion and shall
apply to the Environmental Protection Agency
for all necessary construction and operating
permits.
25
—
285
—6—
b.
Petitioner shall, on or about the 15th day of each
month subsequent
to the entry of this Order, submit
to the Environmental Protection Agency a written
report detailing all progress towards compliance,
such report to be submitted to:
Environmental Protection Agency
Control Program Coordinator
2200 Churchill Road
Springfield, Illinois
62706
c.
Petitioner shall, within twenty-eight
(28) days
of the date of this Order,
continue in effect
its performance bond in the amount of Twenty—Five
Thousand Dollars
($25,000.00),
in a form satis-
factory to the Environmental Protection Agency,
to insure compliance with the control program
detailed in the accompanying Opinion.
Such bond
shall be submitted to the Environmental Protection
Agency at the address given in subparagraph
(b)
above.
d.
The Variance granted herein from Rule 205(g) (1) (c)
shall terminate upon final Board action in the
pending Regulatory proceeding R75-9,
R76-8,-12,-l3,
if a new or amended definition is adopted affecting
Petitioner’s manufacturing process,
in conformity
with the Board’s Opinion in this matter, ~pra.
e.
Petitioner shall, within twenty-eight
(28) days of
the date of this Order,
execute and forward to the
Environmental Protection Agency,
at the address shown
in subparagraph
(b)
above,
a Certificate of Acceptance
in the following form:
CERTIFICATE OF ACCEPTANCE
I,
(We),
_______
_______________—
having read
the Order of
the
Illinois PolluLion Control
Bo~ircI
in
case No. PCB
76-161, understand and accept said Order,
realizing that such acceptance renders all terms and
conditions thereto binding and enforceable.
SIGNED
TITLE
DATE
25
—
286
—7—
2.
Petitioner Stepan Chemical Company be released from the
research and development program required by our Order in Stepan
Chemical Company v. EPA, PCB 74-425, regarding cold catalytic
oxidation.
Mr. Jacob D.
Duinelle dissents.
Mr.
Irvin G. Goodman concurs.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board,
hereby certify the
bove Opinion and Order were
adopted on the
/~t”
day of
_________,
1977, by a vote of
4/_/
trol Board
25
—
287