ILLINOIS POLLUTION CONTROL
    BOARD
    September 1, 1977
    SNTRAL
    ILLINOIS
    PUBLIC SERVICE
    )
    COMPANY,
    )
    Petitioner,
    cVrPOITMENTAL
    PROTECTION
    AGENCY,
    )
    Respondent.
    MIt.
    THOMAS
    It
    COCHRAN,
    OF
    SORLING,
    NORTHRUP,
    HANNA,
    CULLEN
    AND
    COCHRAN,
    REPRESENTED PETITIONER;
    HONORABLE
    WILLIAM
    J.
    SCOTT,
    ATTORNEY
    GENERAL,
    BY
    JOHN
    VAN
    VRANKEN~
    REPRESENTED
    RESPONDENT.
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Goodman):
    On
    May
    31,
    1977,
    Central
    Illinois
    Public
    Service
    Coepany
    (CIPS)
    filed
    a
    Petition
    for
    Variance
    before
    the
    Board
    seeking
    temporary
    relief from
    the
    sulfur
    dioxide
    removal
    requirements ordered
    by
    the
    Board
    in a prior
    case, PCB 75-~382.
    CIPS filed
    supplemental
    in~for~
    nation
    on
    June 6,
    1977.
    The Environmental
    Protection
    Agency
    (Agency)
    filed its
    recommendation on
    June
    29,
    1977,
    A
    hearing
    was
    held
    on July
    6,
    1977,
    in Newton,
    Illinois.
    No citizen
    witnesses
    testified.
    cIps owns
    and operates an electric
    generating
    facility
    known
    as
    the Newton Power
    Station in
    Jasper County.
    Newton
    Unit
    I
    is
    rated at 550 MW
    and is scheduled for
    commercial
    operation
    on
    December 1,
    1977.
    Newton Unit
    2 will also be
    rated
    at
    550
    MW
    and
    is
    scheduled for
    service
    in 198L
    On January
    14, 1976, the Board
    found
    that
    CIPS
    had
    violated
    conditions of a
    construction permit and
    Section 9(b)
    of
    the
    Act
    by
    allowing
    construction
    work
    to
    be done toward
    erection
    of
    a
    coal~
    fired
    boiler whose
    emissions
    would
    violate
    Rule 204(a) (1)
    of
    the
    Air
    ~451-
    ~7-363

    Pollution Regulations.
    The
    Board ordered
    CIPS
    to
    comply
    with
    the
    terms of the
    Settlement Proposal submitted by the parties.
    Item 17
    through Item 21
    of that Proposal
    set
    forth the conditions
    from which
    CIPS now seeks a
    variance,
    Generally,
    the order
    required
    CIPS to
    have a SO2
    removal system instaJ
    led and fully
    operational
    by the
    time Unit
    1 at Newton begins serv~ce.
    It was the
    intention of CIPS
    at the time to install
    either
    a
    lime scrubbing system
    or
    a double
    alkali scrubbing
    system.
    CIPS
    agreed that the
    system
    chosen would
    treat the flue gas
    to meet the 1,2
    lbs./106 BTU
    sulfur
    dioxide
    emission standard.
    CIPS chose
    and began construction
    o:~ double
    alkali flue gas
    desulfurization system
    on
    Newton Unit
    1,
    :~PSstates
    and the
    Agency agrees
    that the double alkali
    system is
    a “second generation”
    type of SO~remdval
    system and shows
    marked
    advances
    in performance
    and reliability over
    ~first generation”
    lime/limestone
    FGD systems.
    The
    FGD system to
    be applied to Newton
    Unit I
    is the
    first appli-
    cation of the
    double alkali system
    on a ‘arge
    utility
    boiler.
    CIPS
    alleges and the Agency
    agrees that,
    because
    this
    application is the
    first of its
    kind on a large utility
    boiler,
    cost and
    construction
    schedules forecasted in
    August,
    1975 were not
    accurate.
    The original
    cost projection was
    $47 million, and
    the
    anticipated
    completion date
    was December
    1,
    1977.
    CIPS now
    contemplates
    completion
    of the FGD
    system by November,
    1979,
    In its petition,
    CIPS outlines the major design
    changes and
    significant increases
    in
    cost which preclude
    it
    from
    adhering to
    the original target
    date,
    The project
    is
    now
    anticipated to cost
    $108 million
    more
    than double the original cost
    estimate.
    Studies
    undertaken at the beginning
    of the project resulted
    in a major
    process change
    in the regenerated liquor loop affecting
    seven major
    components and their
    associated piping and instrumentation.
    CIPS
    indicates that, because
    this system is
    the
    first
    of
    its
    kind,
    redundant and conservative
    design
    have been built
    into the system.
    CIPS also indicates that
    this past severe winter
    weather and man-
    power shortages have
    served to further delay
    completion of the
    project.
    Load projections and
    economics dictate
    that the generating
    unit
    be commercially
    available
    on
    the
    December
    1
    schedule.
    However,
    CIPS alleges that early
    completion of the FGD system
    is
    not a viable
    option.
    During the
    period of the requested variance, CIPS
    calculates
    that its uncontrolled
    SO2 emissions,
    assuming Newton
    Unit
    1 will
    burn 230 tons per
    hour of
    2.8
    sulfur content coal,
    will be 4.6 lb/
    MM BTU.
    Modeling and
    monitoring studies conducted by
    CIPS as well
    as a dispersion
    modeling study conducted by the Agency
    conclude that
    emissions from Newton
    Unit
    I
    will not cause or contribute
    to a
    i3~

