ILLINOIS POLLUTION CONTROL BOARD
August 18,
 1977
ENVIRONMENTAL PROTECTION AGENCY,
Complainant,
v.
 )
 PCB 76—57
DEAN PENN and WALTER DEEMIE,
Respondents.
Mr. John Vafi Vranken, Assistant Attorney General, Attorney
for Complainant
Mr. Dean Penn and Mr. Walter Deemie, appeared pro se
OPINION AND ORDER OF THE BOARD
 (by Mr. Young):
This matter comes before the Board on the Complaint filed
on March
 1, 1976,
 by the Environmental Protection Agency
charqing Dean Penn and Walter Deemie with various violations
of the Act and regulations in the operation of a refuse disposal
site located in Peoria County.
 Specifically, Dean Penn is
charged with owning and Walter Deemie with operating a refuse
disposal site from July
 27,
 1974, until May
 10, 1976, without
the requisite operating permit in violation of Rule 202(b) (1)
and Section 21(e)
 of the Act.
 Respondents are charged with
failing to place cover on all exposed refuse at the end of the
day’s operation on seventeen different occasions
 in violation
of Rule 305(a)
 and Section 21(b)
 of the Act.
 Finally, Respondents
are charged with causing or allowing open burning at the site on
January
 8,
 1976,
 in violation of Rule
 311 and Section
 21(b)
 of
 the Act.
The Board notes that Respondents
 are not unfamiliar with
proceedings before this Board.
 They have been involved in one
prior enforcement proceeding
 (PCB 72-189,
 5 PCB 159)
 and one
variance proceeding
 (PCB 72-432,
 6 PCB 669), both of which involved
this same landfill site.
 The final order in the enforcement pro-
ceeding, based upon a Settlement Stipulation, directed Respondents
to permanently close the site no later than December
 31, 1972,unless
an operating permit was obtained from the Agency.
 When permit dis-
cussions thereafter broke down with the Agency,
 evidently over the
question whether a clay liner should be installed
 to prevent
leaching conditions,
 the Respondents filed the aforementioned
variance petition which basically souqht permission
 to continue
~
~2&-317
(~
 )
 ,~
operation of the site witriout a ~orc~it from the Agency and in
the same manner as the operation had been conducted in the past.
This variance request was denied
 because
 of the fears expressed
regarding a continued leachate condition
 (6
 PCB
 66~
 670)
At
 the
 hearing
 held
 in
 the
 instant
 matter,
 Complainant
attempted to establish several relevant facts through operation
of Rule
 314 of our Procedural
 Rules
 which
 requires, among other
things,
 that
 the
 answers
 to
 request for admissions be sworn.
ComDlainant
 had
 filed
 a
 request
 in::
 admission,
 and
 although
 both
Respondents
 filed
 answers
 thereto,
 neither
 was
 sworn
 as
 required
by
 our
 rule.
 Because
 of
 this
 defect~
 Complainant
 argued
 the
answers
 should
 be
 deemed
 as
 not
 havina
 been
 filed,
 thus
 resulting
in
 the
 admission
 of
 the
 requested
 f&~cts~
 The
 Board
 feels
 other-
wise.
 Although the answers were clearly defective, absent the
filing
 of
 a
 Motion
 to
 Strike
 which
 would
 have
 provided
 the
answering
 party
 a
 chance
 to
 remedy
 the
 defect,
 the
 Board
 is
reluctant
 to,
 and
 shall not~role that the
 answers
 be
 deemed
 as
not having been filed.
in regards
 to
 the
 operatinq
 nermit
 charge,
 the
 record reveals
that Walter Deemie
 admitted.
 that
 h~
 n;~ned (R.
 31)
,
 and operated
the site in question without
 the requisite operating permit
 (R.
32).
 These admissions are sufficient to support a finding of
violation.
 Insofar as Dean Penn
 is concerned,
 the record
establishes that he no longer owns
 the
 site
 in
auestion
 ~R. 21),
nor was he the owner durinq the time frame of the Complaint
 (Ag.
Exh.
 #27).
 In addition to
 this,
 there was no evidence
 to support
a finding that he was an operator of the site.
 In view of the
foregoing,
 the Board must dismiss the entire Complaint as
 to
this Respondent.
The evidence
 in regards
 to the seventeen daily cover charges
is insufficient
 to support a finding of violations with two ex-
ceptions.
 In order to prove
 a violation of the daily cover re-
quirement,
 it
 is necessary to establish that such cover was not
 applied at the end of the working day.
 This fact can be established
by either
 vi
 si t inq the s~te
 ~i
t
 thc’
 ‘nd
 oI
 the
 (~Z1~S
 operation and
findinq
 that. the requisite cover was nob applied, or by visiting
the site on two d~itcrentdays and findinq
 the same refuse uncovered.
EPA v.
 Waukegan, PCB 71-298,
 3
PCB 301,
 305
 (1971).
