ILLINOIS POLLUTION CONTROL
BOARD
September 1, 1977
SNTRAL
 ILLINOIS
 PUBLIC SERVICE
 )
COMPANY,
 )
Petitioner,
cVrPOITMENTAL
 PROTECTION
 AGENCY,
 )
Respondent.
MIt.
 THOMAS
 It
 COCHRAN,
 OF
 SORLING,
 NORTHRUP,
 HANNA,
 CULLEN
 AND
COCHRAN,
 REPRESENTED PETITIONER;
HONORABLE
 WILLIAM
 J.
 SCOTT,
 ATTORNEY
 GENERAL,
 BY
 JOHN
 VAN
 VRANKEN~
REPRESENTED
 RESPONDENT.
OPINION
 AND
ORDER
 OF
 THE
 BOARD
 (by
 Mr.
 Goodman):
On
 May
 31,
 1977,
 Central
 Illinois
 Public
 Service
 Coepany
 (CIPS)
filed
 a
 Petition
 for
 Variance
 before
 the
 Board
 seeking
 temporary
relief from
 the
 sulfur
 dioxide
 removal
 requirements ordered
by
the
Board
 in a prior
 case, PCB 75-~382.
 CIPS filed
supplemental
 in~for~
nation
 on
 June 6,
 1977.
 The Environmental
 Protection
 Agency
(Agency)
 filed its
 recommendation on
 June
 29,
 1977,
 A
 hearing
 was
held
 on July
 6,
 1977,
 in Newton,
 Illinois.
 No citizen
witnesses
testified.
cIps owns
 and operates an electric
 generating
facility
 known
as
 the Newton Power
 Station in
 Jasper County.
 Newton
Unit
 I
 is
rated at 550 MW
 and is scheduled for
 commercial
operation
 on
December 1,
 1977.
 Newton Unit
 2 will also be
 rated
at
 550
 MW
and
is
 scheduled for
 service
 in 198L
On January
 14, 1976, the Board
 found
 that
CIPS
 had
 violated
conditions of a
 construction permit and
 Section 9(b)
 of
 the
 Act
 by
allowing
 construction
 work
 to
 be done toward
erection
 of
 a
coal~
fired
 boiler whose
 emissions
 would
 violate
 Rule 204(a) (1)
 of
 the
 Air
~451-
~7-363
Pollution Regulations.
 The
Board ordered
CIPS
to
comply
 with
 the
terms of the
 Settlement Proposal submitted by the parties.
 Item 17
through Item 21
 of that Proposal
set
forth the conditions
 from which
CIPS now seeks a
 variance,
 Generally,
 the order
required
 CIPS to
have a SO2
 removal system instaJ
led and fully
operational
 by the
time Unit
 1 at Newton begins serv~ce.
 It was the
 intention of CIPS
at the time to install
 either
 a
lime scrubbing system
or
 a double
alkali scrubbing
 system.
 CIPS
agreed that the
system
 chosen would
treat the flue gas
 to meet the 1,2
lbs./106 BTU
sulfur
 dioxide
emission standard.
CIPS chose
 and began construction
o:~ double
alkali flue gas
desulfurization system
on
Newton Unit
1,
 :~PSstates
and the
Agency agrees
 that the double alkali
system is
a “second generation”
type of SO~remdval
 system and shows
marked
advances
 in performance
and reliability over
 ~first generation”
 lime/limestone
 FGD systems.
The
 FGD system to
 be applied to Newton
Unit I
 is the
 first appli-
cation of the
 double alkali system
on a ‘arge
utility
 boiler.
 CIPS
alleges and the Agency
 agrees that,
because
this
 application is the
first of its
 kind on a large utility
boiler,
cost and
 construction
schedules forecasted in
 August,
1975 were not
accurate.
 The original
cost projection was
 $47 million, and
the
anticipated
 completion date
was December
 1,
 1977.
 CIPS now
contemplates
completion
 of the FGD
system by November,
 1979,
In its petition,
 CIPS outlines the major design
 changes and
significant increases
 in
 cost which preclude
 it
from
 adhering to
the original target
 date,
 The project
 is
now
 anticipated to cost
$108 million
 more
 than double the original cost
 estimate.
 Studies
undertaken at the beginning
 of the project resulted
 in a major
process change
 in the regenerated liquor loop affecting
 seven major
components and their
 associated piping and instrumentation.
 CIPS
indicates that, because
 this system is
the
first
 of
 its
 kind,
redundant and conservative
 design
 have been built
 into the system.
CIPS also indicates that
 this past severe winter
 weather and man-
power shortages have
 served to further delay
 completion of the
project.
 Load projections and
 economics dictate
 that the generating
unit
 be commercially
available
 on
 the
 December
 1
 schedule.
 However,
CIPS alleges that early
 completion of the FGD system
 is
 not a viable
option.
During the
 period of the requested variance, CIPS
 calculates
that its uncontrolled
 SO2 emissions,
 assuming Newton
 Unit
 1 will
burn 230 tons per
 hour of
 2.8
 sulfur content coal,
 will be 4.6 lb/
MM BTU.