    —3—
    violation of the National Primary and Secondary Ambient Air
    Quality Standards for SOD.
    The Board notes, however, that the
    information on these stuaies submitted by CIPS and by
    the Agency
    was rather incomplete.
    Should the Board deny the requested variance, CIPS would be
    forced to burn low sulfur coal
    until
    start-up of its FGD system.
    CIPS indicates
    in its petition that the total increased expense
    to the Company for burning out—of-state low sulfur coal as opposed
    to high sulfur Illinois coal until November, 1979, would be
    $20,978,000.00.
    An additional cost would likely be incurred in
    order to restore the efficiency
    of
    the electrostatic precipitator,
    which could be degraded because of the high ash resistivity normally
    associated with low sulfur coal.
    One possible solution to this
    problem would be injection of sulfur trioxide into the gas stream of
    the precipitator, which could cost from
    $2
    to $10 per kilowatt.
    CIPS
    indicates that in addition to degraded precipitator performance,
    other technical difficulties could result from
    the use
    of low sulfur
    coal
    in
    a
    unit
    designed to burn high sulfur coal.
    The Company is
    concerned about the pulverizer mill capacity affected by the coal’s
    grindability and changes
    in heat transfer affected by
    ash slagging
    characteristics.
    CIPS furthermore alleges that completion and start-up of
    the
    FGD system earlier than November, 1979,
    is not feasible because of
    cash flow difficulties, difficulties in retaining sufficient con-
    struction craft labor in the Newton area,
    and the risk of problems
    created by the accelerated completion of this first-of-its-kind
    installation.
    Because of
    the
    lack of experience in this type of
    installation, CIPS has already encountered several unanticipated
    problems resulting in delay.
    CIPS indicates that completion of the
    FGD system is scheduled for June
    1,
    1979,
    but that during the period
    from June to November,
    1979,
    the system will be operated
    in a start-
    up and shake-down mode.
    Therefore, CIPS indicates,
    the 1.2 lb/MM
    BTU will be met during part of this
    period,
    and partial emission
    reduction will occur during a siqnificant portion of this period.
    The Board finds that
    a denial of CTPS
    wiriance request would
    impose an arbitrary and unreasonable hardship upon
    the company.
    The Board agrees that CIPS has proceeded diligently
    in its
    construc-
    tion program and that, considering that this
    is the first
    application
    of this type of FGD system to a large utility boiler,
    the delay has
    been reasonable.
    Because of the apparent lack of a threat to ambient
    air quality and the costs and technical difficulties associated
    with

    burning
    low sulfur
    cc~a1, a
    vari)a:I~s
    ~s
    ~
    ~t.u1
    The
    Board
    also
    finds
    that,
    due
    to
    the
    manpow~r..shurtag~
    in,
    the
    Newton
    area
    and
    the
    need
    for
    more
    time
    to
    instal.~’
    this first~’of~~its
    k~1.n~system
    than
    would ordinarily be needed,, the
    full~,variance
    recuested is warranted.
    In
    addition,
    we
    find
    that
    the
    two
    yeaas~ experience
    SIPS
    will have
    in operation of Unit
    I
    prior
    t
    start-up of
    the
    FOD
    system
    will
    be
    beneficial to the smooth
    operatio~’i.of the system.
    The Board, there-
    fore, grants CIPS
    a variance fromPCB 75—382
    until November
    3,
    1979,
    subject to the conditions belQw.
    This Opinion consti~tutes~
    ~
    Board~
    findings
    of
    facts
    and
    conclusions of law in this matter.
    ORDER
    It is the Order of the Poliuti~nC~nti~ol
    Board that SIPS
    be
    granted a variance from the Board
    ~G~der
    ~n
    PCB
    75-382
    in order to
    operate Newton Unit
    1
    in violation ci whe
    .L2 lb/MM
    BTU SO~emis-
    sion standard until November
    3,
    1.9~9, subject to the following
    conditLns:
    1.
    CIPS will
    subi’nit
    quarterly
    repoits
    until
    June
    1, 1979 describing the ~oqress
    being made
    toward the completion of the DAFGD: Systen..
    2.
    CIPS will submit monthly
    ~reports
    from
    June
    1,
    1979 until November
    3,
    1979, de’~cribingthe progress
    being made in making the DAFG~System commercially
    operational.
    3.
    CIPS
    will
    subrriit
    ‘to
    th~ Agencv~ on
    or
    before
    November
    3,
    1977,
    ,ar’opecat~ng
    erm’~ttrapplicatcon for
    Newton Unit 1, said application to. include the
    re-
    quisite stack testing data and infqr~nation.
    Mr.
    Dumelle
    dissents,
    I,
    Christan
    L.
    Moffett,
    ,C1erk~of”th~
    lllino3s
    Pollution
    Control
    Board,
    hereby
    certify
    t
    e
    ab~ove’
    Opin±on’and
    Order
    were
    ~dopted
    on
    the
    /~
    day
    of~
    .
    ,
    l977~y.
    a
    vote
    of
    ‘j—/
    Christan
    It
    Moffe&~t7J~1erk
    Illinois
    Poilutiotr-1~Sntrol
    Board
    ~2/
    :C~’

    Back to top