 With the ex-
ception of the March
 9,
 1976,
 and the April
 15,
 1976,
 charges,
neither the testimony nor exhibits establish that this procedure
was followed.
 Upon inspecting Agency Exhibits
 24,
 25, and 26,
there can be no doubt that the requisite daily cover was not applied
to the refuse shown therein, and that
 such
 refuse remained uncovered
for nearly two months.
In regards
 to the single open burning charge,
 the
board finds
the
 Agency’s
 evidence
 insufficient
 to
 support
 the
 finding
 of
violation.
 While
 Agency
 testimony
 establishes
 that
 there
 was
 a
2631~~
~ 7
 -~~
/~
—3—
fire at the site
 (R.
 52), the Board does not believe that a
witness’s mere positive response
 to counsel’s question whether
there was
 a fire on the site is sufficient to support a finding
of violation.
 EPA v.
 C.
 M.
 Ford, PCB 72-230,
 6 PCB 165,
 167
 (1972).
Considerable amplification
 is necessary.
 Even if this testimony
were to be considered sufficient to support a finding of violation,
it would still be insufficient to support the imposition of any
penalty for such violation.
 This charge will therefore be dis-
missed.
In consideration of Section 31(c)
 of the Act, the Board
finds that Respondent failed to prove that compliance with the
Board’s regulations would have imposed an arbitrary or unreasonable
hardship.
in dete~rminationof the appropriate remedy for the violations
set forth herein, the Board,
 after consideration of the factors
included in Section
 33 of the Act,
 and the facts
 of this case,
concludes that the technical practicability and economic reasonable-
ness of complying with the regulations as well
 as the economic
value
 of
 the
 pollution source,
 and the priority of location, werq
never
 raised
 as
 issues
 in
 this case.
 While the Board recognizes
the desirability of filling up an abandoned
 sand
 pit that is lo-
cated in a residential area,
 that fact alone does not excuse the
continued,
 longstanding
 violations of
 our
 regulations
 and
 of
 the
Act
 as
 exist
 in this case.
Lastly,
 the Board notes that although no serious environmental
harm has been proven,
 the Board believes
 that a penalty
 is nonethe-
less required.
 If the Board were
 to impose substantial penalties
only if serious harm has been proven,
 the independent significance
of the permit system and our regulations
 is lost, and a return to the
common law nuisance conceots may as well occur.
 The Board has con-
sistently
 stated that the permit
 system
 is
 the
 cornerstone
 of
 the
Act
 and
 that
 whenever
 necessary,
 the
 Board
 should
 use
 its
 penalty
power
 as
 an
 economic
 incentive for compliance with the
 permit
 re-
quirements.
 In view of this belief, and the longstanding violation
found herein,
 the Board will assess
 a penalty of $3,000.00
 for the
violation
 of
 Rule
 202(h)
 (1)
 and
 Section
 21(e)
 of
 the
 Act,
 and
 a
penalty
 of
 $500.flfl
 For
 the violation of
 Rule
 305(a)
 and
 Section
21(b)
 of
 the
 Act.
 The
 Board will further
 require
 Respondent
 to
properly
 close
 the
 site
 or obtain a permit from the Agency.
This
 Opinion
 constitutes
 the
 Board’s
 findings
 of
 fact
 and
conclusions of law in this matter.
ORDER
1.
 Respondent,
 Walter
 Deemie,
 is
 found
 to
 have
 operated
 a
solid
 waste
 management
 site
 from
 July
 27,
 1974,
 until
 May
 10,
 1976,
26319
in violation of Rule 202 (b) (I) of our Solid Waste Rules and
Section 21(e)
 of the Act and shall pay a
 penalty of $3,000.00
for such violations;
 further he is found
 to have violated
 Rule
 305(a)
 of our Solid Waste
Rules
 and Section
 21(b)
 of the
 Act
on March
 9,
 1976,
 and April
 15,
 1976, and shall pay
 a penalty
of
 $500.00 for these violatiocs.
 Penalty payment by certified
check
 or money order payable
 to the State of Illinois shall
 be
made within
 35 days of the date of this Order to:
 Fiscal
Services Division,
 Illinois Environmental Protection Agency,
2200
 Churchill Road,
 Springfield,
 Illinois,
 62706.
2.
 Those portions of the Complaint involving the single
open burning charge as well
 as the remainder of the daily cover
charges
 for which violations were not found
 to exist are hereby
dismissed.
3.
 The Complaint,
 as
 it concerns Respondent Dean Penn,
 is
hereby dismissed.
4.
 Respondent shall apply
 final cover within 90 days of
the adoption of this Order unless he has obtained the requisite
operating permit frem the Agency~
IT
 IS SO ORDERED
Mr.
 Jacob Dumelle dissents
I,
 Christan
 L, Moffett, Clerk of the Illinois
 Pollution Con-
trol Board,~herebycertify the
 a ove Opinion and Order were ado ted
on the
J~
 day of
 ~
 1977
 by a vote of
Illinois Pollution
 Board