ILLINOIS POLLUTION CONTROL BOARD
August 3,~1978
COMMONWEALTH EDISON COMPANY,
)
Petitioner,
V.
)
PCB 77—201
ENVIRON~NTALPROTECTION AGENCY,
Respondent.
DISSENTING OPINION
(by Mr. Dumelle):
My reason for dissenting in the grant of this variance
is rooted
in the feeling that the situation Edison finds
itself
in is
largely self-imposed.
The applicable sulfur dioxide emission air regulation
was first enacted on April
14,
1972.
Compliance was to be
accomplished by May 31,
1975.
The Board,
in granting PCB 74—16
on January
3,
1975, gave
Powerton more time
to develop coal gasification.
But six
weeks later coal gasification was found to be too costly and
dropped by Edison
(see PCB 75—100 filed February 18,
1975)
The time when coal gasification was to be on line
for
Powerton Unit
5 was May, 1980 or five full years after the
original compliance date.
On December
24,
1975, Edison executed a “compliance plan’
for Powerton with the Illinois Environmental Protection Agency.
This “plan” provided for a single scrubber to be installed and
operative on half
(one boiler)
of either Powerton Unit
5 or
6
by January
1,
1980.
And scrubbers for all other boilers
(three)
would come on line by July
1,
1983.
I can find no authority for the execution of the “compli-
ance plan” with Edison by the Agency.
The most distant date
granted by the Board in PCB 74-16 was May,
1980.
The dates
running into July,
1983 simply were beyond any authority of
the Agency to negotiate.
Variances are granted by the Board,
not by the Agency.
Therefore, Edison cannot claim reliance upon the “com-
pliance plan” entered into with the AgenCy.
And thus the
31—167
—2—
delays encountered at Powerton are self—imposed because
Edison certainly knew the legal division of powers between
Board and Agency.
Powerton has now gone three different routes toward
meeting the Board’s regulation.
First was coal gasifica-
tion by May,
1980.
This vanished when costs inexplicably
rose 336 percent in one year.
(See PCB 75—100 petition,
pp.
9—10.)
Second came a four-scrubber program by July,
1983.
Last, we have a single scrubber and low sulfur coal
by July,
1979.
The decision here by Edison to burn low sulfur coal
as against spending large amounts of capital on scrubbers
or gasification equipment may be a corporate decision
occasioned by the ease of “passing through” fuel adjustment
costs to customers compared to the difficulty of raising
capital by bond or stock issues.
If this is true,
then
Illinois coal may never be burned at Powerton in great
quantities unless Section 125 of the Clean Air can be in-
voked by the Governor and the President.
Had Edison used its time well since the beginning of
1974 it would not have been before us
in this proceeding.
The 66 months from January 1974 until July 1979 were ample
to bring on line scrubbers at Powerton to continue using
Illinois coal.
Respectfully submitted,
Jacob D. Dumelle
I, Christan L. Moffett, Clerk of the Board, do hereby certify
that the above Dissenting Opinion was
filed this
(7~~
day of________
1978.
Christan L. ~
Clerk
Pollution Control Board
31—168