 Modeling and
 monitoring studies conducted by
 CIPS as well
as a dispersion
 modeling study conducted by the Agency
 conclude that
emissions from Newton
 Unit
I
will not cause or contribute
 to a
i3~
—3—
violation of the National Primary and Secondary Ambient Air
Quality Standards for SOD.
 The Board notes, however, that the
information on these stuaies submitted by CIPS and by
 the Agency
was rather incomplete.
Should the Board deny the requested variance, CIPS would be
forced to burn low sulfur coal
 until
 start-up of its FGD system.
CIPS indicates
 in its petition that the total increased expense
to the Company for burning out—of-state low sulfur coal as opposed
to high sulfur Illinois coal until November, 1979, would be
$20,978,000.00.
 An additional cost would likely be incurred in
order to restore the efficiency
of
the electrostatic precipitator,
which could be degraded because of the high ash resistivity normally
associated with low sulfur coal.
 One possible solution to this
problem would be injection of sulfur trioxide into the gas stream of
the precipitator, which could cost from
 $2
 to $10 per kilowatt.
 CIPS
indicates that in addition to degraded precipitator performance,
other technical difficulties could result from
 the use
 of low sulfur
coal
 in
 a
unit
 designed to burn high sulfur coal.
 The Company is
concerned about the pulverizer mill capacity affected by the coal’s
grindability and changes
 in heat transfer affected by
 ash slagging
characteristics.
CIPS furthermore alleges that completion and start-up of
 the
FGD system earlier than November, 1979,
 is not feasible because of
cash flow difficulties, difficulties in retaining sufficient con-
struction craft labor in the Newton area,
 and the risk of problems
created by the accelerated completion of this first-of-its-kind
installation.
 Because of
the
lack of experience in this type of
installation, CIPS has already encountered several unanticipated
problems resulting in delay.
 CIPS indicates that completion of the
FGD system is scheduled for June
 1,
 1979,
 but that during the period
from June to November,
 1979,
 the system will be operated
 in a start-
up and shake-down mode.
 Therefore, CIPS indicates,
 the 1.2 lb/MM
BTU will be met during part of this
period,
and partial emission
reduction will occur during a siqnificant portion of this period.
The Board finds that
 a denial of CTPS
 wiriance request would
impose an arbitrary and unreasonable hardship upon
 the company.
The Board agrees that CIPS has proceeded diligently
 in its
 construc-
tion program and that, considering that this
 is the first
 application
 of this type of FGD system to a large utility boiler,
 the delay has
been reasonable.
 Because of the apparent lack of a threat to ambient
air quality and the costs and technical difficulties associated
 with
burning
 low sulfur
 cc~a1, a
 vari)a:I~s
 ~s
 ~
 ~t.u1
 The
 Board
 also
finds
 that,
 due
 to
 the
 manpow~r..shurtag~
 in,
 the
 Newton
 area
 and
 the
need
 for
 more
 time
 to
 instal.~’
 this first~’of~~its
 k~1.n~system
 than
would ordinarily be needed,, the
full~,variance
 recuested is warranted.
In
 addition,
 we
 find
 that
 the
two
 yeaas~ experience
SIPS
 will have
in operation of Unit
 I
 prior
 t
 start-up of
the
 FOD
 system
 will
 be
beneficial to the smooth
 operatio~’i.of the system.
 The Board, there-
fore, grants CIPS
 a variance fromPCB 75—382
until November
 3,
 1979,
subject to the conditions belQw.
This Opinion consti~tutes~
 ~
 Board~
 findings
 of
 facts
 and
conclusions of law in this matter.
ORDER
It is the Order of the Poliuti~nC~nti~ol
 Board that SIPS
 be
granted a variance from the Board
~G~der
 ~n
 PCB
 75-382
 in order to
operate Newton Unit
 1
 in violation ci whe
.L2 lb/MM
BTU SO~emis-
sion standard until November
 3,
 1.9~9, subject to the following
conditLns:
1.
 CIPS will
 subi’nit
quarterly
 repoits
until
June
 1, 1979 describing the ~oqress
 being made
toward the completion of the DAFGD: Systen..
2.
 CIPS will submit monthly
~reports
 from
June
 1,
1979 until November
 3,
 1979, de’~cribingthe progress
being made in making the DAFG~System commercially
operational.
3.
 CIPS
 will
 subrriit
 ‘to
 th~ Agencv~ on
 or
before
November
 3,
 1977,
 ,ar’opecat~ng
 erm’~ttrapplicatcon for
Newton Unit 1, said application to. include the
re-
quisite stack testing data and infqr~nation.
Mr.
 Dumelle
 dissents,
I,
 Christan
 L.
 Moffett,
 ,C1erk~of”th~
lllino3s
 Pollution
 Control
Board,
 hereby
 certify
 t
 e
 ab~ove’
Opin±on’and
 Order
 were
 ~dopted
 on
the
 /~
 day
 of~
 .
 ,
 l977~y.
 a
 vote
 of
 ‘j—/
Christan
 It
 Moffe&~t7J~1erk
Illinois
 Poilutiotr-1~Sntrol
 Board
~2/
 :C~’