1. ILLINOIS POLLUTION CONTROL BOARD
      2. September 21, 1978
      3. Petitioner,

ILLINOIS POLLUTION CONTROL BOARD
September 21,
1978
INTERNATIONAL
HARVESTER
COMPANY,
)
Petitioner,
v.
)
PCB
78—91
)
ENVIRONMENTAL
PROTECTION AGENCY,
)
Respondent.
OPINION
AND
ORDER OF THE
BOARD
(by Mr. Goodman):
International Harvester Company
(Harvester)
filed a
Petition for Variance before the Board on March
24,
1978,
and
filed an Amendment to its Petition on April 25,
1978.
The
Environmental Protection Agency
(Agency)
submitted an Amended
Recommendation on August
21, 1978.
A hearing was held in this
matter on August 22,
1978,
in Rock Island,
Illinois; no citizen
witnesses testified.
The subject of this Petition is Harvester’s Farmall Plant,
a facility located in Rock Island used to manufacture farm
tractors and tractor parts.
Specifically, Harvester seeks a
variance from the particulate emission standards of Rule 203(g)
(1) (B) of the Board’s Air Pollution Regulations
(Chapter
2)
for
three inulticlone-controlled coal-fired boilers
(designated *1,
#2 and #4) which are used to produce heat and process steam.
Stack tests performed on the boilers in question in 1977
revealed the following results:
Allowable Emissions
Boiler
Actual Emissions
Rule
20 3(g) (1) (B)
#1
.440 lbs./MBTU
.213 lbs./MBTU
#2
.524 lbs./MBTtJ
.172 lbs./MBTU
#3
.328 lbs./MBTU
.195 lbs./MBTU
In its Amended Recommendation,
the Agency indicates that
Harvester’s facility is located in a designated non-attainment
area for total suspended particulates.
The particulate monitor
closest to the facility had annual readings
(geometric mean)
in 1976 of 70 ug/m3 and in 1977 of 74 ug/m3.
The Agency
estimated that total particulate emissions from the three
boilers in 1977 exceeded allowable emissions by 87.7 tons.
In
the Agency’s opinion, emissions of such magnitude are in part
responsible for continuing ambient air quality violations
in the
area.
31—485

—2—
Mechanical preciptators were installed on each of the boilers
in question in 1966.
However, stack tests performed in 1977
revealed the above—described levels of emissions.
Harvester
has, therefore, proposed to install
dry
scrubber control equip-
ment to control particulate emissions from the boilers.
The
manufacturer of the proposed equipment has guaranteed that the
equipment will have an efficiency of at least 85.
Such
efficiency will bring all boilers into compliance.
During
construction of the
dry
scrubber system, Harvester will minimize
the use of boiler #2.
The Agency agrees
that,
although the
proposed system represents new technology in Illinois, it should
bring Harvester’s boilers
into compliance.
Harvester was granted an operating permit for its boilers
in 1973 and was not aware that particulate emissions from its
boilers were exceeding the allowable limits until January of
1978 when it received the stack test results described previous-
ly.
Its application for a new operating permit was denied by
the Agency in March of 1978 at which time it petitioned for a
variance.
The Board finds that Harvester’s agreement to minimize use
of boiler #2 will help protect the environment during the period
of the variance and that the proposed dry scrubber system will
bring the boilers into compliance.
The estimated cost of the
proposed system is $4,000,000.
We find that denial of the
requested variance would result in an arbitrary and unreasonable
hardship.
The Board will grant the variance until July 1,
1979,
the latest date
to which the Federal Clean Air Act allows
variances to be granted.
The Board will also require that
Harvester execute a $10,000 performance bond to assure timely
compliance, perform stack tests upon completion of its compliance
progran~~nd adhere to other conditions detailed in the Order below.
This Opinion constitutes the findings of fact and conclu-
sions of law of the Board in this matter.
31—486

—3—
ORDER
It is the Order of the Pollution Control Board that
International
Harvester
Co.
be
granted
a
variance
from
Rule
203(g)
(1)
(B)
of
the
Air
Pollution
Regulations
until
July
1,
1979, subject to the following conditions:
1.
Harvester shall adhere to the Compliance Schedule
attached as exhibit A to its amended petition, which is
incorporated by reference as if fully set forth herein;
2.
Until compliance is fully achieved, Harvester shall
use boiler #4 on a priority basis and shall not use
boiler
#2 unless necessary;
3.
Until compliance is
fully achieved,
the ash content
of the coal burned in the boilers shall not exceed 10;
4.
Harvester shall apply to the Agency for all
necessary construction permits by September 15,
1978;
5.
Within
35 days of the date of this Order, Harvester
shall execute a performance bond of $10,000 in a form
acceptable to the Agency.
Said bond shall be submitted
to the Agency at the following address:
Environmental Protection Agency
Division of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield,
Illinois
62706
6.
Within
35 days of the date of this Order and
on a quarterly basis thereafter,
Harvester shall
submit written reports to the Agency detailing
all progress made toward compliance with Rule 203
(g) (1) (B)
of Chapter
2 as well as an analysis of
all coal consumed.
Said reports shall be submitted
to the Agency at the address specified in paragraph
5 above;
7.
Within
35 days of the completion of the dry
scrubber system, Harvester shall have stack tests
conducted by an independent company.
Harvester
shall
notify
the
Agency
in
writing
at
least
seven
days prior to the testing, and shall allow Agency
representatives to witness the testing and to analyze
all test results.
Notification shall be made to
the address specified in paragraph
5 above; and
31—487

—4—
8.
Within
45
days
of
the
adoption
of
the
Order,
the
International Harvester Company shall execute and
forward to the add~esslisted in paragraph
5 above a
Certification of Acceptance and Agreement to be bound
to all terms and conditions of this Order.
The 45 day
period shall be
held
in
abeyance
during any period
this matter is being appealed.
The form of said
certification shall be as follows:
CERTIFICATION
I,
(We),
_____________________,
having read and fully
understanding the Order of the Illinois Pollution Control
Board in PCB 78-91, hereby accept said Order and agree to be
bound by all of the terms and conditions thereof.
SIGNED_________________________
TITLE_________________________
DATE__________________________
I, Christan L. Moffett,
Clerk of the Illinois Pollution
Control Board, hereby certify the above Opinion and Order were
adopted on the
~/
‘~
~
day of
_______________,
1978 by a vote
Christan L. Moff4~) Clerk
Illinois Pollution Control Board

Back to top